00016170 Preliminary Results.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
OR 82: Wallowa to Joseph Culvert Repair Project
Solicitation number
S-73000-00016170
Issued by
Wasco County, Oregon

About this file

This is a bid tabulation document for an Invitation to Bid (ITB) issued by the State of Oregon for the OR:82 Wallowa to Joseph Culvert Repair Project, with ITB number S-73000-00016170. The project involves comprehensive culvert rehabilitation and repair work, including the removal of asbestos materials, temporary traffic control measures, water management, erosion control, and the rehabilitation or replacement of 18-inch, 24-inch, and 36-inch culverts along a specified corridor. The estimated quantities include 833 linear feet of 18-inch culvert rehabilitation, 404 linear feet of 24-inch culvert rehabilitation, 168 linear feet of 36-inch culvert rehabilitation, mainline video inspection of 2,810 linear feet, installation of culvert pipe sections, concrete inlet construction, trench resurfacing, and permanent seeding. The bid closing date was April 16, 2026, at 10:00 AM. Seven contractors submitted bids: Papaya Contracting LLC, HP Civil Inc., JR Carlon Corp, Whitaker Construction Company, Jesse Rodriguez Construction LLC, Wildish Standard Paving Co, and Central Oregon Homes.

The bid tabulation reflects significant price variation among bidders across all line items, with total project bids ranging from $750,746.30 to $1,631,369.00. Notable pricing disparities appear in specialized items such as the 18-inch culvert pipe installation, where unit prices ranged from $228.90 to $3,824.00 per linear foot, and the Concrete Inlet Type D, where bids ranged from $2,250.00 to $35,550.00. Mobilization costs ranged from $50,000.00 to $243,750.00, while culvert rehabilitation rates varied substantially by diameter, indicating different contractor methodologies and resource allocations. The tabulation document explicitly notes that this bid tabulation is not an indicator of award and serves only as a compilation of submitted bids for consideration by the contracting agency.

