001_KISD_South Campus_Bid Pack 1_Demo_CM Manual.pdf
PDF 3 MB Posted
- Solicitation number
- RFP KSD 260000002144 2
- Issued by
- Kent County, Michigan
About this file
This document is a Construction Manager's Project Manual and bid package for the Kent Intermediate School District (KISD) Career Tech - South Campus Bid Package No. 1, a building demolition project located in Caledonia, Michigan. The project is being administered by Owen-Ames-Kimball Co. (O-A-K) as the Construction Manager. The scope of work includes two bid categories: Bid Category No. 1 encompasses complete demolition of the existing building including removal of footings, foundations, ductwork, piping, wiring, equipment, and all associated architectural, structural, and mechanical-electrical-plumbing (MEP) demolition; Bid Category No. 2 covers site-related earthwork including site clearing, grading, excavation, fill, removal of pavements and site structures, and preparation of the site for future work. A mandatory pre-bid conference will be held on Tuesday, May 19, 2026, at 3820 68th Street SE, Caledonia, Michigan, at 10:00 a.m. Sealed bids in triplicate are due by 2:00 p.m. on Wednesday, June 3, 2026, at O-A-K's Operations Center located at 6645 East Paris Avenue, Caledonia, Michigan. Bids will be opened and read publicly at the same location and time, with virtual attendance available via Zoom. Bidders may submit proposals for one bid category individually or in combination with other categories.
Bid security must accompany each proposal in the form of a certified or cashier's check or bid bond in an amount equal to five percent (5%) of the base bid amount. Qualified bidders must demonstrate at least five years of successful experience on similar work, possess appropriate licensing, and maintain adequate financial resources. Contracts exceeding $50,000 require Performance, Labor, and Material bonds from a surety company with an A- or better rating. The successful bidder must furnish post-bid information within ten days of notification of the Notice of Pending Award, including insurance documentation, cost breakdowns, lists of work to be performed by company forces versus subcontractors, manufacturer and supplier information, and schedule details. Unit labor rates for change orders must include all direct costs without markup. Contractors are responsible for compliance with Owen-Ames-Kimball Co.'s safety requirements, including MIOSHA requirements, silica exposure plans, proper fall protection, and substance abuse policies. The bid documents reference AIA Document A132-2019 as the Standard Form of Agreement between Owner and Contractor. All bidders must complete a sworn and notarized Familial Disclosure Statement in accordance with Michigan Public Act Section 1267 and an Affidavit of Compliance with the Iran Economics Sanctions Act (Michigan Public Act No. 517 of 2012).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KENT INTERMEDIATE SCHOOL DISTRICT
CAREER TECH – SOUTH CAMPUS
BID PACKAGE No. 1
DEMO
CONSTRUCTION MANAGER’S
PROJECT MANUAL
May 15, 2026
Construction Manager:
Owen-Ames-Kimball Co.
126 Ottawa Ave NW, Suite 600
Grand Rapids, MI 49503
616.456.1521
Send RFIs and Substitution Requests to: Jared Gauss at jaredg@oakmi.com
Kent ISD – Caree Tech – South Campus – Bid Pack No. 1
Demo www.owen-ames-kimball.com
Construction Management Project Manual Index
Bidding Requirements
Advertisement for Bids
Instruction to Bidders
Statement of Participation
Certificate of Insurance and Endorsement
Bid Form
Familial Disclosure Statement, Affidavit of Compliance
Safety Data Questionnaire
General Conditions
Specifications
Division 1 - General Requirements
01010 Summary of Work
01020 Allowances
01026 Unit Prices
01030 Schedule of Alternates
01040 Project Coordination
01045 Cutting and Patching of New Work
01050 Field Engineering
01095 Reference Standards and Definitions
01200 Project Meetings
01300 Submittals
01400 Quality Control
01500 Temporary Utilities
01600 Material and Equipment
01650 Starting Systems
Preliminary Construction Schedules
Subcontractor Submittal Form
Referenced Documents Available for Online Viewing
AIA A132 – 2019 – Standard Form of Agreement Between Owner and Contractor:
https://tinyurl.com/2p8pnk2b
Owen-Ames-Kimball Co. Safety Manual:
https://tinyurl.com/34zxyj49
ADVERTISEMENT FOR BIDS
BID PROPOSAL
Sealed bids, in triplicate, for the Kent Intermediate School District – South Campus Bid Pack 1 – Building Demo will be received until 2:00 pm local time, Wednesday, June 3rd, 2026, at O-A-K's Operations Center, 6645 East Paris Ave., Caledonia, MI 49316. Bids received after this time will neither be considered nor accepted.
All proposals received by the time and date stated above will be opened and read publicly at 2:00 pm local time, Wednesday, June 3rd, 2026, at O-A-K's Operations Center, 6645 East Paris Ave., Caledonia, MI 49316. You may attend in person or watch online via:
https://us06web.zoom.us/j/81921516656?pwd=g5BYoHL1I3znRN5hXs4opqH2bXs1uc.1
Passcode if required: 710659
Bids may be mailed to O-A-K's Operations Center, 6645 East Paris Ave., Caledonia, MI 49316. Mailed bids must be received prior to the bid due time and date stated above. FAXED, EMAILED OR UPLOADED TO BUILDING
CONNECTED BIDS WILL NOT BE ACCEPTED.
