00013705 Bid Results.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- S-X06001-00013704
- Issued by
- Coos County, Condon City, Oregon
About this file
This file is a Bid Results tabulation for Invitation to Bid (ITB) No. S-73000-00013705 issued by the State of Oregon for the ESB I-5 Exit 14 SB On Ramp Fence Project (ESB# 15419). The project involves construction work in Grants Pass, Oregon, with a bid closing date of May 14, 2025, at 2:00 PM. Five contractors submitted bids for the project: FLOLINE CONSTRUCTION (Grants Pass, OR), Draco Enterprises LLC (Jefferson, OR), NW INDUSTRIAL FLOORING, INC. DBA NW Pure Construction, Inc. (Boring, OR), Civil West Construction (Salem, OR), and Common Ground Excavation llc (Scotts Mills, OR). The scope of work includes five line items: mobilization, temporary work zone traffic control, installation of 60 feet of 12-inch culvert with a sloped end in an existing ditch line, installation of 252 feet of Type CL-6 chain link fence with three-strand barbed wire and one 12-foot chain link gate with three-strand barbed wire, and installation of 38 feet of three-strand barbed wire on existing fence.
Bid prices ranged significantly across the five contractors, with total project bids spanning from $17,960.00 (FLOLINE CONSTRUCTION) to $63,720.00 (Common Ground Excavation llc). The tabulation shows unit prices and total prices for each line item across all bidders, demonstrating substantial variation in pricing strategies, particularly for fence installation (ranging from $40.00 to $165.00 per foot) and culvert installation (ranging from $4,200.00 to $20,923.32). This bid tabulation is explicitly noted as not being an indicator of award but rather a summary of submitted bids for consideration. No incumbent vendor information, set-asides, funding sources, or contract term details are provided in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Police_Drone_Procurement_Spec_Sheet.docx | DOCX document | |
| RFQ Drone.docx | DOCX document | |
| RFQ Drone Evaluation Criteria.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 5/14/25 | ||||||||
| ITB No. | S-73000-00013705 | BIDDER | |||||||
| NAME: | FLOLINE CONSTRUCTION | Draco Enterprises LLC | NW INDUSTRIAL FLOORING, INC. DBA NW Pure Construction, Inc. | Civil West Construction | Common Ground Excavation llc | ||||
| Bid Closing: | 5/14/2025 at 2:00 pm | CITY/STATE: | Grants Pass OR | Jefferson, OR | Boring, OR | Salem, OR | Scotts Mills , OR | ||
| Description: | ESB I-5 Exit 14 SB On Ramp Fence Project | ESB# | 15419 | 14162 | 14083 | 14086 | 15498 | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | Mobilization | 1 | LS | $500.00 | $ 500.00 | $3,000.00 | $ 3,000.00 | $8,500.00 | $ 8,500.00 | $5,150.00 | $ 5,150.00 | $10,000.00 | $ 10,000.00 |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $1,000.00 | $ 1,000.00 | $3,000.00 | $ 3,000.00 | $4,000.00 | $ 4,000.00 | $5,156.94 | $ 5,156.94 | $3,000.00 | $ 3,000.00 |
| 3 | Install 60 ft of 12 inch Culvert with one (1) sloped end in Existing Ditch line | 1 | LS | $6,000.00 | $ 6,000.00 | $10,000.00 | $ 10,000.00 | $14,500.00 | $ 14,500.00 | $20,923.32 | $ 20,923.32 | $4,200.00 | $ 4,200.00 |
| 4 | Install Type CL-6 Chain Link Fence with 3 Strand Barbed Wire and (1) 12 ft Chain Link Gate with 3 Strands Barbed Wire. | 252 | FT | $40.00 | $ 10,080.00 | $35.00 | $ 8,820.00 | $68.00 | $ 17,136.00 | $71.47 | $ 18,010.44 | $165.00 | $ 41,580.00 |
| 5 | Install 38 feet of 3 Strands Barbed Wire on Existing Fence | 38 | FT | $10.00 | $ 380.00 | $30.00 | $ 1,140.00 | $25.00 | $ 950.00 | $57.60 | $ 2,188.80 | $130.00 | $ 4,940.00 |
| TOTAL | $ 17,960.00 | $ 25,960.00 | $ 45,086.00 | $ 51,429.50 | $ 63,720.00 |