00014363 Bid Results.xlsx
XLSX spreadsheet 24 KB Posted
- Solicitation number
- S-73000-00014363
- Issued by
- Coos County, Oregon
About this file
This is a bid results spreadsheet from the Oregon Department of Transportation (ODOT) for an emergency culvert repair project (ITB No. S-73000-00014363) located on US Highway 101 at milepost 281.85 in Coos County. The project involves replacing a failed culvert with a new fish passage culvert, with Farline Bridge, Inc. submitting the sole bid on August 7, 2025, at 2:00 pm. The comprehensive project includes 36 bid line items covering mobilization, traffic control, temporary water management, erosion control, culvert installation, and streambed enhancement. The bid documents specify a substantial completion date of September 26, 2025, with final completion by October 3, 2025, and restrict in-water work to the period between July 15 and September 30.
The total bid price submitted by Farline Bridge, Inc. is $1,250,793.20, with significant line items including a $172,000 culvert pipe installation, $125,000 for mobilization, and $175,000 for streambed enhancement. The project is funded through the Federal Highway Administration's Emergency Relief (ER) Program and is subject to federal and state regulations, including domestic preference requirements for steel and manufactured products. Contractors must provide performance and payment bonds for 100% of the contract price and comply with prevailing wage rates from both the Oregon Bureau of Labor and Industries and the Davis-Bacon Act. The project requires specialized technical capabilities in infrastructure construction, environmental mitigation, and culvert installation, with strict environmental and traffic management constraints.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ATT C Bid Pricing Form~11.xlsx | XLSX spreadsheet | |
| ATT B Plans~25.pdf | ||
| CUBIC SOLE SOURCE PUBLIC NOTICE.pdf | ||
| ATT A Special Provisions and Specifications~32.pdf | ||
| ATT D Project Wage Rates~3.pdf | ||
| 00014363 Invitation to Bid.docx | DOCX document | |
| ATT E FHWA Form 1273.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 8/7/25 | ||||
| ITB No. | S-73000-00014363 | BIDDER | |||
| NAME: | Farline Bridge, Inc. | ||||
| Bid Closing: | 8/7/2025 at 2:00 pm | CITY/STATE: | Stayton, OR | ||
| Description: | ER US101: MP281.85 Bearhead Mountain Lane Culvert | CCB# | 194787 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $125,000.00 | $ 125,000.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $50,000.00 | $ 50,000.00 |
| 3 | Potable Changeable Message Signs | 4 | EA | $5,000.00 | $ 20,000.00 |
| 4 | Flaggers | 1700 | HR | $79.00 | $ 134,300.00 |
| 5 | Flagger Station Lighting | 2 | EA | $5,000.00 | $ 10,000.00 |
| 6 | Temoporary Water Management Facility | 1 | LS | $40,850.00 | $ 40,850.00 |
| 7 | Bypass Pumping Monitoring | 21 | DAY | $850.00 | $ 17,850.00 |
| 8 | Erosion Control | 1 | LS | $10,000.00 | $ 10,000.00 |
| 9 | Sediment Barrier, Type 3 | 100 | FT | $10.00 | $ 1,000.00 |
| 10 | Pollution Control Plan | 1 | LS | $2,500.00 | $ 2,500.00 |
| 11 | Construction Survey Work | 1 | LS | $8,700.00 | $ 8,700.00 |
| 12 | Removal of Structures and Obstructions | 1 | LS | $15,000.00 | $ 15,000.00 |
| 13 | Clearing and Grubbing | 1 | LS | $50,000.00 | $ 50,000.00 |
| 14 | Stone Embankment | 350 | CUYD | $98.64 | $ 34,524.00 |
| 15 | Riprap Geotextile, Type 1 | 190 | SQYD | $7.00 | $ 1,330.00 |
| 16 | Subgrade Geotextile | 450 | SQYD | $2.00 | $ 900.00 |
| 17 | Loose Riprap, Class 2000 | 24 | CUYD | $184.00 | $ 4,416.00 |
| 18 | Installing 114 Inch (137 x 87) Arch Culvert Pipe (Agency Supplied) | 86 | FT | $2,000.00 | $ 172,000.00 |
| 19 | Filling Abandoned Structures | 1 | EA | $30,000.00 | $ 30,000.00 |
| 20 | Structure Excavation | 870 | CUYD | $92.59 | $ 80,553.30 |
| 21 | Granular Structure Backfill | 210 | CUYD | $139.84 | $ 29,366.40 |
| 22 | Reinforcement, Grade 60 | 12000 | LB | $1.50 | $ 18,000.00 |
| 23 | Granular Structural Concrete, Class 3300 | 44 | CUYD | $1,800.00 | $ 79,200.00 |
| 24 | Cold Plane Pavement Removal, 3" Deep | 470 | SQYD | $22.00 | $ 10,340.00 |
| 25 | Aggregate Base | 350 | TONS | $127.89 | $ 44,761.50 |
| 26 | Level 3, 1/2 Inch ACP Mixture | 380 | TONS | $200.00 | $ 76,000.00 |
| 27 | Delineators, Type 1 | 4 | EA | $135.00 | $ 540.00 |
| 28 | Culvert Drainage Markers, Type 1 | 2 | EA | $160.00 | $ 320.00 |
| 29 | Culvert Drainage Markers, Type 2 | 1 | EA | $425.00 | $ 425.00 |
| 30 | Bi-Directional Yellow Type IAR Markers | 6 | EA | $35.00 | $ 210.00 |
| 31 | Thermoplastic, Sprayed, Surface, Non-Profiled | 780 | FT | $3.15 | $ 2,457.00 |
| 32 | Permanent Seeding | 0.1 | ACRE | $5,000.00 | $ 500.00 |
| 33 | Multiple Mailbox Supports | 1 | EA | $1,200.00 | $ 1,200.00 |
| 34 | Mailbox Concrete Collars | 1 | EA | $50.00 | $ 50.00 |
| 35 | Streambed Enhancement | 1 | LS | $175,000.00 | $ 175,000.00 |
| 36 | Fish Rocks, Type 2 | 10 | EA | $350.00 | $ 3,500.00 |
| TOTAL | $ 1,250,793.20 |
File details come from the government source that posted it. Updated .