In accordance with Section 1267 of the Revised School Code each bid must be accompanied by a sworn and notarized Familial Disclosure Statement completed by the bidder disclosing any familial relationship between the
Owner or any employee of the Bidder and any member of the District’s Board of Education or the Superintendent of the District.
SITE INSPECTION
A construction pre-bid meeting will be held on Tuesday, May 19th, 2026
Location: 3820 68th St. SE, Caledonia, MI
Time: 10:00am
All bidders are encouraged to attend.
BID DOCUMENTS
The Bidding Documents may be examined at the following locations:
• Owen-Ames-Kimball Co. Website: http://www.owen-ames-kimball.com/subcontractors/
• Builders Exchange plan rooms in Grand Rapids, Kalamazoo, Lansing and Traverse City.
BIDDER QUALIFICATIONS
Bidders submitting a Bid for this Project shall have qualifications as follows:
a. Shall be a reputable, recognized organization, with at least five (5) years successful experience on work of this type and scope of this project.
b. Shall have a license where required by public authorities having jurisdiction.
c. Shall have ample financial resources for work of this magnitude.
BID SECURITY - PERFORMANCE BONDS
Each bid shall be accompanied by good and sufficient bid security or bid bond in an amount not less than 5% of the
Bid amount and shall secure the Owner from loss or damage by reason of the withdrawal of the Bid by a Bidder or by failure of the successful Bidder to enter into a Contract with the Owner if his Bid is accepted by the Owner.
Bid securities will not be released or returned until the bid “hold-firm” date or a subcontract has been successfully executed for the specific bid category of work, whichever occurs first.
Bid security may be provided by furnishing a bond from a surety company having a rating of A- or better or certified check. Owen-Ames-Kimball is not responsible for the loss of bid security if provided by certified check.
The successful Bidder will be required to secure Performance, Labor and Material bonds for all contracts exceeding
$50,000, from a surety company having a rating of A- or better, for the full amount of the Contract.
Kent ISD – Career Tech – South Campus – Bid Package No. 1 – Demo www.owen-ames-kimball.com
SUPPLEMENT TO INSTRUCTIONS TO BIDDERS
STANDARD AIA FORMS
The Instructions to Bidders (AIA Document A701-2018 Edition), Articles 1 through 8, and as herein amended or added to, are a part of the Contract Documents, and shall apply to all Contractors, and/or Subcontractors.
ARTICLE 1 – DEFINITIONS Add Subparagraph 1.10 as follows:
1.10 All references made to Owner shall be implied to refer to the Construction Manager.
ARTICLE 3 – BIDDING DOCUMENTS
3.1 Distribution Add Subparagraph 3.1.6 as follows:
3.1.6 The Bidding Documents, including drawings, specifications, and necessary forms, can be examined at the following locations.
• Owen-Ames-Kimball Co. website: www.owen-ames-kimball.com/subcontractors/
• Builders Exchange plan rooms in Grand Rapids, Kalamazoo, Lansing, and Traverse City.
3.2 MODIFICATION OR INTERPRETATION OF BIDDING DOCUMENTS Revise Subparagraph 3.2.2. as follows:
Line 2 shall read “…ten days…”
ARTICLE 4 – BIDDING PROCEDURES
4.1 PREPARATION OF BIDS Revise Subparagraph 4.1.1. and Add Subparagraph 4.1.6.1, 4.1.9 and 4.1.10 as follows:
Bids shall be submitted, in triplicate, on the Bid Proposal Form included within the bidding Documents.
4.1.6.1 Proposals will be accepted for one (1) Bid Category only, or a combination of two (2) or more Categories. If the Bidders wish to have their combined bid considered for separate categories, they must submit separate proposals for the individual category along with their combined bid proposal.
4.1.9 A Pre-Bid Conference will be held in accordance with the following schedule:
Date: Tuesday, May 19th, 2026
Place and Time: 3820 68th St. SE, Caledonia, MI 49316 @ 10:00am
4.1.10 In accordance with Section 1267 of the Revised School Code each bid must be accompanied by a sworn and notarized Familial Disclosure Statement completed by the bidder disclosing any familial relationship between the Owner or any employee of the Bidder and any member of the District’s Board of Education or the
Superintendent of the District.
4.2 BID SECURITY Add Subparagraphs 4.2.1.1, 4.2.1.2 and Revise Subparagraph 4.2.3 as follows:
4.2.1.1 Bid security shall be required for each bid tendered.
4.2.1.2 Bid security shall be in the form of either a CERTIFIED or CASHIER’S CHECK on an open and solvent bank or bid bond issued by surety company payable to the Owner in an amount equal to five percent (5%) of the base bid.
4.2.3 Revise Lines 1 and 2 to read “If a surety bond is provided the attorney-in-fact who …”.
4.3 ADDENDA Revise Subparagraph 4.3.3 as follows:
www.owen-ames-kimball.com
4.3.3 Addenda will be issued no later than two days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.
4.4 MODIFICATION OR WITHDRAWAL OF BIDS Revise Subparagraph 4.4.3 as follows:
4.4.3 After the time and date of receipt of Bids, a bid may not be modified, withdrawn or cancelled by the Bidder for sixty (60) days.
ARTICLE 5 – CONSIDERATION OF BIDS
5.3 ACCEPTANCE OF BID (AWARD) Revise Subparagraph 5.3.2 and add Subparagraph 5.3.4 as follows:
5.3.2 Revise Line 1 to read “…right to accept Mandatory and Voluntary Alternates in any order…”
5.3.3 Owner reserves the right determine which bidders are considered the lowest qualified bidder and to award to said bidder.
5.3.4 After the Owner has awarded the Bid Categories the Construction Manager will prepare and send a Notice of
Pending Award to the successful Bidders.
ARTICLE 6 – POST-BID INFORMATION
6.1 CONTRACTOR’S QUALIFICATION STATEMENT Revise Subparagraph 6.1 as follows:
The Owner, Architect and Construction Manager may make such investigations as they deem necessary to determine the ability of the Bidder to perform the work. The Bidder shall furnish all such information and data for this purpose as the Construction Manager may request within twenty-four (24) hours, including, but not limited to, lists of projects completed, financial statements for the past two (2) years, a current list of work in progress. The Owner reserves the right, based on the advice of the Construction Manager and
Architect, to reject any bid if the evidence submitted, or investigation of such Bidder, fails to prove that such
Bidder is properly qualified to carry out the obligations of the contract and to complete the work contemplated therein.
6.3 SUBMITTALS Revise Subparagraph 6.3.1, replace Subparagraphs 6.3.1.1 thru 6.3.1.3 and add
Subparagraphs 6.3.1.4 thru 6.3.1.6 as follows:
6.3.1 The Bidder shall within ten (10) days upon issuance of a Notice of Pending Award furnish to the Owner through the Construction Manager the following:
6.3.1.1 The necessary insurance forms as specified in the Bidding Documents.
6.3.1.2 A cost breakdown on the continuation sheets of the “Application and Certificate for Payment”, AIA
Document G703 showing all major work items, separated by both material and labor.
6.3.1.3 A list of the work which will be performed with the Bidder’s own forces, a list of their subcontractors and a list of work that will be performed by the subcontractor’s forces.
6.3.1.4 Names of the manufacturer’s, products and suppliers of principle items, materials or systems proposed for the work.
6.3.1.5 Schedule information.
6.3.1.6 The Bidder will be notified in writing if any of the above items are not acceptable.
ARTICLE 7 – PERFORMANCE BOND AND PAYMENT BOND
7.1 BOND REQUIREMENTS Revise Subparagraph 7.1.1 as follows and Delete Subparagraph 7.1.3
7.1.1 Revise first sentence to read “For Contracts exceeding $50,000 the Bidder shall furnish separate Performance and Payment Bonds covering the…”
7.2 TIME OF DELIVERY AND FORM OF BONDS Delete Subparagraph 7.2.2
ARTICLE 8 – ENUMERARTION OF THE PROPOSED CONTRACT DOCUMENTS
8.1 Revise sentence to read: Copies of the proposed Contract Documents will be made available to the Awarded
Bidder as modified and would include but not limited to the following documents as issued by the Construction
Manager.
www.owen-ames-kimball.com
ARTICLE 9 – INSURANCE
9.1 INSURANCE REQUIREMENTS The required insurance will name Owen-Ames-Kimball Co., Owner and
Architect, along with their respective officers, agents and employees are named as additional insureds for the auto liability and general liability on a primary and non-contributory basis for ongoing and completed operations. The ONLY acceptable endorsement for the additional insureds requirements is ISO form CG 20
37 07 04.
9.1.1 Commercial General Liability – ISO Occurrence form CG 20 10 07 04 and CG 20 37 07 04 are the required forms.
ARTICLE 10 – DESCRIPTION OF WORK Add paragraph 10.1 and 10.2
10.1 BID CATEGORIES Add Subparagraphs 10.1.1, 10.1.1.1., 10.1.1.2, 10.1.1.3 as follows:
10.1.1 Bid Categories have been established to guide Bidders in determining scope of work where trade jurisdiction is not clearly defined. These descriptions are not meant to be all inclusive of work to be included in the Bid.
If a conflict in the assignment of work exists between the Bidding Documents and the descriptions of these bid categories, the requirements of the bid category description(s) shall take precedence and the
Construction Manager shall immediately be notified of the conflict. Bidders are to familiarize themselves with all Bid Categories.
10.1.1.1 Requirements for a specific Bid Category, trade or contract will generally be described in that portion of the
Specifications or Drawings related to that trade or contract. Such requirements may, however, be described in other sections of the contract documents. Contractors will be held responsible for having carefully examined all drawings and read all divisions of the specifications and all contract documents to avoid omissions or duplications and to ensure a complete job.
10.1.1.2 There is not necessarily a direct relationship between the Bid Category numbers or names and the
Specification Division or Section numbers.
10.1.1.3 Unless specifically noted as being furnished only, scopes include the complete installation including materials, labor, equipment, interface with the work of other trades, etc.
10.2 INDEX OF BID CATEGORIES Add paragraph 10.2
Bid Category No. 2 – Demolition
Bid Category No. 1 – Earthwork
10.3 BID CATEGORY DESCRIPTIONS Add paragraph 10.3
Bid Categories have been established to guide Bidders in determining scope of work where trade jurisdiction is not clearly defined. These descriptions are not meant to be all inclusive of work to be included in Bid.
Unless specifically noted as being furnished only or install only, scope includes complete installation including all labor, material, equipment, etc.
Bidders are required to familiarize themselves with all Bid Categories www.owen-ames-kimball.com
BID CATEGORY NO. 1 - DEMOLITION
1. Complete demolition work as shown on the drawings and as specified in the following sections:
Division 01 As it pertains to this contractor’s work
02 4100 Demolition
2. See General Comments re: Demolition
3. Complete removal of existing building as indicated. Includes removal of footings and foundations.
4. Applicable fees, permits, inspections, etc. as required for the completion of the work in this bid category.
5. Maintain the work areas in safe condition throughout demolition operations.
6. Complete demolition plan as required by MIOSHA and furnish to Construction Manager before beginning work.
7. Contractor is to provide their own air personal (MIOSHA) air monitoring.
8. Hazardous Materials and Noted in Hazardous Materials Report to be removed by others prior to start of building demo.
9. This contractor is responsible for all other demo associated with the building and building elements.
10. Demolition contractors will be required for demolition and removal of ductwork, piping, wiring, and equipment as part of building.
11. Provide and install any necessary shoring as needed or required during demo operations
Exclude:
1. Hazardous Materials Removals
BID CATEGORY NO. 2 – EARTHWORK
1. Complete site related and demolition work as shown on the drawings and as specified in the following sections:
Division 01 As it pertains to this contractor’s work
31 1000 Site Clearing
31 2200 Grading
31 2316 Excavation
31 2323 Fill
2. Applicable fees, permits, inspections, etc. as required for the completion of the work in this bid category.
3. Responsible for keeping public roads clean of traffic dirt and debris.
4. See General Comments re: Demolition
5. Temporary tree protection measures.
6. Site related demolition, including but not limited to, pavements, site walls, utility structures, underground storm piping and playgrounds.
7. Soil erosion permit and erosion control. Include permitting and facilitation of inspections and corrections as needed. This contactor responsible for installing and maintaining items listed on the SESC plan. See SESC Key on
C103
8. Include protection of existing items noted to remain and be protected during construction.
9. Implement and maintain all BMP's deemed necessary by either the Certified Storm Water Operator or the Agency responsible for jurisdiction of Protection Act 451.
10. Responsible for tree/root removal as indicated on drawings
11. This contractor is responsible for preparing the site for all future work by rough grading site and making safe.
Exclude:
2. Building Demo
GENERAL COMMENTS
Demolition:
1. Dumpsters will not be provided by the Construction Manager. Site related demolition items are to be removed from site properly by the Earthwork Contactor. Building related demolition debris, and materials to be removed from the site by the Demolition Contractor.
2. Unless specifically noted otherwise the division of demolition work shall be as follows: Earthwork contractor – site demolition; Demolition Contractor – architectural, structural, and MEP demolition.
General Safety:
1. Your Firm, all employees, subcontractors, and material suppliers onsite will comply with Owen-Ames-Kimball
Co.’s Safety Policy and Requirements, INCLUDING BUT NOT LIMITED TO THESE HIGHLIGHTED ITEMS:
a. Hard hats are required.
b. Contractor safety manuals/books will be kept on-site.
c. Contractors must provide their own first aid and fire protection equipment.
d. Contractors are responsible for providing the necessary barricades for their work.
e. Contractors are responsible for their own fall protection.
f. Contractors must comply with the "Right to Know" law.
g. Contractors must comply with O.A.K.'s substance abuse policy.
h. No Smoking, Tobacco, or E-Cigarettes on School Property.
i. A designated competent/qualified person shall be required to be on site for the following but not limited to structural demolition, scaffolding, fall protection & excavations.
j. Contractors shall furnish a written job specific Silica Exposure Plan per MiOSHA requirements.
k. Contractors required to work in a masonry restricted zone must have proper training.
2. Owen-Ames-Kimball Co. Safety Manual can be viewed in its entirety here:
https://tinyurl.com/34zxyj49
End of Instruction Bidders
STATEMENT OF PARTICIPATION
Owen-Ames-Kimball Co. strives to recognize and represent the community in which you reside and serve through continuous efforts to encourage local participation and inclusive practices on all our construction projects.
Owen-Ames-Kimball Co. encourages local participation. We believe we have a responsibility to support the growth of the businesses within the community in which the project resides.
Owen-Ames-Kimball Co. practices inclusion. These inclusive practices are established within our organization and in our business endeavors, and strongly promoted on our jobsites. We encourage all of our subcontractors to implement inclusive practices within their organizations and through partnering efforts on our projects.
SUBMIT IN TRIPLICATE
BID FORM
BID TO: Kent Intermediate School District
2930 Knapp St
Grand Rapids, MI 49525
BID FROM: _________________________________________
PROJECT: Kent ISD – Career Tech South Campus – Bid Package 1 – Demo
Ladies and Gentlemen:
The undersigned, having familiarized themselves with the local conditions affecting the cost of the Work and having examined the site, and Bidding Documents prepared by hereby propose to furnish all labor, material, equipment, taxes and services required for the proper completion of each of the following categories for this Project, including all addenda issued thereto, for the sum of:
Bid Category No.____________ Title
Dollars ($ _ ), Said amount constituting the Base Bid.
