00013661_RFB.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
R2 Paving RFB - OR228 MP0. 37-1. 33 Paving
Solicitation number
S-73000-00013361
Issued by
Lake County, Oregon

About this file

This document is a Request for Bid (RFB) from the Oregon Department of Transportation (ODOT) for an On-Call Region 2 Paving project located on OR228 from mile point 0.37 to 1.47. The project involves a 3-inch full-width overlay paving with 0"-3" CPPR at project start and end, covering approximately 0.96 miles. The bid is due on 4/15/2025 at 2:00 pm, with a required completion date of 6/30/2025. The project includes multiple work items such as mobilization, temporary work zone traffic control, pollution control plan, aggregate shoulders, cold plane pavement removal, asphalt mixture placement, and various pavement markings and striping.

The total project will be competitively bid with unit pricing for 12 distinct line items, including 3,894 tons of asphalt mixture and 20,045 linear feet of paint striping. The bid is subject to domestic preference requirements under ORS 279C.303 and prevailing wage rates dated January 5, 2025 for Linn County. Traffic lane closures are restricted during commute times (6 AM to 9 AM and 4 PM to 7 PM, Monday-Friday), with no holiday or weekend closures permitted. Portable Changeable Message Signs must be placed at least 7 days in advance of any lane closures, and contractors must submit a traffic control plan to the project manager.

View the file

Other files

File Type Posted
00013361_RFB_Amd2.xlsx XLSX spreadsheet
TYP Bike Path Paving.pdf PDF
6110-0 - LVT Sole Manufacturer.pdf PDF
00013661_RFB_Amd1~1.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule

REQUEST FOR BID AND RESULTING WORK ORDER
On-Call Region 2 Paving
INSTRUCTIONS: ODOT will fill in all information below except Contractor Information, Work Order Number (to be added upon award of Work Order), and pricing. ODOT will provide a list of bid items and their estimated quantities. Contractor must complete the Contractor Information section, including a signature, and insert unit and total prices for all bid items. Contractor must submit its bid by uploading the completed Request for Bid/Work Order form to the Attachments tab for the project in OregonBuys and entering the total bid price on the Items tab.

This request for bid and any resulting work order are subject to the domestic preference requirements of ORS 279C.303. See Project Specific Requirements section below for additional information.

Request for Bid Number: S-73000-00013361 Work Order Number:

Issue Date: 3/27/2025 Bid due date and time: 4/15/2025 2:00 pm

Project Name: OR228 MP0.37-1.47 Paving

Project description (include mile point locations): 3" full width overlay paving from MP0.37 (East end of Halsey where sidewalk turns to asphalt) to MP1.33 (west end of Spoon Creek Bridge). 0"-3" CPPR full width for 50' at start and end of project limits.

ODOT Project Manager Name and Phone number: Cody Stone
ODOT Project Manager Billing Address (may be an email): Cody.Stone@odot.oregon.gov

ODOT Site Representative (if different than ODOT Project Manager):

Required Completion Date: 6/30/2025

CONTRACTOR INFORMATION

Contractor (COMPANY) Legal Name:

Address:

Contact Person: Email:

Phone: CCB #:

Contractor's On-Call Region 2 Paving Price Agreement Number: PO-73000-

Contractor’s signature below indicates its firm offer to provide the Services described in this Work Order in accordance with all terms, conditions, and specifications contained in the Price Agreement referenced above, and any additional specifications contained within this Work Order and its attachments. The Work Order is not effective until it is signed by ODOT's Procurement Authority, and ODOT issues a notice to proceed.

Contractor Signature: Date:

ODOT Signature (Procurement Authority):Date:
ANTICIPATED WORK ITEMS (PAY ITEMS)
This Work Order indicates an estimate of services/quantities required. Payment to Contractor will be made based on actual quantities provided/performed:
ItemDescriptionEst. Qty.UnitUnit PriceTotal Price
1Mobilization1LS$ - 0
2Temporary Work Zone Traffic Control, Complete1LS$ - 0
3Pollution Control Plan1LS$ - 0
4Aggregate Shoulders267TON$ - 0
5Cold Plane Pavement Removal, 0"-3" Deep433SQYD$ - 0
6Level 3, 1/2" Dense ACP Mixture (PG64-22)3,894TON$ - 0
7Extra for Asphalt Approaches4EACH$ - 0
8Hi-Build Paint, Extruded or Sprayed, Surface20,045FOOT$ - 0
9Pavement Legend, Type AB, Arrows Elongated4EACH$ - 0
10Pavement Bar, Type AB24FOOT$ - 0
11Pavement Legend, Type AB, School1EACH$ - 0
12Continous Rumble Strips0.96MILE$ - 0
$ - 0
PROJECT SPECIFIC REQUIREMENTS

X This project requires compliance with the domestic preference requirements of ORS 279C.303. Contractor shall comply with Price Agreement Exhibit A - State Buy America Provisions.

X This project requires payment of the following prevailing wage rates, which are available online at http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx:

The “PREVAILING WAGE RATES for Public Works Contracts in Oregon” dated January 5, 2025

County where the work will be performed: Linn
The following attachments are incorporated into this Request for Bid and any resulting Work Order:

X One or more traffic lanes may be closed when allowed, shown, or directed during the following periods of time:

No closures during commute times. 6 AM to 9 AM and 4 PM to 7 PM, Monday - Friday No Holiday or weekend closures.

X Portable Changeable Message Signs (PCMS) shall be placed a minimum of 7 days in advance of any ramp or lane closure to alert the public of the closure. The location of the PCMS and the message on the PCMS shall be submitted to the Project Manager as part of the Contractor’s proposed TCP.

Traffic will be allowed on the cold planed surface up to ____ calendar days after removing the existing surface. Sweep and clean the cold planed surface before opening to traffic.

COMMENTS & SPECIAL INSTRUCTIONS:

File details come from the government source that posted it. Updated .