00016247 Exhibit 6 Plans.Revised.pdf
PDF 1 MB Posted
- Attached to
- I-84: Weatherby to Ontario MBM 2026 Project
- Solicitation number
- S-73000-00016247
- Issued by
- Baker County, Oregon
About this file
This is a set of construction plans prepared by the Oregon Department of Transportation for the I-84 Weatherby to Ontario MBM 2026 Project, a bridge resurfacing initiative spanning Baker and Malheur Counties. The project encompasses four discrete bridge sites located along Interstate 84 between milepost 337.27 and milepost 379.02, with work including the application of approximately 445 tons of Level 4, 1/2 Inch Lime Treated Asphalt Concrete Pavement across the designated surfaces. Construction is scheduled to commence on June 8, 2026, with substantial completion required by June 30, 2026, and final completion by July 13, 2026. The sealed bid submission deadline is April 7, 2026, with public bid opening conducted via Microsoft Teams immediately thereafter. The awarded contractor must coordinate all scheduling with ODOT's Contract Administrator Rick Elliott (Rick.Elliott@odot.oregon.gov, 541-786-2244) and work in conjunction with the District 14 Bridge Crew; ODOT will provide temporary traffic control during construction.
Contract compensation will be provided on a unit-price basis for three pay items: Mobilization (1 lump sum), Pollution Control Plan (1 lump sum), and Level 4, 1/2 Inch Lime Treated Asphalt Concrete Pavement (450 tons). The estimated project value ranges between $100,000 and $250,000. All bidders must be licensed with the Oregon State Construction Contractors Board prior to bid submission, and all subcontractors must be similarly licensed before commencing work. Bid security equal to 10% of the total bid amount is required, with performance and payment bonds each equal to 100% of the contract value due within seven days of award. Insurance requirements include Commercial General Liability ($2,000,000 per occurrence/$5,000,000 aggregate), Commercial Automobile Liability ($1,000,000 combined single limits), and Workers' Compensation coverage ($500,000 per accident). The project is funded with State of Oregon funds, and all work must comply with prevailing wage rates established by the Bureau of Labor and Industries. Retainage shall not exceed 5% of progress payments under Oregon Revised Statutes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00016247 Invitation To Bid.docx | DOCX document | |
| 00016247 Sample Contract.docx | DOCX document | |
| 00016247 Exhibit 5 Specifications.pdf | ||
| 00016247 Addendum 1.docx | DOCX document | |
| 00016247 Exhibit 6 Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M
"'T'
I
0 ,.,., lO ,.,., z i:i:
STATE OF OREGON
INDEX OF SHEETS
SHEET NO. DESCRIPTION DEPARTMENT OF TRANSPORTATION
AOI
BAOI thru
BA02 incl.
Title Sheet
Typical Sections
PROJECT SITE 1
/T-84,MP337.27-
BAKER CO.
PLANS FOR PROPOSED PROJECT
PAVING
1-84: WEATHERBY TO ONTARIO
MBM 2026 PROJECT
OLD OREGON TRAIL HIGHWAY
BAKER & MALHEUR COUNTIES
APRIL2026
CONTINUES
LOWER LEFT
PROJECT SITE 2
/T-84, MP 370.00-
PROJECT SITE 3
/T-84, MP 375.80-
PROJECT SITE 4
1-84, MP 376.00
HUNTINGTON
Title_Sheet_A0U84.dgn :: Default 3/4/2026 11 :45:45 AM hwye53h
CONTINUES
TOP RIGHT
ATTENTION:
Oregon Law Requires You To Follow Rules Adopted By The Oregon Utility Notification Center.
Those Rules Are Set Forth In OAR 952-001-0001 Through OAR 952-001-0100.
You May Obtain Copies Of The Rules By Calling The Center (Note: The Telephone Number For
The Oregon Utility Notification Center Is
(503) 232-1987).
,;� 6.,l�' .�. ,;�< ,4 ,;�< ,;4 6.,<c,+ ""'<:-+ <t'"' ., .. <(" .. .,q,.+ """"' .,<c,+ ""+ ""'1c'"'
.�• LET'S ALL .�'ft
,4 WORK TOGETHER ,1
•',," TO MAKE THIS �{'
h ,;� • �"' JOB SAFE • �"'
.&.�rr.:-�� �� ��� �t �,:. h.., <c�� .. �""'<- "'<c" "'<" "'<c" "'i" "'i" <c" I(< t l T. 12 S., R. 44 E., W.M.
T. 1 7 S., R. 46 E., W.M.
T. 18 S., R. 47 E., W.M.
1-84: WEATHERBY TO ONTARIO
MBM 2026 PROJECT
OLD OREGON TRAIL HIGHWAY
BAKER & MALHEUR COUNTIES
FEDERAL HIGHWAY
ADMINISTRATION
OREGON
DIVISION
FINAL ELECTRONIC DOCUMENT
AVAILABLE UPON REQUEST
PROJECT NUMBER
STATE
SHEET
NO.
AO1
2026.04.02 08:14:35 -07'00'
2026.03.04 11:48:32 -08'00'
| A01 |
| BA01-FLAT |
| BA02-FLAT |
File details come from the government source that posted it. Updated .