TAXES: Bid sum includes all applicable taxes, including Michigan Sales Tax. Confirm that your company can pay Michigan Sales and Use Tax: ☐ Yes ☐ No
ALLOWANCES: Base bid includes applicable allowance cost(s) as set forth in Section 01020 of the General
Requirements and as identified in the Instruction to Bidders Bid Category Descriptions.
COST OF BONDS: Bid sum includes cost of furnishing a Performance Bond and Labor and a Material
Payment Bond, each in the amount of 100% of Base Bid.
ACKNOWLEDGEMENT OF ADDENDA
The following addenda have been received, are hereby acknowledged, and their execution is included in the above Base Bid:
Addendum No. Dated Addendum No. Dated Addendum No. Dated_________
Addendum No. Dated Addendum No. Dated Addendum No. Dated_________
ALTERNATES
Base bid amount may be increased or decreased in accordance with each of the following alternate bids as may be selected, following the procedures stated in the Instruction to Bidders. Any applicable bonding cost should be included with the Alternate pricing.
VOLUNTARY ALTERNATES (Identify in detail on appropriate attachment any Voluntary Alternates shown here)
A
B
C
BID SECURITY
Accompanying this Bid, as required by the Instructions to Bidders, is a bid security in the form of
(Certified Check/Cashier's Check/Bidder's Bond) in the amount of:
Dollars ($ _______ ), payable to the Owner, which it is agreed, shall be retained as liquidated damages, not as a penalty, by the
Owner, if the undersigned fails to execute the Contract in conformity with the form of Contract incorporated in the Contract Documents and fails to furnish specified bonds within ten (10) days after date of issuance of Letter of Intent to the undersigned.
If awarded the Contract, the undersigned agrees to commence Work within ten (10) days after date of issuance of Notice of Pending Award, which shall be considered as the notice to proceed, and agrees to complete the Work in accordance with the Construction Progress Schedule.
CONSTRUCTION PROGRESS SCHEDULE
If awarded this Contract, the undersigned:
Endorses the Construction Progress Schedule:
Amends the Construction Progress Schedule as follows:
INSURANCE AND ENDORSEMENTS REQUIREMENTS:
(Samples are attached to the Supplement to Instructions to Bidders)
Acknowledged By:___________________________________________________________________________________________
UNIT LABOR RATES
The undersigned further proposes and agrees that should the amount of work required be increased or decreased where unit prices have not been established, the following labor rates will be the basis for any change order proposal. Labor rates are to include all direct costs without mark-up as defined in Article 7.3 of the General Conditions. Prior to contract award, if requested by the Construction Manager, the successful bidder shall provide documentation substantiating the proposed labor rates.
FEES FOR ADDITIONAL WORK
1. There will be a fee of 10% applied to the total cost of materials purchased and work completed by a contractor’s own forces. This percentage represents both overhead and profit.
2. There will be a fee of 5% applied to the total cost of work completed by a subcontractor. This percentage represents both overhead and profit.
CREDIT FOR WORK DELETED
Should any work be deleted from Contract by order of the Owner, full cost savings realized thereby will be credited to Owner.
FAMILIAL DISCLOSURE
See Page 6 of this Bid Form for required statement.
AFFIDAVIT OF COMPLIANCE
See Page 7 of this Bid Form for required statement.
SAFETY SUPPLEMENT FORM
The apparent low bidder(s) will be required to complete this form and submit to the project manager no later than (3) days after the bid opening or at the time of the post bid interview. Based on the information supplied
Owen-Ames-Kimball Co. may require further safety measures at no additional cost prior to award if warranted.
Job Hourly Benefits Employer's Payroll Total
Classification Rate Liability Taxes
AGREEMENT
The undersigned agree(s) to provide the post-bid information required within (10) days after notification of the Notice of Award and to execute an agreement for work covered by this Proposal on AIA Document
A132-2019, Standard Form of Agreement Between Owner and Contractor Where the Basis of Payment is a Stipulated Sum.
In submitting this bid, it is understood that the Owner reserves the right to reject any or all bids. It is further agreed that this bid is binding for a period of sixty (60) days from the opening thereof.
Respectfully submitted, Date , 2026
Firm Name
By
Signed
Title
Official Address
(If a corporation, affix seal)
Telephone No. ( ) ext. ___
E-Mail Address
Contact Information if there are questions about bid:
Name:_____________________________________________
Direct or Mobile Phone:__________________________
E-Mail:____________________________________________
Familial Disclosure Statement
(Must be completed for bid to be considered)
In accordance with Section 1267 of the Revised School Code this bid must be accompanied by a sworn and notarized statement disclosing any familial relationship between the Owner or any employee of the
Bidder and any member of the District’s Board of Education or Superintendent of the District.
___ No, there is not a familial relationship between the Owner or any employee of the Bidder and any member of the District’s Board of Education or Superintendent of the District.
___ Yes, there is a familial relationship between the Owner or an employee of the Bidder and a member of the District’s Board of Education or Superintendent of the District. The person(s) and relationship are as follows:
Owner/Employee Name BOE member or Superintendent Name Familial Relationship
Contractor: _________________________________________________________________________________________________
(Name of Contractor)
By: _______________________________________________________________
Title: _______________________________________________________________
Date: _______________________________________________________________
County of: _______________________________________ State of: _______________________________________
This instrument was acknowledged before me on the ____________day of ____________________________, 2026, by,_________________________________________________________________________________, Notary Public
__________________________________________ County, ________________________________.
My Commission Expires: ____________________________________________
Acting in the County of: ____________________________________________
Affidavit of Compliance – Iran Economics Sanctions Act
(Must be completed for bid to be considered)
Michigan Public Act No. 517 of 2012
The undersigned, the owner or authorized office of the below-named contractor (the “Contractor”), pursuant to the compliance certification requirement provided in the Kent Intermediate School District
(“the School District”) Request for Proposals For Career Tech South Campus Bid Package No. 1 – Demo
(the RFP”), hereby certifies, represents and warrants that the Contractor (including its officers, directors, employees) is not an “Iran linked business” within the meaning of the Iran Economics Sanctions Act, Michigan Public Act No.517 of 2012 (“the Act”), and that in the event Contractor will not become an “Iran linked business” at any time during the course of performing any services under this contract.
The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School
District’s Investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years form the date determined that the person had submitted the false certification.
Contractor:
(Name of Contractor)
By: _______________________________________________________________
Title: _______________________________________________________________
Date: _______________________________________________________________
County of: _______________________________________ State of: _______________________________________
This instrument was acknowledged before me on the ____________day of ____________________________, 2026, by,_________________________________________________________________________________, Notary Public
__________________________________________ County, ________________________________.
My Commission Expires: ____________________________________________
Acting in the County of: ____________________________________________
Safety Data Questionnaire Supplement to Bid Form
The Safety data listed below shall be submitted no later than three (3) days after the bid opening by the apparent low bidder, or as requested by O-A-K for evaluation. Further documentation may be requested as a part of the evaluation process. Information specified below must be current and accurate.
COMPANY INFORMATION
Company Name:
Company Type:
Address:
City: State: Zip:
Name of your Safety and Health Officer responsible for this project:
Safety Accreditations:
Length of experience in this role:
Safety and Health Officer E-mail:
Safety and Health Officer Phone:
Does your company have a written procedure to ensure that adequate safety and health program resources, such as budget, equipment, training, and manpower are included in your bid?
YES □ NO □
Does your company have a written construction safety program? YES □ NO □
I acknowledge that my company will provide a written Site-Specific safety plan? YES □ NO □
Does your company have a written Accident/Incident Investigation Procedure? YES □ NO □
Does your company provide training and proper equipment for fall protection as required by MIOSHA?
Does your company have a safety training program? YES □ NO □
What mandatory training topics have been covered in the past year?
What percent of your company’s employees have OSHA Training Certification? _______ %
Does your company have a written drug and alcohol-free workplace program that includes drug testing? YES □
NO □
Does your company conduct post-Incident drug and alcohol testing? YES □ NO □
Has your company ever been removed from a project due to safety concerns within the last 3 years?
YES □ NO □ If yes, please briefly explain:
Does your company have a written procedure to screen subcontractors based on their past safety performance and history? YES □ NO □
Explain how you will ensure that subcontractors are following the same safety standards and expectations as your company?
Please list the PPE that your company will require while on site of all of your company’s employees and subcontractors:
I acknowledge that my Employees, Company, and/or Subcontractors can be removed from the project if safety standards and requirements are not being followed. YES □ NO □
Has your company received any citations or violations from MIOSHA in the past three (3) years?
YES □ NO □ If yes, please list:
Has your company received any willful safety violations from MIOSHA in the past five (5) years?
List your company’s Workers Compensation Experience Modification Rate for each of the last three (3) years.
20____________ 20____________ 20____________
List the number of man-hours your company worked in each of the last three (3) years.
List the OSHA recordable injuries your company experienced in each of the last three (3) years.
List the Total Recordable Incident Rate (TRIR) your company experienced in each of the last three (3) years.
Calculation: TRIR = (number of OSHA Recordable Incidents) x 200,000 / Total Number of man-hours worked
PROJECT SPECIFIC
How often will your company perform documented job site safety Inspections?
Daily □ Weekly □ Bi-Weekly □ Monthly □
Does your company conduct toolbox safety talks or weekly safety huddles? YES □ NO □
Does your company have a written procedure to ensure that only employees who are qualified by training and experience are allowed to operate equipment, tools, machinery and vehicles? YES □ NO □
Do you see any potential safety hazards on this project that your company does not have experience with or are concerned about? YES □ NO □ If yes, please explain:
COMPANY ACKNOWLEDGEMENT
I certify that my response and the information provided are true and correct to the best of my personal knowledge and belief and that I have made no willful misrepresentations in the questionnaire, nor have I withheld any relevant information in my statements and answers to questions. I am aware that any information given by me in this questionnaire may be investigated and I hereby give my full permission for and such investigation and I fully acknowledge that any misrepresentations or omissions in my response and information my cause my bid to be rejected.
Furthermore, I acknowledge that O-A-K may, at no additional cost or increase to the bid, require the contractor to perform additional safety requirements if the above information is deemed incomplete, Insufficient, below industry standard, or not to level of safety commitment expected. This may include but not be limited to additional site safety audits and inspections, full time safety supervisor, etc.
Bidders full name and entity status:
Signature
Authorized Representative of Company
Printed Name
Authorized Representative of Company
Title Date
Document A232
– 2019 General Conditions of the Contract for Construction, Construction Manager as Adviser Edition
Init.
AIA Document A232™ – 20 19 . Copyright © 1992, 2009, and 2019 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:10:42 ET on 11/03/2021 under Order No.2152401120 which expires on 09/06/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (875850319)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.
This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.
This document is intended to be used in conjunction with AIA Documents A132™–2019, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition; B132™–2019, Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition; and C132™–2019, Standard Form of Agreement Between Owner and Construction Manager as Adviser.
for the following PROJECT:
(Name, and location or address)
LDC Entry Alterations LDC Building Renovation Oakleigh Renovations KCTC Projects KTC Projects LPP Partial LNS Work LNS Business Renovations LCC Building Renovations And Other Project Directed by Kent ISD
THE CONSTRUCTION MANAGER:
(Name, legal status, and address)
Owen Ames Kimball Co.
300 Ionia NW Grand Rapids, MI 49503
THE OWNER:
(Name, legal status, and address)
Kent Intermediate School District 2930 Knapp Street SE Grand Rapids, MI 49525
THE ARCHITECT:
(Name, legal status, and address)
Mathison | Mathison Architects 560 5th St NW #405 Grand Rapids, MI 49504
BMA Architects 17216 Van Wagoner Spring Lake, MI 49456
Progressive Companies 1811 4 Mile Road NE Grand Rapids, MI 49525
GMB Architecture + Engineering 85 East Eight St, Suite 200 Holland, MI 49423
Init.
AIA Document A232™ – 20 19 . Copyright © 1992, 2009, and 2019 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:10:42 ET on 11/03/2021 under Order No.2152401120 which expires on 09/06/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (875850319)
TABLE OF ARTICLES
1 GENERAL PROVISIONS
2 OWNER
3 CONTRACTOR
4 ARCHITECT AND CONSTRUCTION MANAGER
5 SUBCONTRACTORS
6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
7 CHANGES IN THE WORK
8 TIME
9 PAYMENTS AND COMPLETION
10 PROTECTION OF PERSONS AND PROPERTY
11 INSURANCE AND BONDS
12 UNCOVERING AND CORRECTION OF WORK
13 MISCELLANEOUS PROVISIONS
14 TERMINATION OR SUSPENSION OF THE CONTRACT
15 CLAIMS AND DISPUTES
AIA Document A232™ – 20 19 . Copyright © 1992, 2009, and 2019 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:10:42 ET on 11/03/2021 under Order No.2152401120 which expires on 09/06/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (875850319)
ARTICLE 1 GENERAL PROVISIONS
§ 1.1 Basic Definitions § 1.1.1 The Contract Documents. The Contract Documents are enumerated in the Agreement between the Owner and Contractor (hereinafter the Agreement) and consist of the Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of the Contract, other documents listed in the Agreement, and Modifications issued after execution of the Contract. A Modification is
(1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written order for a minor change in the Work issued by the Architect. Unless specifically enumerated in the Agreement, the Contract Documents do not include the advertisement or invitation to bid, Instructions to Bidders, sample forms, other information furnished by the Owner in anticipation of receiving bids or proposals, the Contractor’s bid or proposal, or portions of addenda relating to bidding or proposal requirements.
§ 1.1.2 The Contract. The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Contractor and the Architect or the Architect’s consultants, (2) between the Owner and the Construction Manager or the Construction Manager’s consultants, (3) between the Owner and the Architect or the Architect’s consultants, (4) between the Contractor and the Construction Manager or the Construction Manager’s consultants, (5) between the Owner and a Subcontractor or Sub-subcontractor (6) between the Construction Manager and the Architect, or (7) between any persons or entities other than the Owner and Contractor. The Construction Manager and Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of their duties.
§ 1.1.3 The Work. The term "Work" means the construction and services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment, and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations. The Work may constitute the whole or a part of the Project.
§ 1.1.4 The Project. The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by other Contractors, and by the Owner’s own forces and Separate Contractors.
§ 1.1.5 Contractors. Contractors are persons or entities, other than the Contractor or Separate Contractors, who perform Work under contracts with the Owner that are administered by the Architect and Construction Manager.
§ 1.1.6 Separate Contractors. Separate Contractors are persons or entities who perform construction under separate contracts with the Owner not administered by the Architect and Construction Manager.
§ 1.1.7 The Drawings. The Drawings are the graphic and pictorial portions of the Contract Documents showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedules, and diagrams.
§ 1.1.8 The Specifications. The Specifications are that portion of the Contract Documents consisting of the written requirements for materials, equipment, systems, standards and workmanship for the Work, and performance of related services.
§ 1.1.9 Instruments of Service. Instruments of Service are representations, in any medium of expression now known or later developed, of the tangible and intangible creative work performed by the Architect and the Architect’s consultants under their respective professional services agreements. Instruments of Service may include, without limitation, studies, surveys, models, sketches, drawings, specifications, and other similar materials.
§ 1.1.10 Initial Decision Maker. The Initial Decision Maker is the person identified in the Agreement to render initial decisions on Claims in accordance with Section 15.2. The Initial Decision Maker shall not show partiality to the Owner or Contractor and shall not be liable for results of interpretations or decisions rendered in good faith.
AIA Document A232™ – 20 19 . Copyright © 1992, 2009, and 2019 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:10:42 ET on 11/03/2021 under Order No.2152401120 which expires on 09/06/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (875850319)
§ 1.2 Correlation and Intent of the Contract Documents § 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results.
§ 1.2.1.1 The invalidity of any provision of the Contract Documents shall not invalidate the Contract or its remaining provisions. If it is determined that any provision of the Contract Documents violates any law, or is otherwise invalid or unenforceable, then that provision shall be revised to the extent necessary to make that provision legal and enforceable. In such case the Contract Documents shall be construed, to the fullest extent permitted by law, to give effect to the parties’ intentions and purposes in executing the Contract.
§ 1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade.
§ 1.2.3 Unless otherwise stated in the Contract Documents, words that have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings.
§ 1.3 Capitalization Terms capitalized in these General Conditions include those that are (1) specifically defined, (2) the titles of numbered articles, or (3) the titles of other documents published by the American Institute of Architects.
§ 1.4 Interpretation In the interest of brevity the Contract Documents frequently omit modifying words such as "all" and "any" and articles such as "the" and "an," but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement.
§ 1.5 Ownership and Use of Drawings, Specifications, and Other Instruments of Service § 1.5.1 The Architect and the Architect’s consultants shall be deemed the authors and owners of their respective Instruments of Service, including the Drawings and Specifications, and retain all common law, statutory, and other reserved rights in their Instruments of Service, including copyrights. The Contractor, Subcontractors, sub-subcontractors, and suppliers shall not own or claim a copyright in the Instruments of Service. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with the Project is not to be construed as publication in derogation of the Architect’s or Architect’s consultants’ reserved rights.
§ 1.5.2 The Contractor, Subcontractors, Sub-subcontractors, and suppliers are authorized to use and reproduce the Instruments of Service provided to them, subject to any protocols established pursuant to Sections 1.7 and 1.8, solely and exclusively for execution of the Work. All copies made under this authorization shall bear the copyright notice, if any, shown on the Instruments of Service. The Contractor, Subcontractors, Sub-subcontractors, and suppliers may not use the Instruments of Service on other projects or for additions to the Project outside the scope of the Work without the specific written consent of the Owner, Architect, and the Architect’s consultants.
§ 1.6 Notice § 1.6.1 Except as otherwise provided in Section 1.6.2, where the Contract Documents require one party to notify or give notice to the other party, such notice shall be provided in writing to the designated representative of the party to whom the notice is addressed and shall be deemed to have been duly served if delivered in person, by mail, by courier, or by electronic transmission if a method for electronic transmission is set forth in the Agreement.
§ 1.6.2 Notice of Claims as provided in Section 15.1.3 shall be provided in writing and shall be deemed to have been duly served only if delivered to the designated representative of the party to whom the notice is addressed by certified or registered mail, or by courier providing proof of delivery.
§ 1.7 Digital Data Use and Transmission The parties shall agree upon protocols governing the transmission and use of Instruments of Service or any other information or documentation in digital form. The parties will use AIA Document E203™–2013, Building
AIA Document A232™ – 20 19 . Copyright © 1992, 2009, and 2019 by The American Institute of Architects. All rights reserved. The “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are registered trademarks and may not be used without permission. This document was produced by AIA software at 13:10:42 ET on 11/03/2021 under Order No.2152401120 which expires on 09/06/2022, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail copyright@aia.org.
User Notes: (875850319)
Information Modeling and Digital Data Exhibit, to establish the protocols for the development, use, transmission, and exchange of digital data.
§ 1.8 Building Information Models Use and Reliance Any use of, or reliance on, all or a portion of a building information model without agreement to protocols governing the use of, and reliance on, the information contained in the model and without having those protocols set forth in AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, and the requisite AIA Document G202™–2013, Project Building Information Modeling Protocol Form, shall be at the using or relying party’s sole risk and without liability to the other party and its contractors or consultants, the authors of, or contributors to, the building information model, and each of their agents and employees.
ARTICLE 2 OWNER
§ 2.1 General § 2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Owner shall designate in writing a representative who shall have express authority to bind the Owner with respect to all matters requiring the Owner’s approval or authorization. Except as otherwise provided in Section 4.2.1, the Construction Manager and the Architect do not have such authority. The term "Owner" means the Owner or the Owner’s authorized representative.
§ 2.1.2 The Owner shall furnish to the Contractor, within fifteen days after receipt of a written request, information necessary and relevant for the Contractor to evaluate, give notice of, or enforce mechanic’s lien rights. Such information shall include a correct statement of the record legal title to the property on which the Project is located, usually referred to as the site, and the Owner’s interest therein.
§ 2.2 Evidence of the Owner’s Financial Arrangements § 2.2.1 Prior to commencement of the Work, and upon written request by the Contractor, the Owner shall furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract. The Contractor shall have no obligation to commence the Work until the Owner provides such evidence. If commencement of the Work is delayed under this Section 2.2.1, the Contract Time shall be extended appropriately.
§ 2.2.2 Following commencement of the Work and upon written request by the Contractor, the Owner shall furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract only if (1) the Owner fails to make payments to the Contractor as the Contract Documents require;
(2) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due;
or (3) a change in the Work materially changes the Contract Sum. If the Owner fails to provide such evidence, as required, within fourteen days of the Contractor’s request, the Contractor may immediately stop the Work and, in that event, shall notify the Owner that the Work has stopped.