00410 Bid Form for General Const Contract.pdf

PDF 187 KB Posted

Attached to
Wetmore Run Well Development
Solicitation number
Not on record
Issued by
Potter County, Pennsylvania

About this file

This is a bid form for a general and mechanical construction contract issued by the Galeton Borough Authority for the Wetmore Run Well Development project located in Galeton, Pennsylvania. The project involves bringing two pre-drilled and cased water wells online, installing interconnecting piping from the wells to existing treatment facilities, providing new electrical power service entrances and emergency generators, upgrading existing treatment facilities, and connecting to the existing municipal potable water distribution system. Bids for Contract 2026-W1 (General/Mechanical), along with two companion contracts (2026-W2 for Waterline Replacement and 2026-W3 for Electrical/Controls/Instrumentation), are due by 2:00 PM local time on Tuesday, July 28, 2026, with public bid opening scheduled for 2:05 PM the same day at 24 West Main Street, Galeton, PA 16922. A non-mandatory pre-bid conference is scheduled for Tuesday, July 7, 2026 at 2:00 PM at the same location. Bidding documents are available electronically at no cost through www.PennBid.net or may be purchased for $250 (non-refundable) from Century Engineering, a Kleinfelder Company at 330 Innovation Blvd, Suite 305, State College, PA 16803. Prospective bidders may examine documents at no cost at the issuing office Monday through Thursday from 8:00 AM to 5:00 PM or Friday from 8:00 AM to Noon.

The bid is structured on a lump sum basis and will remain subject to acceptance for sixty days after bid opening, or up to one hundred twenty days if award is delayed by required government approvals, bond sales, or grant awards. Bidders must acknowledge compliance with Pennsylvania Department of Labor regulations regarding unemployment compensation, commonwealth labor laws, and workers' compensation, and must remain compliant throughout the contract and warranty period. All awarded bidders will be required to pay either the PennBid minimum fee or the required percentage-based fee up to the maximum amount in accordance with PennBid Terms and Conditions. The bid form requires bidders to certify that they have examined all bidding documents, visited and thoroughly examined the site, are familiar with applicable laws and regulations including American Iron and Steel requirements, and that their bid price includes all costs associated with the work as specified.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Galeton Borough Authority Wetmore Run Well Development

2026-W1, 2026-W2 & 2026-W3

CEI File No. 25001215.056B 00410-1 BID FORM FOR CONSTRUCTION CONTRACTS

SECTION 00410

BID FORM FOR CONSTRUCTION CONTRACT

CONTRACT #2026-W1: GENERAL / MECHANICAL

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: Galeton Borough Authority, 24 West Main Street, Galeton, PA 16922.

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents and all issued addendums.

ARTICLE 2—ATTACHMENTS TO THIS BID

CEI File No. 25001215.056B 00410-2 BID FORM FOR CONSTRUCTION CONTRACTS

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Lump Sum Bids

3.02 Unit Price Bids – Not Used

ARTICLE 4—NOT USED

ARTICLE 5— NOT USED

ARTICLE 6—TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

CEI File No. 25001215.056B 00410-3 BID FORM FOR CONSTRUCTION CONTRACTS

ARTICLE 7—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

7.01 Bid Acceptance Period

A. The Bid will remain subject to acceptance for sixty (60) days after the Bid opening, except if the award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant, the Owner shall reject all bids or award the contract to the lowest responsible and responsive bidder within one hundred twenty (120) days of the bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

7.02 Instructions to Bidders

A. Bidder accepts terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

7.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda: [Add rows as needed.

Bidder is to complete table.]

Addendum Number Addendum Date

7.04 Bidder hereby acknowledges if awarded a contract, whether or not their bid was placed via PennBid or via hard copy bid to Owner, that the awarded bidder will pay PennBid either the PennBid minimum fee or else the PennBid required amount based on the PennBid percentage up to the maximum amount in accordance with the PennBid Terms and Conditions.

BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

7.05 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda, the Invitation for Bids, Signature Documents, the form of Bid, the form of Bid Bond, the form of Contract, the Non-Collusion Affidavit, the form of Surety Bond or Bonds, the Contract Conditions, any Federal Requirements, any State Requirements, Specifications, the other related data identified in the Bidding Documents.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work and including all American Iron and Steel requirements.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been

CEI File No. 25001215.056B 00410-4 BID FORM FOR CONSTRUCTION CONTRACTS identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site;

information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and (c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

7.06 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

CEI File No. 25001215.056B 00410-5 BID FORM FOR CONSTRUCTION CONTRACTS

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

5. Bidder acknowledges that that they are compliant with, and will remain compliant with the Pennsylvania Department of Labor Unemployment Compensation regulations and are not listed as non-compliant on the Non- Compliance list located at https://www.dli.pa.gov/Documents/Non- Compliance-Lists/UC-Non-Compliance-List.pdf and will immediately notify the Project Owner if they should become non-compliant during the duration of the contract and warranty period.

6. Bidder acknowledges that that they are compliant with, and will remain compliant with the Pennsylvania Department of Labor regulations regarding commonwealth's labor laws and have met their legal obligation such as paying owed back wages, or fines and fees to the department and are not listed as non-compliant on the Non-Compliance list located at https://www.dli.pa.gov/Documents/Non-Compliance-Lists/BLLC-Non- Compliance-List.pdf and will immediately notify the Project Owner if they should become non-compliant during the duration of the contract and warranty period.

7. Bidder acknowledges that that they are compliant with, and will remain compliant with the Pennsylvania Department of Labor regulations regarding Worker’s Compensation and are not listed as non-compliant on the Non- Compliance list located at https://www.dli.pa.gov/Documents/Non- Compliance-Lists/BWC-Non-Compliance-List.pdf and will immediately notify the Project Owner if they should become non-compliant during the duration of the contract and warranty period.

8. If applicable laws and regulations require inspection of the work by the Pennsylvania Department of Transportation, Pennsylvania Turnpike Commission, or similar public agency, the CONTRACTOR shall be responsible for coordinating the performance of the Work with inspectors employed by or for the public agency. The expense of these inspections shall be borne by the CONTRACTOR.

In the event the public agency requires payment for this inspection from the OWNER, the OWNER shall deduct the amount due and payable for such services from compensation otherwise due the CONTRACTOR. It is expressly understood, by and between the CONTRACTOR and the OWNER, that the cost for such public agency inspection has been included within the price bid for such portions of the Work as are affected by this public agency inspection.

9. Bidder will submit written evidence of its authority to do business in the state where the Project is located not later than the date of its execution of the Agreement.

CEI File No. 25001215.056B 00410-6 BID FORM FOR CONSTRUCTION CONTRACTS

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization) By:

(individual’s signature) Name:

(typed or printed) Title:

(typed or printed) Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed) Title:

(typed or printed) Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

File details come from the government source that posted it. Updated .