00013573 Att A Special Provisions.docx
DOCX document 46 KB Posted
- Attached to
- US 97: MP 22 - MP 25. 5 Inlay Paving
- Solicitation number
- S-73000-00013573
- Issued by
- Multnomah County, Oregon
About this file
This document is a Special Provisions attachment for an Oregon Department of Transportation (ODOT) highway paving project located on US 97 between mileposts 22 and 25.5, south of Moro, Oregon. The project involves cold plane pavement removal, asphalt concrete pavement repair, and HMAC (Hot Mix Asphalt Concrete) inlay with temporary pavement markers. ODOT will handle traffic control and permanent pavement marking. The work will be conducted on southbound and northbound lanes, with grinding depths ranging from 2.5 to 3.0 inches and varying lane widths from 33 to 45 feet. The project requires a preconstruction conference, and work must commence within 10 working days of the meeting, with single lane flagger-controlled closure allowed from 6am to 7pm Monday through Thursday.
The contract specifies payment for all work through bid schedule items, with no separate payments for unlisted items. There will be no retainage, and the contractor will be paid upon completion of contract work. The project uses the 2024 Oregon Standard Specifications for Construction, and contractors must comply with specific technical requirements including pavement smoothness testing, aggregate treatment, and anti-stripping additives. A smoothness price adjustment mechanism is included, with potential financial incentives or penalties based on the International Roughness Index (IRI) of the completed pavement. The project also includes specific requirements for utility notifications, traffic accommodations, bridge load restrictions, and pavement edge delineation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NOI Structured Juniper April 2025.pdf | ||
| 00013573 Prelim Bid Results.xlsx | XLSX spreadsheet | |
| 00013573 Invitation to Bid.docx | DOCX document | |
| 00013573 Att B Bid Pricing Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A – Special Provisions
PROJECT NAME: US 97: MP 22 – 25.5 Inlay Paving
SCOPE OF WORK: Work includes cold plane pavement removal, asphalt concrete pavement repair, HMAC inlay and temporary pavement markers. ODOT will perform traffic control and permanent pavement marking.
WORK LOCATION: The work is located on US 97, South of Moro.
PROJECT MANAGER:
Ramon Alonso 63055 N. Hwy 97. Bldg. M Bend, OR 97701 Phone: (541) 419-9481 Email: Ramon.ALONSO@odot.state.or.us
APPLICABLE SPECIFICATIONS: The Specifications which are applicable to the work on this project are the 2024 Oregon Standard Specifications for Construction (“Standard Specifications”), which are by this reference incorporated herein and the Special Provisions. The Standard Specifications include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Specifications. Sections of the technical specifications not identified in the Specifications remain applicable to the Contract according to their original terms.
Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Specifications as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
COOPERATION WITH UTILITIES: This project is located within the Oregon Utility Notification Center area, which is a utilities notification system for notifying owners of utilities about work being performed in the vicinity of their facilities. The contractor shall notify owners of Utilities prior to the performance of work in the vicinity of their Utilities. The utilities notification system telephone number is 811 (or use the old number which is 1-800-332-2344).
PAYMENT: Payment for all work under this contract is to be included in the bid items contained in the Bid Schedule. Payment constitutes full compensation to the Contractor for furnishing all Materials, Equipment, labor and incidentals necessary to complete the work as specified. There will be no separate payment for items not listed, as that work will be included in payment made for the items listed in the Bid Schedule.
PAYMENT TO CONTRACTOR: The Contractor shall be paid upon completion of contract work. A bill must be submitted to the Project Manager for payment processing. There shall be no retainage for work performed under this contract.
PRECONSTRUCTION CONFERENCE, SCHEDULE AND LIMITATIONS OF OPERATIONS: The Contractor shall meet with the Project Manager for a preconstruction conference at a mutually agreed upon time. Work shall commence within 10 working days of this meeting providing the Notice to Proceed has been received. At the preconstruction conference, submit a project schedule to plan, coordinate and control the progress of construction and traffic control installations. The project schedules will take into account the orderly, timely, and efficient prosecution of the work in sufficient detail to enable both the Contractor and the Project Manager to plan, coordinate, appraise, document, and control their respective contract responsibilities. The predicted Completion date(s) for the project schedule shall be within the specified contract time.
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.02(a) General Requirements - Add the following bullets to the end of the bullet list:
· Accommodate all over-dimensional loads through the work zone. Do not hold or delay over-dimensional loads for more than 20 minutes.
· When paving operations create an abrupt edge, protect traffic by installing a "DO NOT PASS" (R4‑1) sign before the Work Area at sign spacing "A" from the TCD Spacing Table" shown on the Standard Drawings. Alternate "ABRUPT EDGE" (CW21‑7) signs with appropriate (CW21‑8) rider and "DO NOT PASS" (R4‑1) signs at 1/2 mile spacings. Install a "BUMP" (W8‑1) sign 100 feet prior to the transverse paving edge.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
One or more Traffic Lanes may be closed on US 97 when allowed, shown, or directed during the following periods of time except as indicated in 00220.40(e)(2):
· Single lane flagger-controlled closure is allowed 6am – 7pm Monday – Thursday ODOT will provide traffic control, contractor and ODOT are to agree on work schedule prior to work starting.
