This is a bid results tabulation for an Oregon Department of Transportation highway construction project involving the I-5 corridor near Roseburg, Oregon. The project, designated ITB No. S-73000-00013901, encompasses a Maintenance and Improvement (MIM) drainage correction paving project spanning milepost 90.5 to 92.5 on Interstate 5. The scope of work includes mobilization, temporary traffic control, erosion control, drainage infrastructure installation, pavement removal, and resurfacing with asphalt concrete pavement (ACP). Key work items include approximately 6,800 square yards of cold plane pavement removal at 2 inches deep, 1,500 square yards at 4 inches deep, 2,000 square yards at 6 inches deep, 2,100 tons of Level 4, 1/2 inch ACP mixture, installation of 138 linear feet of 18-inch storm sewer pipe, three concrete inlets, and pavement markings totaling 7,000 linear feet. The bid closing date was June 25, 2025, at 2:30 p.m., with two bidders submitting proposals: LTM, Incorporated dba Knife River Materials of Roseburg, Oregon, and HP Civil Inc. of Salem, Oregon.
LTM, Incorporated submitted a total bid of $821,407.00, while HP Civil Inc. submitted a total bid of $1,144,961.11, representing a difference of $323,554.11 between the two bids. Notable pricing variations between bidders include temporary work zone traffic control, where HP Civil Inc. bid significantly higher at $245,000.00 compared to LTM's $64,235.00, and concrete inlet work, where HP Civil Inc. bid $30,000.00 versus LTM's $7,500.00. The bid tabulation document explicitly notes that this tabulation is not an indicator of award but serves only as a compilation of submitted bids for consideration. Both bidders hold Oregon construction licenses, with LTM holding CCB# 56603 and HP Civil Inc. holding CCB# 202060.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REQ-DASOBO-00131027_SolinstDataLoggers_OWRD_Approved.pdf | ||
| Notice of Special Procurement.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 6/25/25 | |||||
| ITB No. | S-73000-00013901 | BIDDER | ||||
| NAME: | LTM, Incorporated dba Knife River Materials | HP Civil Inc. | ||||
| Bid Closing: | 6/25/2025 at 2:30 pm | CITY/STATE: | Roseburg, OR | Salem, OR | ||
| Description: | I-5: MP 90.5 to MP 92.5 MIM Drainage Correction Paving Project | CCB# | 56603 | 202060 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1.0 | LS | $63,682.00 | $ 63,682.00 | $114,496.11 | $ 114,496.11 |
| 2 | TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE | 1.0 | LS | $64,235.00 | $ 64,235.00 | $245,000.00 | $ 245,000.00 |
| 3 | PORTABLE CHANGEABLE MESSAGE SIGNS | 2.0 | EACH | $3,000.00 | $ 6,000.00 | $2,000.00 | $ 4,000.00 |
| 4 | EROSION CONTROL | 1.0 | LS | $500.00 | $ 500.00 | $500.00 | $ 500.00 |
| 5 | INLET PROTECTION, TYPE 3 | 5.0 | EACH | $150.00 | $ 750.00 | $110.00 | $ 550.00 |
| 6 | POLLUTION CONTROL PLAN | 1.0 | LS | $500.00 | $ 500.00 | $500.00 | $ 500.00 |
| 7 | CONSTRUCTION SURVEY WORK | 1.0 | LS | $18,000.00 | $ 18,000.00 | $10,000.00 | $ 10,000.00 |
| 8 | RIPRAP GEOTEXTILE, TYPE 1 | 100.0 | SQYD | $6.00 | $ 600.00 | $7.50 | $ 750.00 |
| 9 | LOOSE RIPRAP, CLASS 50 | 10.0 | CUYD | $300.00 | $ 3,000.00 | $450.00 | $ 4,500.00 |
| 10 | MAINLINE VIDEO INSPECTION | 150.0 | FOOT | $24.00 | $ 3,600.00 | $15.00 | $ 2,250.00 |
| 11 | 18 INCH STORM SEWER PIPE, 5 FT DEPTH | 138.0 | FOOT | $415.00 | $ 57,270.00 | $515.00 | $ 71,070.00 |
| 12 | CONCRETE INLETS, TYPE G-2 | 3.0 | EACH | $2,500.00 | $ 7,500.00 | $10,000.00 | $ 30,000.00 |
| 13 | TRENCH RESURFACING | 92.0 | SQYD | $350.00 | $ 32,200.00 | $275.00 | $ 25,300.00 |
| 14 | AMG COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 6800.0 | SQYD | $14.00 | $ 95,200.00 | $14.75 | $ 100,300.00 |
| 15 | AMG COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEP | 1500.0 | SQYD | $22.00 | $ 33,000.00 | $14.75 | $ 22,125.00 |
| 16 | AMG COLD PLANE PAVEMENT REMOVAL, 6 INCHES DEEP | 2000.0 | SQYD | $22.00 | $ 44,000.00 | $14.75 | $ 29,500.00 |
| 17 | LEVEL 4, 1/2 INCH ACP MIXTURE | 2100.0 | TON | $145.00 | $ 304,500.00 | $190.00 | $ 399,000.00 |
| 18 | MONO-DIRECTIONAL WHITE TYPE IAR MARKERS, RECESSED | 82.0 | EACH | $35.00 | $ 2,870.00 | $35.00 | $ 2,870.00 |
| 19 | PAVEMENT MARKING TAPE, GROOVED, PATTERNED, WET WEATHER | 7000.0 | FOOT | $12.00 | $ 84,000.00 | $11.75 | $ 82,250.00 |
| TOTAL | $ 821,407.00 | $ 1,144,961.11 |