About this file

This is a Request for Bid (RFB) form issued by the Oregon Department of Transportation (ODOT) for on-call Region 2 paving services. The project involves a 3-inch inlay paving repair on Interstate 5 northbound at milepoint 222 in Linn County to address shoulder surface damage caused by a vehicle fire. The work scope encompasses approximately 8 feet wide by 110 feet long and includes cold plane pavement removal (98 square yards), placement of Level 3, 1/2-inch dense asphalt concrete mixture (17 tons), thermoplastic marking retracement (110 linear feet), and replacement of 16-inch gap pattern rumble strips (0.021 mile). Seven pay items are included: mobilization, temporary work zone traffic control, pollution control plan, cold plane pavement removal, asphalt mixture placement, thermoplastic markings, and rumble strip replacement. Work may be performed Sunday night through Thursday morning between 9:00 p.m. and 5:30 a.m. Portable changeable message signs must be placed at least 7 days in advance of any lane closure. The bid was due November 16, 2026, at 2:00 p.m., and work must be completed by December 31, 2026. Only holders of the On-Call Region 2 Paving Price Agreement (PO-73000-) are eligible to submit bids.

Contractors must submit completed bid forms through the OregonBuys system with unit and total prices for all bid items. Payment will be based on actual quantities provided and performed rather than estimated quantities. The project requires compliance with Oregon prevailing wage rates effective September 3, 2026, as amended October 5, 2026, available through the Oregon Bureau of Labor and Industries. Domestic preference requirements under ORS 279C.303 and State Buy America Provisions outlined in Price Agreement Exhibit A apply. Contractors must provide their company legal name, address, contact person, email, phone number, CCB number, and authorized signature as part of their bid submission. The ODOT Project Manager is Cody Stone, reachable at 503-953-6334 or Cody.Stone@ODOT.Oregon.gov.

View the file

Other files

File Type Posted
00018291_bid tab.xlsx XLSX spreadsheet
Photos_2.pdf PDF
00018291_RFB.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

REQUEST FOR BID AND RESULTING WORK ORDER
On-Call Region 2 Paving
INSTRUCTIONS: ODOT will fill in all information below except Contractor Information, Work Order Number (to be added upon award of Work Order), and pricing. ODOT will provide a list of bid items and their estimated quantities. Contractor must complete the Contractor Information section, including a signature, and insert unit and total prices for all bid items. Contractor must submit its bid by uploading the completed Request for Bid/Work Order form to the Attachments tab for the project in OregonBuys and entering the total bid price on the Items tab.

Request for Bid Number: S-73000-00018291 Work Order Number:

Issue Date: 10/29/2026 Version 3 - 11/13/2026 Bid due date and time: 11/16/2026 2:00 pm

Project Name: I5 MP222 NB Fire Damage

Project description (include milepoint locations): 3" inlay paving on I5 NB at MP222 to repair shoulder surface damaged by a vehicle fire, approximately 8' wide and 110' long. Longitudinal markings that have been damaged by fire should be retraced and shall match existing color, layout/location, and material as existing. 16" gap pattern rumble strips to be replaced and match existing.

ODOT Project Manager Name and Phone number: Cody Stone 503-953-6334
ODOT Project Manager Billing Address (may be an email): Cody.Stone@ODOT.Oregon.gov

ODOT Site Representative (if different than ODOT Project Manager):

Required Completion Date: 12/31/2026

CONTRACTOR INFORMATION

Contractor (COMPANY) Legal Name:

Address:

Contact Person: Email:

Phone: CCB #:

Contractor's On-Call Region 2 Paving Price Agreement Number: PO-73000-

Contractor’s signature below indicates its firm offer to provide the Services described in this Work Order in accordance with all terms, conditions, and specifications contained in the Price Agreement referenced above, and any additional specifications contained within this Work Order and its attachments. The Work Order is not effective until it is signed by ODOT's Procurement Authority, and ODOT issues a notice to proceed.

Contractor Signature: Date:

ODOT Signature (Procurement Authority):Date:
ANTICIPATED WORK ITEMS (PAY ITEMS)
This Work Order indicates an estimate of services/quantities required. Payment to Contractor will be made based on actual quantities provided/performed:
ItemDescriptionEst. Qty.UnitUnit PriceTotal Price
1Mobilization1LS$ - 0
2Temporary Work Zone Traffic Control, Complete1LS$ - 0
3Pollution Control Plan1LS$ - 0
4Cold Plane Pavement Removal, 3" Deep98SQ YD$ - 0
5Level 3, 1/2" Dense ACP Mixture (PG64-22)17TON$ - 0
6Thermoplastic, Extruded or Sprayed, Grooved, Non-Profiled110FOOT$ - 0
7Gap Pattern Rumble Strips0.021MILE$ - 0
PROJECT SPECIFIC REQUIREMENTS

This project requires compliance with the domestic preference requirements of ORS 279C.303. Contractor shall comply with Price Agreement Exhibit A - State Buy America Provisions.

x If the contract price exceeds $50,000, this project requires payment of the following prevailing wage rates, which are available online at http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx:

"Prevailing Wage Rates for Public Works Contracts” effective September 3, 2026 and as amended October 5, 2026.

County where the work will be performed: Linn
xThe following attachments are incorporated into this Request for Bid and any resulting Work Order:

Photos.pdf x One or more traffic lanes may be closed when allowed, shown, or directed during the following periods of time:

Sunday night through Thursday morning, 9 PM to 5:30 AM x Portable Changeable Message Signs (PCMS) shall be placed a minimum of 7 days in advance of any ramp or lane closure to alert the public of the closure. The location of the PCMS and the message on the PCMS shall be submitted to the Project Manager as part of the Contractor’s proposed TCP.

Traffic will be allowed on the cold planed surface up to ____ calendar days after removing the existing surface. Sweep and clean the cold planed surface before opening to traffic.

COMMENTS & SPECIAL INSTRUCTIONS: