00016170 Preliminary Results.xlsx
XLSX spreadsheet 28 KB Posted
- Attached to
- OR 82: Wallowa to Joseph Culvert Repair Project
- Solicitation number
- S-73000-00016170
- Issued by
- Wasco County, Oregon
About this file
This is a bid tabulation document for an Invitation to Bid (ITB) issued by the State of Oregon for the OR:82 Wallowa to Joseph Culvert Repair Project, with ITB number S-73000-00016170. The project involves comprehensive culvert rehabilitation and repair work, including the removal of asbestos materials, temporary traffic control measures, water management, erosion control, and the rehabilitation or replacement of 18-inch, 24-inch, and 36-inch culverts along a specified corridor. The estimated quantities include 833 linear feet of 18-inch culvert rehabilitation, 404 linear feet of 24-inch culvert rehabilitation, 168 linear feet of 36-inch culvert rehabilitation, mainline video inspection of 2,810 linear feet, installation of culvert pipe sections, concrete inlet construction, trench resurfacing, and permanent seeding. The bid closing date was April 16, 2026, at 10:00 AM. Seven contractors submitted bids: Papaya Contracting LLC, HP Civil Inc., JR Carlon Corp, Whitaker Construction Company, Jesse Rodriguez Construction LLC, Wildish Standard Paving Co, and Central Oregon Homes.
The bid tabulation reflects significant price variation among bidders across all line items, with total project bids ranging from $750,746.30 to $1,631,369.00. Notable pricing disparities appear in specialized items such as the 18-inch culvert pipe installation, where unit prices ranged from $228.90 to $3,824.00 per linear foot, and the Concrete Inlet Type D, where bids ranged from $2,250.00 to $35,550.00. Mobilization costs ranged from $50,000.00 to $243,750.00, while culvert rehabilitation rates varied substantially by diameter, indicating different contractor methodologies and resource allocations. The tabulation document explicitly notes that this bid tabulation is not an indicator of award and serves only as a compilation of submitted bids for consideration by the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00016170 Exhibit 6 Plans.pdf | ||
| 00016170 Attachment A Form A2 Pricing Form.xlsx | XLSX spreadsheet | |
| 00016170 Exhibit 5 Specifications.docx | DOCX document | |
| 00016170 Invitation To Bid.docx | DOCX document | |
| 00016170 Sample Contract.docx | DOCX document | |
| 00016170 Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 4/16/26 | ||||||||
| ITB No. | S-73000-00016170 | BIDDER | |||||||
| NAME: | Papaya Contracting LLC | HP Civil Inc. | JR Carlon Corp | Whitaker Construction Company | Jesse Rodriguez Construction LLC | Wildish Standard Paving Co | Central Oregon Homes | ||
| Bid Closing: | 04/16/2026 @ 10:00 AM | ||||||||
| Description: | OR:82 Wallowa To Joseph Culvert Repair Project | ||||||||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $50,000.00 | $ 50,000.00 | $ 78,838.00 | $ 78,838.00 | $126,838.75 | $ 126,838.75 | $100,000.00 | $ 100,000.00 | $89,000.00 | $ 89,000.00 | $93,000.00 | $ 93,000.00 | $ 243,750.00 | $ 243,750.00 | $ - 0 | |
| 2 | Temporary Protection and Direction of Traffic | 1 | LS | $ 50,000.00 | $ 50,000.00 | $ 94,000.00 | $ 94,000.00 | $75,000.00 | $ 75,000.00 | $ 81,700.00 | $ 81,700.00 | $ 95,000.00 | $ 95,000.00 | $ 50,000.00 | $ 50,000.00 | $ 198,814.15 | $ 198,814.15 | $ - 0 | |
