00111 _ Advertisement for Bids (Updated 03_27.pdf

PDF 141 KB Posted

Attached to
FY 2025 LMIG for Roadway Resurfacing
Solicitation number
PE-63700-NONST-2025-000000007
Issued by
Crawford County, Georgia

About this file

This is an Advertisement for Bids issued by the Cook County Board of Commissioners in Adel, Georgia for FY 2025 LMIG Roadway Resurfacing project. The project involves resurfacing approximately 3.34 miles of roadway and associated measures, with sealed bids due by 11:00 AM on January 22, 2025 at 1200 South Hutchinson Avenue, Adel, GA 31620. The work must be completed within 120 consecutive calendar days to substantial completion and 150 consecutive calendar days for final contract close-out. Bidders must be GDOT Prequalified Contractors and include their license numbers on bid envelopes.

The project will be funded through Local Special Purpose Local Option Sales Tax (SPLOST) and/or Local Maintenance & Improvement Grant (LMIG). Bidders must submit a Bid Bond or certified cashier's check for 10% of the bid amount, and the winning bidder must provide Performance and Payment Bonds for 100% of the contract amount. Bidding documents can be obtained from Watkins & Associates, LLC for $300 (non-refundable). All contractors and subcontractors must participate in E-Verify and submit a Georgia Security and Immigration Compliance Act Affidavit. The owner reserves the right to reject any or all bids and waive informalities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Advertisement for Bids Section 00111

Cook County Board of Commissioners W&A Project No.: W0315-003-01 FY 2025 LMIG for Roadway Resurfacing 01200-1

COOK COUNTY BOARD OF COMMISSIONERS

ADEL, GEORGIA

FY 2025 LMIG FOR ROADWAY RESURFACING

ADVERTISEMENT FOR BIDS

PART 1 GENERAL

1.01. COMPETITIVE COST SEALED BIDS

Sealed Bids for the construction of the FY 2025 LMIG for Roadway Resurfacing will be received, by Cook County Board of Commissioners, at 1200 South Hutchinson Avenue, Adel, GA 31620, until 11:00 AM, Wednesday, January 22, 2025, local time, at which time the Bids received will be publicly opened and read. No bid may be withdrawn after the closing time for receipt of bids for a period of sixty (60) days.

1.02. CONTRACTOR LICENSE

Any Contractor submitting a bid must be a GDOT Prequalified Contractor. License numbers must be written on the face of the bid envelope. No bid will be opened unless the license number is clearly shown. See Instructions to Bidders for additional bidding requirements.

1.03. SCOPE OF WORK

The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed FY 2025 LMIG for Roadway Resurfacing as shown on the construction drawings. In general, construction consists of resurfacing approximately 3.34 miles of roadway and all associated measures for the complete project.

Time allotted for completion of work is 120 consecutive calendar days to substantial completion. Work shall be complete and ready for contract close-out with 150 consecutive calendar days. All work shall be completed in accordance with the plans and specifications.

The work will be awarded in one (1) Contract.

1.04. PLANS AND BIDDING DOCUMENTS

Copies of Bidding Documents for bidding purposes can be obtained from Watkins & Associates, L.L.C., 1606 Whiddon Mill Road, Tifton, Georgia 31793, Phone: (229) 388- 8823, (Office of the Engineer) upon payment of $300.00 for each set (non-refundable).

Prospective Bidders may examine the Bidding Documents at the Cook County Board of Commissioners, located at 1200 South Hutchinson Avenue, Adel, GA 31620 or at Watkins & Associates, LLC on Mondays through Fridays between the hours of 8 A.M. and 5 P.M. Upon request and receipt of the document payment indicated above, Watkins & Associates, LLC will transmit the Bidding Documents via delivery service. The date that the Bidding Documents are transmitted will be considered the prospective Bidder’s date of receipt of the Bidding Documents. Partial sets of Bidding Documents will not be available from the Engineer. Neither Owner nor Engineer will be responsible for full or partial sets of Bidding Documents, including Addenda if any, obtained from sources other than the Office of the Engineer.

FY 2025 LMIG for Roadway Resurfacing 01200-2

1.05. REQUESTS FOR INFORMATION

Plan holders list, addenda and bid results are available at www.watkinseng.com.

1.06. PREQUALIFICATION OF BIDDERS

Prequalification may be required of Bidders prior to the award of contract. At the Owner’s request, detailed written evidence such as financial data, bonding capacity, previous experience, present commitments, and other such data may be necessary to assist Owner in determining Contractor’s qualifications shall be provided per the Instructions to Bidders contained in the contract documents.

1.07. BONDS

All bid forms must be accompanied by a Bid Bond or a certified cashier’s check in an amount not less than ten percent (10%) of the amount bid. All bonds shall be by a surety company licensed in Georgia with “A” minimum rating performance and financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. The successful bidder, if awarded the Contract, will be required to furnish a Performance Bond and Payment Bond, each in the amount of one hundred percent (100%) of the Contract amount. All bonds must appear on the Treasury Department's most current Circular 570 Listing. Each Bond shall be accompanied by a “Power of Attorney” authorizing the attorney-in-fact to bind the surety and certified to include the date of the bond.

1.08. PERMITS

All anticipated federal, state, or local permits required for the project have been applied for and are expected to be approved prior to issuance of the Notice to Proceed.

1.09. GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT AFFIDAVIT

All qualifying Contractors and Subcontractors performing work with the Cook County Board of Commissioners must register and participate in the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, to verify the work eligibility information of new employees. In order for a Bid to be considered, it is mandatory that the Bidder’s Affidavit of Compliance with O.C.G.A. §13-10-91 be completed and submitted with the Bid.

1.10. FUNDING SOURCES

Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the Local Special Purpose Local Option Sales Tax (SPLOST) and/or Local Maintenance & Improvement Grant (LMIG).

1.11. RESERVATION OF RIGHTS

Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, nonresponsive, unbalanced, or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder, whether because the Bid is not responsive or

FY 2025 LMIG for Roadway Resurfacing 01200-3 the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner. Owner reserves the right to waive informalities and to re-advertise.

Owner: Cook County Board of Commissioners By: Randy Lane Title: County Manager Date: December 23, 2024 January 6, 2025 January 20, 2025

END OF SECTION

PART 1 GENERAL
1.01. COMPETITIVE COST SEALED BIDS
1.02. Contractor license
1.03. SCOPE of work
The work to be done shall consist of furnishing all labor, materials and equipment necessary to construct the proposed FY 2025 LMIG for Roadway Resurfacing as shown on the construction drawings. In general, construction consists of resurfacing approx...
1.04. plans and bidding documents
1.05. requests for information
1.06. Prequalification of bidders
1.07. Bonds
1.08. Permits
1.09. georgia security and immigration compliance act affidavit
1.10. funding sources
Any Contract or Contracts awarded under this Advertisement for Bids will be funded by a grant from the Local Special Purpose Local Option Sales Tax (SPLOST) and/or Local Maintenance & Improvement Grant (LMIG).

1.11. reservation of rights

File details come from the government source that posted it. Updated .