005. 5.27.2026_SOW_Datacenter_re-cable_project_DRAFT.docx
DOCX document 165 KB Posted
- Attached to
- Installation of Dedicated 120VAC and 240VAC Receptacles for Data Center Re-cabling Project
- Solicitation number
- 26WA161706
About this file
This is a Statement of Work (SOW) for the Installation of Dedicated 120VAC and 240VAC Receptacles for Data Center Re-cabling Project at the Western Area Power Administration (WAPA) Desert Southwest Region Phoenix Campus, located at 615 S 43rd Ave, Phoenix, AZ 85009. The contractor shall furnish and install a code-compliant underfloor electrical gutter system (16-gauge steel with removable hinge covers) beneath the raised data center subfloor to route power conductors and support deployment of a new Supervisory Control and Data Acquisition (SCADA) system. The scope requires installation of eight (8) 240VAC, 20-amp receptacles utilizing NEMA L6-20R locking-type connectors and eight (8) 120VAC, 20-amp receptacles utilizing NEMA 5-20R connectors, each supplied by individual dedicated 20-amp circuit breakers with no circuit sharing. All circuits shall be distributed between independent A-side and B-side power sources to provide redundant power feeds. Each designated data center cabinet shall receive one receptacle of each type (240VAC and 120VAC) connected to both A-side and B-side power sources. Work must be performed Monday through Friday between 7:00 a.m. and 3:00 p.m., excluding federal holidays, with a WAPA representative present on-site at all times. The contractor must conduct a pre-construction site visit, complete all pre-construction activities including measurements and sketches, and comply with the National Electrical Code (NEC) and all applicable federal, state, and local requirements. Contact information includes COR Timothy Hurst at 602-605-2726 or hurst@wapa.gov, with Michael Burgess (burges@wapa.gov) as backup. All contractor employees must be U.S. citizens with current Travel ID or passport, with worker names submitted 48 hours in advance for security clearance. Deliverables include complete installation of receptacles and dedicated circuits, updated panel schedules, circuit and receptacle labeling, electrical testing and commissioning results, and as-built documentation if requested. The contractor is responsible for all labor, materials, equipment, supervision, testing, permits if required, waste removal, equipment storage coordination, damage restoration, and warranties on all equipment and workmanship. Safety compliance with OSHA regulations (29 CFR 1904, 1910, 1925, and 1926) is mandatory, including preparation of a Job Hazard Analysis (JHA) and site-specific safety plan for review and approval before work commences.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Installation of Dedicated 120VAC and 240VAC Receptacles for Data Center Re-cabling Project
FOR
WESTERN AREA POWER ADMINISTRATION
DESERT SOUTHWEST REGION
PHOENIX CAMPUS
MAY 27 2026
CONTENTS
A. INTRODUCTION/OBJECTIVE
B. REQUIREMENTS
C. DELIVERABLES
D. QUALITY ASSURANCE
E. ACCESS AND RESTRICTIONS
F. UTILITIES
G. SAFETY
H. EXHIBITS
A. INTRODUCTION/OBJECTIVE
1. The purpose of this project is to install an underfloor electrical gutter system within the Western Area Power Administration (WAPA) Data Center to support the deployment of the new Supervisory Control and Data Acquisition (SCADA) system. The gutter system will provide a dedicated, organized, and protected pathway beneath the raised floor for routing power conductors and associated electrical infrastructure required for SCADA equipment operation.
The objective is to furnish and install a code-compliant underfloor gutter system capable of distributing both 120 VAC and 240 VAC branch circuits from designated electrical panels to strategically located receptacles serving the new SCADA equipment racks, workstations, and supporting devices.
2. To ensure the best results the contractor shall at a minimum, conduct one on-site visit to WAPA’s DSW Phoenix facility prior to commencement of any work. It is the contractor’s responsibility to have a complete technical and visual understanding of the project requirements. The Contractor must also complete all other appropriate pre-construction activities such as, ensuring the proposed activity conforms to all applicable building codes, taking all appropriate measurements, making all appropriate sketches of the proposed project and site layout/conditions; and taking notice of all relevant requirements/considerations. If required, the Contractor may request additional information from the COR/PM.
3. The Contractor is to contact DSW federal employee Timothy Hurst (COR) at 602-605-2726 or hurst@wapa.gov and including Michael Burgess burges@wapa.gov as back up COR designated duties are to verify that the site is ready for the performance of work as set forth in this SOW, to coordinate arrival time to allow a WAPA representative to meet and escort the contractor while on DSW property. The contractor is not permitted to work on-site without the presence of a WAPA representative. Work must be performed Monday through Friday between the hours of 7:00am – 3:00pm. Excluding all Federal Holidays. Work performed outside of these hours must be coordinated and approved 48 hours in advance by the COR.
B. REQUIREMENTS
Installation of Dedicated 120VAC and 240VAC Receptacles for Data Center Re-cabling Project
1. Purpose
The Contractor shall provide all labor, materials, equipment, supervision, testing, permits (if required), and documentation necessary to install dedicated electrical receptacles and circuits within the WAPA Data Center.
2. General Information
· Location: Datacenter
· Electrical Panel: COL-B COL-A
· Approximate distance: See Exhibit A
· Gutter Construction: 16 Gauge steel covers and body
· Gutter features: Open top assembly, removable hinge covers, with knock outs.
3. Scope of Work The contractor shall provide all labor and materials necessary to complete the following work:
A. 240VAC Receptacles Furnish and install a total of eight (8) 240VAC, 20-amp receptacles utilizing NEMA L6-20R locking-type connectors.
Each receptacle shall be supplied by an individual dedicated 20-amp circuit breaker.
No receptacle shall share a circuit with another receptacle.
Circuits shall be distributed between independent A-side and B-side power sources to provide redundant power feeds.
B. 120VAC Receptacles Furnish and install a total of eight (8) 120VAC, 20-amp receptacles utilizing NEMA 5-20R receptacles.
Each receptacle shall be supplied by an individual dedicated 20-amp circuit breaker.
No receptacle shall share a circuit with another receptacle.
Circuits shall be distributed between independent A-side and B-side power sources to provide redundant power feeds.
4. Cabinet Power Configuration Each designated data center cabinet shall receive redundant electrical service as follows:
One (1) 240VAC NEMA L6-20R receptacle connected to the A-side power source.
One (1) 240VAC NEMA L6-20R receptacle connected to the B-side power source.
One (1) 120VAC NEMA 5-20R receptacle connected to the A-side power source.
One (1) 120VAC NEMA 5-20R receptacle connected to the B-side power source.
This configuration shall be repeated for all designated cabinets identified by WAPA as part of the Data Center Re-cabling Project.
5. Installation Requirements The Contractor shall:
Perform all work in accordance with the latest edition of the National Electrical Code (NEC) and all applicable federal, state, and local requirements.
Furnish and install an approved electrical gutter/raceway system beneath the raised data center subfloor for routing all conductors associated with the new 120VAC and 240VAC receptacles. The gutter system shall provide a protected and organized pathway for running the appropriate branch-circuit wiring from the electrical panels to each designated receptacle location. The Contractor shall size all conductors in accordance with the National Electrical Code (NEC), install dedicated wiring for each circuit. A-side and B-side circuits shall be routed separately within the underfloor distribution system whenever practical to maintain power redundancy and minimize the potential for a single point of failure. All wiring shall be properly supported, identified, labeled, and installed in a neat and professional manner that maintains data center airflow, allows future maintenance and expansion, and does not interfere with existing SCADA, communications, network, or facility infrastructure. Upon completion, the Contractor shall ensure all receptacles are operational, properly connected to their respective dedicated breakers, and clearly identified by cabinet designation and power source (A-side or B-side).
6. Testing and Commissioning Upon completion, the Contractor shall:
Verify voltage, grounding, polarity, and circuit continuity.
Test each receptacle for proper operation.
Confirm proper assignment of A-side and B-side power sources.
Update panel schedules to reflect new circuit installations.
Provide testing documentation to WAPA.
C. DELIVERABLES
The Contractor shall provide:
Complete installation of all specified receptacles and dedicated circuits.
Updated panel schedules.