| 3 | Temporary Signs | 236 | SQFT | $ 21.00 | $ 4,956.00 | $ 10.00 | $ 2,360.00 | $14.85 | $ 3,504.60 | $ 21.00 | $ 4,956.00 | $ 22.00 | $ 5,192.00 | $ 40.00 | $ 9,440.00 | $ 51.40 | $ 12,130.40 | $ - 0 | |
| 4 | Flaggers | 480 | HOURS | $ 75.00 | $ 36,000.00 | $ 92.00 | $ 44,160.00 | $114.75 | $ 55,080.00 | $ 75.00 | $ 36,000.00 | $ 107.00 | $ 51,360.00 | $ 100.00 | $ 48,000.00 | $ 146.40 | $ 70,272.00 | $ - 0 | |
| 5 | Flagger Station Lighting | 1 | EACH | $ 450.00 | $ 450.00 | $ 1.00 | $ 1.00 | $1,500.00 | $ 1,500.00 | $ 5,600.00 | $ 5,600.00 | $ 500.00 | $ 500.00 | $ 4,000.00 | $ 4,000.00 | $ 1,587.00 | $ 1,587.00 | $ - 0 | |
| 6 | Automated Flagger Assistance Device | 2 | EACH | $ 6,000.00 | $ 12,000.00 | $ 1,000.00 | $ 2,000.00 | $2,200.00 | $ 4,400.00 | $ 4,100.00 | $ 8,200.00 | $ 5,500.00 | $ 11,000.00 | $ 2,000.00 | $ 4,000.00 | $ 7,070.00 | $ 14,140.00 | $ - 0 | |
| 7 | Temporary Water Management, MP 50.41 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 8 | Temporary Water Management, MP 50.77 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 9 | Temporary Water Management, MP 51.04 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 9,500.00 | $ 9,500.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 10 | Temporary Water Management, MP 51.17 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 11 | Temporary Water Management, MP 53.50 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 500.00 | $ 500.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 12 | Temporary Water Management, MP 61.32 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 3,575.00 | $ 3,575.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 13 | Temporary Water Management, MP 61.42 | 1 | LS | $ 2,000.00 | $ 2,000.00 | $ 1,000.00 | $ 1,000.00 | $2,250.00 | $ 2,250.00 | $ 9,000.00 | $ 9,000.00 | $ 3,575.00 | $ 3,575.00 | $ 1,000.00 | $ 1,000.00 | $ 44,500.00 | $ 44,500.00 | $ - 0 | |
| 14 | Erosion Control | 1 | LS | $ 2,500.00 | $ 2,500.00 | $ 1,000.00 | $ 1,000.00 | $1,200.00 | $ 1,200.00 | $ 8,880.00 | $ 8,880.00 | $ 4,750.00 | $ 4,750.00 | $ 4,000.00 | $ 4,000.00 | $ 11,540.00 | $ 11,540.00 | $ - 0 | |
| 15 | Pollution Control Plan | 1 | LS | $ 1,000.00 | $ 1,000.00 | $ 500.00 | $ 500.00 | $1,200.00 | $ 1,200.00 | $ 3,000.00 | $ 3,000.00 | $ 750.00 | $ 750.00 | $ 2,000.00 | $ 2,000.00 | $ 1,198.00 | $ 1,198.00 | $ - 0 | |
| 16 | Contaminated Soil Disposal | 17 | TON | $ 45.00 | $ 765.00 | $ 60.00 | $ 1,020.00 | $250.00 | $ 4,250.00 | $ 465.00 | $ 7,905.00 | $ 95.00 | $ 1,615.00 | $ 30.00 | $ 510.00 | $ 202.00 | $ 3,434.00 | $ - 0 | |
| 17 | Bulk Asbestos Sampling, Analytical Testing, and Reporting | 1 | LS | $ 3,700.00 | $ 3,700.00 | $ 12,500.00 | $ 12,500.00 | $8,500.00 | $ 8,500.00 | $ 3,480.00 | $ 3,480.00 | $ 5,500.00 | $ 5,500.00 | $ 2,000.00 | $ 2,000.00 | $ 8,930.00 | $ 8,930.00 | $ - 0 | |
| 18 | Remove Asbestos Material, Friable | 9 | FOOT | $ 50.00 | $ 450.00 | $ 43.00 | $ 387.00 | $150.00 | $ 1,350.00 | $ 580.00 | $ 5,220.00 | $ 200.00 | $ 1,800.00 | $ 100.00 | $ 900.00 | $ 1,542.00 | $ 13,878.00 | $ - 0 | |
| 19 | Remove Asbestos Material, Friable | 3 | SQFT | $ 96.00 | $ 288.00 | $ 43.00 | $ 129.00 | $256.00 | $ 768.00 | $ 1,740.00 | $ 5,220.00 | $ 575.00 | $ 1,725.00 | $ 100.00 | $ 300.00 | $ 1,542.00 | $ 4,626.00 | $ - 0 | |
| 20 | Removal of structures and obstructions | 1 | LS | $ 1,500.00 | $ 1,500.00 | $ 29,000.00 | $ 29,000.00 | $1,036.99 | $ 1,036.99 | $ 22,400.00 | $ 22,400.00 | $ 14,795.00 | $ 14,795.00 | $ 10,000.00 | $ 10,000.00 | $ 38,650.00 | $ 38,650.00 | $ - 0 | |