View the file

Other files

File Type Posted
00016170 Exhibit 6 Plans.pdf PDF
00016170 Attachment A Form A2 Pricing Form.xlsx XLSX spreadsheet
00016170 Exhibit 5 Specifications.docx DOCX document
00016170 Invitation To Bid.docx DOCX document
00016170 Sample Contract.docx DOCX document
00016170 Addendum 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:4/16/26
ITB No.S-73000-00016170BIDDER
NAME:Papaya Contracting LLCHP Civil Inc.JR Carlon CorpWhitaker Construction CompanyJesse Rodriguez Construction LLCWildish Standard Paving CoCentral Oregon Homes
Bid Closing:04/16/2026 @ 10:00 AM
Description:OR:82 Wallowa To Joseph Culvert Repair Project
This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$50,000.00$ 50,000.00$ 78,838.00$ 78,838.00$126,838.75$ 126,838.75$100,000.00$ 100,000.00$89,000.00$ 89,000.00$93,000.00$ 93,000.00$ 243,750.00$ 243,750.00$ - 0
2Temporary Protection and Direction of Traffic1LS$ 50,000.00$ 50,000.00$ 94,000.00$ 94,000.00$75,000.00$ 75,000.00$ 81,700.00$ 81,700.00$ 95,000.00$ 95,000.00$ 50,000.00$ 50,000.00$ 198,814.15$ 198,814.15$ - 0
3Temporary Signs236SQFT$ 21.00$ 4,956.00$ 10.00$ 2,360.00$14.85$ 3,504.60$ 21.00$ 4,956.00$ 22.00$ 5,192.00$ 40.00$ 9,440.00$ 51.40$ 12,130.40$ - 0
4Flaggers480HOURS$ 75.00$ 36,000.00$ 92.00$ 44,160.00$114.75$ 55,080.00$ 75.00$ 36,000.00$ 107.00$ 51,360.00$ 100.00$ 48,000.00$ 146.40$ 70,272.00$ - 0
5Flagger Station Lighting1EACH$ 450.00$ 450.00$ 1.00$ 1.00$1,500.00$ 1,500.00$ 5,600.00$ 5,600.00$ 500.00$ 500.00$ 4,000.00$ 4,000.00$ 1,587.00$ 1,587.00$ - 0
6Automated Flagger Assistance Device2EACH$ 6,000.00$ 12,000.00$ 1,000.00$ 2,000.00$2,200.00$ 4,400.00$ 4,100.00$ 8,200.00$ 5,500.00$ 11,000.00$ 2,000.00$ 4,000.00$ 7,070.00$ 14,140.00$ - 0
7Temporary Water Management, MP 50.411LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
8Temporary Water Management, MP 50.771LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
9Temporary Water Management, MP 51.041LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 9,500.00$ 9,500.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
10Temporary Water Management, MP 51.171LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
11Temporary Water Management, MP 53.501LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
12Temporary Water Management, MP 61.321LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 3,575.00$ 3,575.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
13Temporary Water Management, MP 61.421LS$ 2,000.00$ 2,000.00$ 1,000.00$ 1,000.00$2,250.00$ 2,250.00$ 9,000.00$ 9,000.00$ 3,575.00$ 3,575.00$ 1,000.00$ 1,000.00$ 44,500.00$ 44,500.00$ - 0
14Erosion Control1LS$ 2,500.00$ 2,500.00$ 1,000.00$ 1,000.00$1,200.00$ 1,200.00$ 8,880.00$ 8,880.00$ 4,750.00$ 4,750.00$ 4,000.00$ 4,000.00$ 11,540.00$ 11,540.00$ - 0
15Pollution Control Plan1LS$ 1,000.00$ 1,000.00$ 500.00$ 500.00$1,200.00$ 1,200.00$ 3,000.00$ 3,000.00$ 750.00$ 750.00$ 2,000.00$ 2,000.00$ 1,198.00$ 1,198.00$ - 0
16Contaminated Soil Disposal17TON$ 45.00$ 765.00$ 60.00$ 1,020.00$250.00$ 4,250.00$ 465.00$ 7,905.00$ 95.00$ 1,615.00$ 30.00$ 510.00$ 202.00$ 3,434.00$ - 0