Circuit and receptacle labeling.
Electrical testing and commissioning results.
As-built documentation reflecting final installation, if requested by WAPA.
D. QUALITY ASSURANCE
1. The Contractor retains the sole responsibility for delivering, receiving, storing, and providing all equipment, tools and supplies needed for this work to include any equipment required to move items while onsite. No items will be stored on WAPA property before or during work unless approved by the COR.
2. The Contractor must coordinate all deliveries with the PM/COR a minimum of 48 hours before scheduled delivery.
3. The Contractor will take all measures to protect existing equipment and facilities onsite from damage. Damage caused by the Contractor to grounds, facilities and finishes will be returned to original condition by the Contractor.
4. The Contractor shall maintain service of existing systems to the maximum extent possible and coordinate interruptions of any utility services in advance with the PM/COR.
5. The Contractor shall provide warranties on all equipment, materials, and workmanship.
6. All waste, debris, and trash created by the Contractor during this project will be removed by the Contractor from the property and disposed of properly in accordance with all applicable codes and regulations.
E. ACCESS AND RESTRICTIONS
1. WAPA’s address is 615 S 43rd Ave, Phoenix AZ 85009. Normal hours are Monday through Friday from 7:00am to 3:00pm. Excluding all Federal Holidays. Coordinate with the COR to work outside the normal work hours 48 hours in advance. The Contractor cannot work on-site without a WAPA representative present. All Contractor’s employees shall be US Citizens and hold a current Travel ID and or Passport. Names of all workers must be submitted to the COR 48 hours in advance for security requirements.
F. UTILITIES
1. Electric Power for Construction Purposes: Electric power is available for construction purposes and will be available without cost. Source of supply is receptacles located in the facility. Power made available by WAPA will be delivered as single phase 60Hz, at approximately 120-V. If the Contractor requires any other voltage or location, he must provide his own power source.
2. Water for Construction Purposes: Non-potable water is available to the Contractor as necessary for the performance of the work. The contractor shall provide his own drinking (potable) water.
G. SAFETY
1. The Contractor shall comply with all applicable Federal, State, and local safety and health, and environmental laws, regulations, codes, and standards when performing work under this Statement of Work (SOW). This includes adherence to Occupational Safety and Health Administration (OSHA) regulations found in 29 CFR 1904, 29 CFR 1910, 29 CFR 1925, and 29 CFR 1926, as applicable. In cases of conflict, the most stringent requirements shall govern. The United States' liability is limited to negligence by its employees, in accordance with the Federal Tort Claims Act.
2. The Contractor is solely responsible for developing, implementing, and maintaining a safety and health program that protects its employees, government personnel, government property, and the public from injury or damage caused by contract operations. The program must address all applicable regulatory requirements and supporting compliance documents must be readily available to the WAPA representative at all times. The Contractor shall ensure all its personnel are trained, qualified, and medically capable of safely performing their assigned work.
3. For contract work involving hazardous operations or complex activities with elevated risk, the Contractor shall prepare and submit a Job Hazard Analysis (JHA) and a site-specific safety plan to the Contracting Officer and the designated WAPA representative for review and approval before starting such work. The JHA must identify hazards associated with work activities and establish corresponding hazard control measures.
4. The Contractor shall coordinate with the WAPA representative and WAPA Safety representatives prior to conducting operations requiring the implementation OSHA-mandated programs, including, but not limited to permit-required confined space entry, control of hazardous energy (lockout/tagout), hot work, fall protection, and hazard communication (use of hazardous chemicals on site), and excavations and trenching operation. The contractor's site-specific safety plan and applicable job hazard analyses must address these programs in detail where relevant to the scope of work.
5. Prior to commencing work, an on-site safety meeting will be conducted with the designated WAPA representative to review work activities, hazards, and mitigation methods. The Contractor shall also conduct periodic safety meetings with its employees to address site-specific hazards.
6. The Contractor shall immediately correct any unsafe conditions identified during the performance of work. WAPA reserves the right to stop work and/or remove Contractor employee(s) from the worksite whose actions or failure to comply with safety requirements pose a risk to personnel, property, or the public.