| 21 | Loose Riprap, Class 50 | 10 | CY | $ 140.00 | $ 1,400.00 | $ 150.00 | $ 1,500.00 | $119.50 | $ 1,195.00 | $ 140.00 | $ 1,400.00 | $ 150.00 | $ 1,500.00 | $ 300.00 | $ 3,000.00 | $ 397.00 | $ 3,970.00 | $ - 0 | |
| 22 | Loose Riprap, Class 100 | 10 | CY | $ 175.00 | $ 1,750.00 | $ 150.00 | $ 1,500.00 | $125.00 | $ 1,250.00 | $ 140.00 | $ 1,400.00 | $ 150.00 | $ 1,500.00 | $ 300.00 | $ 3,000.00 | $ 397.00 | $ 3,970.00 | $ - 0 | |
| 23 | Rehabilitate 18" culvert | 833 | FOOT | $ 335.00 | $ 279,055.00 | $ 225.00 | $ 187,425.00 | $279.45 | $ 232,781.85 | $ 300.00 | $ 249,900.00 | $ 295.00 | $ 245,735.00 | $ 350.00 | $ 291,550.00 | $ 168.15 | $ 140,068.95 | $ - 0 | |
| 24 | Rehabilitate 24" culvert | 404 | FOOT | $ 365.00 | $ 147,460.00 | $ 315.00 | $ 127,260.00 | $305.10 | $ 123,260.40 | $ 255.00 | $ 103,020.00 | $ 390.00 | $ 157,560.00 | $ 425.00 | $ 171,700.00 | $ 204.25 | $ 82,517.00 | $ - 0 | |
| 25 | Rehabilitate 36" culvert | 168 | FOOT | $ 512.00 | $ 86,016.00 | $ 575.00 | $ 96,600.00 | $711.45 | $ 119,523.60 | $ 485.00 | $ 81,480.00 | $ 648.00 | $ 108,864.00 | $ 725.00 | $ 121,800.00 | $ 517.75 | $ 86,982.00 | $ - 0 | |
| 26 | Mainline Video Inspection | 2810 | FOOT | $ 7.23 | $ 20,316.30 | $ 10.00 | $ 28,100.00 | $16.00 | $ 44,960.00 | $ 12.00 | $ 33,720.00 | $ 11.00 | $ 30,910.00 | $ 20.00 | $ 56,200.00 | $ 21.55 | $ 60,555.50 | $ - 0 | |
| 27 | 18 inch culvert Pipe, 5 ft depth | 44 | FOOT | $ 360.00 | $ 15,840.00 | $ 700.00 | $ 30,800.00 | $228.90 | $ 10,071.60 | $ 560.00 | $ 24,640.00 | $ 475.00 | $ 20,900.00 | $ 400.00 | $ 17,600.00 | $ 3,824.00 | $ 168,256.00 | $ - 0 | |
| 28 | 24 inch culvert pipe, 5 ft depth | 8 | FOOT | $ 580.00 | $ 4,640.00 | $ 1,000.00 | $ 8,000.00 | $239.41 | $ 1,915.28 | $ 1,060.00 | $ 8,480.00 | $ 867.00 | $ 6,936.00 | $ 600.00 | $ 4,800.00 | $ 4,820.00 | $ 38,560.00 | $ - 0 | |
| 29 | 36 inch culvert pipe, 5 ft depth | 6 | FOOT | $ 770.00 | $ 4,620.00 | $ 1,500.00 | $ 9,000.00 | $750.00 | $ 4,500.00 | $ 1,520.00 | $ 9,120.00 | $ 925.00 | $ 5,550.00 | $ 800.00 | $ 4,800.00 | $ 5,774.00 | $ 34,644.00 | $ - 0 | |
| 30 | Concrete inlet, Type D | 1 | EACH | $ 2,250.00 | $ 2,250.00 | $ 10,500.00 | $ 10,500.00 | $5,356.56 | $ 5,356.56 | $ 7,690.00 | $ 7,690.00 | $ 12,657.00 | $ 12,657.00 | $ 5,000.00 | $ 5,000.00 | $ 35,550.00 | $ 35,550.00 | $ - 0 | |
| 31 | Trench Resurfacing | 5 | SQYD | $ 170.00 | $ 850.00 | $ 600.00 | $ 3,000.00 | $850.00 | $ 4,250.00 | $ 1,520.00 | $ 7,600.00 | $ 295.00 | $ 1,475.00 | $ 500.00 | $ 2,500.00 | $ 3,500.00 | $ 17,500.00 | $ - 0 | |
| 32 | Culvert Drainage Markers, Type 1 | 21 | EACH | $ 195.00 | $ 4,095.00 | $ 200.00 | $ 4,200.00 | $250.00 | $ 5,250.00 | $ 250.00 | $ 5,250.00 | $ 195.00 | $ 4,095.00 | $ 300.00 | $ 6,300.00 | $ 400.00 | $ 8,400.00 | $ - 0 | |
| 33 | Culvert Drainage Markers, Type 2 | 21 | EACH | $ 195.00 | $ 4,095.00 | $ 200.00 | $ 4,200.00 | $250.00 | $ 5,250.00 | $ 215.00 | $ 4,515.00 | $ 195.00 | $ 4,095.00 | $ 400.00 | $ 8,400.00 | $ 456.00 | $ 9,576.00 | $ - 0 | |
| 34 | Permanent Seeding | 1 | LS | $ 750.00 | $ 750.00 | $ 3,400.00 | $ 3,400.00 | $1,800.00 | $ 1,800.00 | $ 3,940.00 | $ 3,940.00 | $ 1,596.00 | $ 1,596.00 | $ 2,000.00 | $ 2,000.00 | $ 6,370.00 | $ 6,370.00 | $ - 0 | |
| TOTAL | $ 750,746.30 | $ 788,380.00 | $ 861,742.63 | $ 897,716.00 | $ 905,010.00 | $ 933,800.00 | $ 1,631,369.00 | $ - 0 |