17Bulk Asbestos Sampling, Analytical Testing, and Reporting1LS$ 3,700.00$ 3,700.00$ 12,500.00$ 12,500.00$8,500.00$ 8,500.00$ 3,480.00$ 3,480.00$ 5,500.00$ 5,500.00$ 2,000.00$ 2,000.00$ 8,930.00$ 8,930.00$ - 0
18Remove Asbestos Material, Friable9FOOT$ 50.00$ 450.00$ 43.00$ 387.00$150.00$ 1,350.00$ 580.00$ 5,220.00$ 200.00$ 1,800.00$ 100.00$ 900.00$ 1,542.00$ 13,878.00$ - 0
19Remove Asbestos Material, Friable3SQFT$ 96.00$ 288.00$ 43.00$ 129.00$256.00$ 768.00$ 1,740.00$ 5,220.00$ 575.00$ 1,725.00$ 100.00$ 300.00$ 1,542.00$ 4,626.00$ - 0
20Removal of structures and obstructions1LS$ 1,500.00$ 1,500.00$ 29,000.00$ 29,000.00$1,036.99$ 1,036.99$ 22,400.00$ 22,400.00$ 14,795.00$ 14,795.00$ 10,000.00$ 10,000.00$ 38,650.00$ 38,650.00$ - 0
21Loose Riprap, Class 5010CY$ 140.00$ 1,400.00$ 150.00$ 1,500.00$119.50$ 1,195.00$ 140.00$ 1,400.00$ 150.00$ 1,500.00$ 300.00$ 3,000.00$ 397.00$ 3,970.00$ - 0
22Loose Riprap, Class 10010CY$ 175.00$ 1,750.00$ 150.00$ 1,500.00$125.00$ 1,250.00$ 140.00$ 1,400.00$ 150.00$ 1,500.00$ 300.00$ 3,000.00$ 397.00$ 3,970.00$ - 0
23Rehabilitate 18" culvert833FOOT$ 335.00$ 279,055.00$ 225.00$ 187,425.00$279.45$ 232,781.85$ 300.00$ 249,900.00$ 295.00$ 245,735.00$ 350.00$ 291,550.00$ 168.15$ 140,068.95$ - 0
24Rehabilitate 24" culvert404FOOT$ 365.00$ 147,460.00$ 315.00$ 127,260.00$305.10$ 123,260.40$ 255.00$ 103,020.00$ 390.00$ 157,560.00$ 425.00$ 171,700.00$ 204.25$ 82,517.00$ - 0
25Rehabilitate 36" culvert168FOOT$ 512.00$ 86,016.00$ 575.00$ 96,600.00$711.45$ 119,523.60$ 485.00$ 81,480.00$ 648.00$ 108,864.00$ 725.00$ 121,800.00$ 517.75$ 86,982.00$ - 0
26Mainline Video Inspection2810FOOT$ 7.23$ 20,316.30$ 10.00$ 28,100.00$16.00$ 44,960.00$ 12.00$ 33,720.00$ 11.00$ 30,910.00$ 20.00$ 56,200.00$ 21.55$ 60,555.50$ - 0
2718 inch culvert Pipe, 5 ft depth44FOOT$ 360.00$ 15,840.00$ 700.00$ 30,800.00$228.90$ 10,071.60$ 560.00$ 24,640.00$ 475.00$ 20,900.00$ 400.00$ 17,600.00$ 3,824.00$ 168,256.00$ - 0
2824 inch culvert pipe, 5 ft depth8FOOT$ 580.00$ 4,640.00$ 1,000.00$ 8,000.00$239.41$ 1,915.28$ 1,060.00$ 8,480.00$ 867.00$ 6,936.00$ 600.00$ 4,800.00$ 4,820.00$ 38,560.00$ - 0
2936 inch culvert pipe, 5 ft depth6FOOT$ 770.00$ 4,620.00$ 1,500.00$ 9,000.00$750.00$ 4,500.00$ 1,520.00$ 9,120.00$ 925.00$ 5,550.00$ 800.00$ 4,800.00$ 5,774.00$ 34,644.00$ - 0
30Concrete inlet, Type D1EACH$ 2,250.00$ 2,250.00$ 10,500.00$ 10,500.00$5,356.56$ 5,356.56$ 7,690.00$ 7,690.00$ 12,657.00$ 12,657.00$ 5,000.00$ 5,000.00$ 35,550.00$ 35,550.00$ - 0
31Trench Resurfacing5SQYD$ 170.00$ 850.00$ 600.00$ 3,000.00$850.00$ 4,250.00$ 1,520.00$ 7,600.00$ 295.00$ 1,475.00$ 500.00$ 2,500.00$ 3,500.00$ 17,500.00$ - 0
32Culvert Drainage Markers, Type 121EACH$ 195.00$ 4,095.00$ 200.00$ 4,200.00$250.00$ 5,250.00$ 250.00$ 5,250.00$ 195.00$ 4,095.00$ 300.00$ 6,300.00$ 400.00$ 8,400.00$ - 0
33Culvert Drainage Markers, Type 221EACH$ 195.00$ 4,095.00$ 200.00$ 4,200.00$250.00$ 5,250.00$ 215.00$ 4,515.00$ 195.00$ 4,095.00$ 400.00$ 8,400.00$ 456.00$ 9,576.00$ - 0
34Permanent Seeding1LS$ 750.00$ 750.00$ 3,400.00$ 3,400.00$1,800.00$ 1,800.00$ 3,940.00$ 3,940.00$ 1,596.00$ 1,596.00$ 2,000.00$ 2,000.00$ 6,370.00$ 6,370.00$ - 0
TOTAL$ 750,746.30$ 788,380.00$ 861,742.63$ 897,716.00$ 905,010.00$ 933,800.00$ 1,631,369.00$ - 0

File details come from the government source that posted it. Updated .