00014475 Bid Results.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- ER US101: MP315. 89, MP332. 5 & MP344. 44 Horizontal Drains State and local contract opportunity
- Solicitation number
- S-73000-00014475
- Issued by
- Crook County, Oregon
About this file
This document is a bid results spreadsheet for the Oregon Department of Transportation (ODOT) for an emergency relief highway drainage infrastructure project along US Highway 101 in Curry County. The project involves horizontal drain installations at three specific mileposts (315.89, 332.5, and 344.44), with two bidders - Granite Construction Company and HP Civil, Inc. - submitting competitive proposals by the bid closing date of August 20, 2025, at 10:00 AM. The project scope includes multiple line items such as mobilization, temporary access roads, erosion control, horizontal drains, steel casing, storm sewer pipes, pipe slope anchors, and associated construction activities, totaling approximately 52,580 linear feet of horizontal drain and pipe work.
The bid tabulation reveals significant pricing variations between the two contractors, with Granite Construction Company submitting a total bid of $5,412,635 and HP Civil, Inc. proposing $6,582,880. The project is federally funded through the Emergency Relief Program, subject to federal contracting requirements including Davis-Bacon Act prevailing wage rates and Buy America provisions. Additional requirements include 12% of work hours performed by apprentices, BOLI certification, disadvantaged business enterprise (DBE) outreach, and substantial completion mandated by November 21, 2025, with liquidated damages of $1,100 per calendar day for delays. Bidders were required to provide a 10% bid bond and will need to furnish performance and payment bonds at 100% of the contract price.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment H Apprenticeship Requirements.docx | DOCX document | |
| ATT C Bid Pricing Form~14.xlsx | XLSX spreadsheet | |
| 00014475 Invitation to Bid.docx | DOCX document | |
| ATT I FHWA Form 1273~1.pdf | ||
| Attachment B Plans~8.pdf | ||
| ATT G Project Wage Rates~2.pdf | ||
| Attachment A Special Provisions and Specifications~7.pdf | ||
| 7055 Contract_Executed.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 8/20/25 | |||||
| ITB No. | S-73000-00014475 | BIDDER | ||||
| NAME: | Granite Construction Company | HP Civil, Inc. | ||||
| Bid Closing: | 8/20/2025 at 10:00 AM | CITY/STATE: | Vancouver, WA | Salem, OR | ||
| Description: | ER US101: MP315.89, MP332.5 & MP344.44 Horizontal Drains | CCB# | 101195 | 202060 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| US101: MP315.89 Horizontal Drains | |||||||
| 1 | Mobilization | 1 | LS | 150,000.00 | $150,000.00 | $230,000.00 | $230,000.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | 45,000.00 | $45,000.00 | $30,000.00 | $30,000.00 |
| 3 | Flaggers | 100 | HR | 135.00 | $13,500.00 | $90.00 | $9,000.00 |
| 4 | Temporary Access Road | 1 | LS | 168,000.00 | $168,000.00 | $850,000.00 | $850,000.00 |
| 5 | Erosion Control | 1 | LS | 30,000.00 | $30,000.00 | $41,000.00 | $41,000.00 |
| 6 | Pollution Control Plan | 1 | LS | 500.00 | $500.00 | $1,000.00 | $1,000.00 |
| 7 | Construction Survey Work | 1 | LS | 5,000.00 | $5,000.00 | $12,500.00 | $12,500.00 |
| 8 | Horizontal Drains | 16,080 | FT | 45.00 | $723,600.00 | $41.00 | $659,280.00 |
| 9 | Steel Casing | 1,020 | FT | 100.00 | $102,000.00 | $100.00 | $102,000.00 |
| 10 | Drain Orientation Readings | 15 | EA | 500.00 | $7,500.00 | $500.00 | $7,500.00 |
| 11 | 12 Inch Storm Sewer Pipe (HDPE) | 424 | FT | 280.00 | $118,720.00 | $70.00 | $29,680.00 |
| 12 | 24 Inch Storm Sewer Pipe (HDPE) | 407 | FT | 575.00 | $234,025.00 | $110.00 | $44,770.00 |
| 13 | 8 Inch Storm Sewer Pipe, Assembly | 9 | EA | 7,500.00 | $67,500.00 | $2,000.00 | $18,000.00 |
| 14 | Pipe Slope Anchor, Metal, 12 Inch | 25 | EA | 1,000.00 | $25,000.00 | $2,900.00 | $72,500.00 |
| 15 | Pipe Slope Anchor, Metal, 24 Inch | 24 | EA | 1,200.00 | $28,800.00 | $4,500.00 | $108,000.00 |
| 16 | Pipe Wyes, 12 inch x 24 Inch | 4 | EA | 10,000.00 | $40,000.00 | $4,000.00 | $16,000.00 |
| US101: MP332.55 Horizontal Drains | |||||||
| 17 | Mobilization | 1 | LS | 205,000.00 | $205,000.00 | $262,000.00 | $262,000.00 |
| 18 | Temporary Access Road | 1 | LS | 376,000.00 | $376,000.00 | $785,000.00 | $785,000.00 |
| 19 | Erosion Control | 1 | LS | 35,000.00 | $35,000.00 | $45,000.00 | $45,000.00 |
| 20 | Pollution Control Plan | 1 | LS | 500.00 | $500.00 | $1,000.00 | $1,000.00 |
| 21 | Construction Survey Work | 1 | LS | 5,000.00 | $5,000.00 | $150,000.00 | $150,000.00 |
| 22 | Horizontal Drains | 22,100 | FT | 45.00 | $994,500.00 | $41.00 | $906,100.00 |
| 23 | Steel Casing | 1,840 | FT | 100.00 | $184,000.00 | $100.00 | $184,000.00 |
| 24 | Drain Orientation Readings | 28 | EA | 500.00 | $14,000.00 | $500.00 | $14,000.00 |
| 25 | 12 Inch Storm Sewer Pipe (HDPE) | 1,040 | FT | 280.00 | $291,200.00 | $50.00 | $52,000.00 |
| 26 | 8 Inch Storm Sewer Pipe, Assembly | 16 | EA | 7,500.00 | $120,000.00 | $2,000.00 | $32,000.00 |
| 27 | Pipe Slope Anchor, Metal, 12 Inch | 62 | EA | 1,200.00 | $74,400.00 | $3,000.00 | $186,000.00 |
| 28 | Pipe Wyes, 12 inch x 12 Inch | 3 | EA | 2,500.00 | $7,500.00 | $3,200.00 | $9,600.00 |
| US101: MP344.44 Horizontal Drains | |||||||
| 29 | Mobilization | 1 | LS | 125,000.00 | $125,000.00 | $170,000.00 | $170,000.00 |
| 30 | Temporary Work Zone Traffic Control, Complete | 1 | LS | 45,000.00 | $45,000.00 | $35,000.00 | $35,000.00 |
| 31 | Flaggers | 50 | HR | 135.00 | $6,750.00 | $90.00 | $4,500.00 |
| 32 | Temporary Access Road | 1 | LS | 142,000.00 | $142,000.00 | $630,000.00 | $630,000.00 |
| 33 | Erosion Control | 1 | LS | 25,000.00 | $25,000.00 | $40,000.00 | $40,000.00 |
| 34 | Pollution Control Plan | 1 | LS | 500.00 | $500.00 | $1,000.00 | $1,000.00 |
| 35 | Construction Survey Work | 1 | LS | 5,000.00 | $5,000.00 | $15,000.00 | $15,000.00 |
| 36 | Horizontal Drains | 14,400 | FT | 45.00 | $648,000.00 | $41.00 | $590,400.00 |
| 37 | Steel Casing | 960 | FT | 100.00 | $96,000.00 | $100.00 | $96,000.00 |
| 38 | Drain Orientation Readings | 14 | EA | 500.00 | $7,000.00 | $500.00 | $7,000.00 |
| 39 | 12 Inch Storm Sewer Pipe (HDPE) | 523 | FT | 280.00 | $146,440.00 | $50.00 | $26,150.00 |
| 40 | 8 Inch Storm Sewer Pipe, Assembly | 8 | EA | 7,500.00 | $60,000.00 | $2,000.00 | $16,000.00 |
| 41 | Pipe Slope Anchor, Metal, 12 Inch | 31 | EA | 1,200.00 | $37,200.00 | $2,900.00 | $89,900.00 |
| 42 | Pipe Wyes, 12 inch x 12 Inch | 1 | EA | 2,500.00 | $2,500.00 | $4,000.00 | $4,000.00 |
| TOTAL | $ 5,412,635.00 | $ 6,582,880.00 |