Add the following subsection:
00220.41 Bridge Work - Before starting any grading or Pavement removal at Bridge ends or removal of Pavement from Bridge decks, arrange so that all Equipment, labor, and Materials required to complete the Pavement replacement Work and Bridge deck waterproofing Work are on hand or are guaranteed to be delivered. Once grading and Pavement removal begins, vigorously prosecute and complete this Work. Complete paving and membrane waterproofing Work in the shortest possible time.
Temporarily taper or bevel longitudinal and transverse grade changes or drop‑offs resulting from grading and Pavement removal and membrane waterproofing Work with asphalt concrete mixture to provide a smooth and safe transition. Construct tapers according to 00620.40.
Add the following subsection:
00220.45 Load Restrictions on Bridges - Limit the combined weight of construction vehicles, Equipment, and daily Material usage to 65,000 pounds for every 1,000 square feet of surface area plus the weight of long term storage of Materials to 25,000 pounds for every 100 square feet of surface area of the Bridge or a total of 200,000 pounds for each span of the Bridge, whichever is less.
The Contractor may request alternate loadings by submitting, 30 Calendar Days before proposed loadings, stamped loading calculations and data according to 00150.35.
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
Comply with Section 00223 of the Standard Specifications.
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications modified as follows:
00224.46 Pavement Edge Delineation - Replace the paragraph that begins “Place tubular or conical markers…” with the following paragraph:
Place tubular or conical markers to delineate the edge of Pavement immediately after construction Work or paving operations create an abrupt or sloped edge drop-off greater than 1 inch in height along the right hand or left hand Shoulder.
SECTION 00225 – TEMPORARY PAVEMENT MARKING
Comply with Section 00225 of the Standard Specifications.
SECTION 00305 - CONSTRUCTION SURVEY WORK
Comply with Section 00305 of the Standard Specifications.
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:
Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00745.51.
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
Comply with Section 00730 of the Standard Specifications modified as follows:
00730.11 Emulsified Asphalt – Replace the sentence that begins “Furnish CSS-1, CSS-1h…” with the following sentence:
Furnish CSS-1, CSS-1h, CMS-2, CMS-2S, CMS-2h, CRS-1, CRS-2, HFRS-2, HFMS-2 or HPTC as selected by the Contractor.
00730.80 Measurement - Replace this subsection, except for the subsection number and title, with the following:
The quantities of Emulsified Asphalt used as tack will be measured on the weight basis.
SECTION 00738 – SAFETY EDGE
Comply with Section 00738 of the Standard Specifications modified as follows:
00738.00 Scope – Add the following to the end of this section: Reference standard drawing RD 615 for safety edge construction details.
SECTION 00745 - ASPHALT CONCRETE PAVEMENT - STATISTICAL ACCEPTANCE
Comply with Section 00745 of the Standard Specifications modified as follows:
00745.02 Definitions -
Add the following definition:
Localized Roughness - An area that exceeds 160.0 inches per mile in a continuous International Roughness Index (IRI) evaluation over a 25.0-foot base length.
00745.11(b) Asphalt Cement Additives – Delete the bullet that begins “Anti-stripping asphalt cement…”
Add the following subsection:
00745.11(d) Aggregate Treatment - Latex Polymer - A latex polymer Aggregate treatment Material may be used to treat new crushed Aggregates instead of lime if Tensile Strength Ratio test results on the mixture with the latex polymer treatment at the JMF meet the minimum criteria in 00745.13(a).
(1) General:
a. Provide a system to automatically meter the latex emulsion at the proper rate and apply the emulsion uniformly to the Aggregate prior to the addition of the asphalt cement. Follow manufacturer's recommendations to set up, adjust, and calibrate the Equipment.
b. Demonstrate to the Engineer's satisfaction that the required application rate of latex solids is being met. If it is not, take corrective action. Document and notify the Engineer of the corrective action.
(2) Material - Use latex polymer emulsion concentrate meeting the following:
Minimum Maximum Test Method
| Solids Percent | 65.0 | – | ASTM D 1417 |
| pH | 9.0 | 11.0 | ASTM D 1417 |
| Brookfield Viscosity | 500 | 3000 | ASTM D 1417 |
| Spindle 3, 20 RPM, cPs |
Provide a quality compliance certificate for the polymer latex emulsion concentrate to the Engineer according to 00165.35.
(3) Application Rate - Apply the latex emulsion to achieve a minimum of 0.75 pounds of latex solids per Ton of new Aggregate (0.0375%) for dense graded mixtures and a minimum of 0.50 pounds of latex solids per Ton of Aggregate (0.025%) for open‑graded mixtures. Higher application rates may be required to meet minimum TSR limits. Determine application rate during mix design testing.
(4) Treatment During ACP Production:
a. Adjust Aggregate moisture content to meet the manufacturer's recommendation for emulsion application. Apply the latex emulsion at the minimum rate specified above or at a higher rate if TSR testing indicates a higher rate is required.
b. Apply the latex emulsion to the Aggregate just prior to entry into dryer drum. Mix Aggregate with the emulsion in a pugmill or in the dryer drum prior to application of asphalt cement. Heat Aggregates to at least 250 °F after treatment and prior to addition of asphalt cement.
Add the following subsection:
00745.11(e) Liquid Anti-Stripping Additive – An asphalt cement liquid anti-stripping additive (LASA) may be used instead of lime treatment of Aggregate.
(1) General – For LASA to be considered for use, meet the following criteria:
· Be designated as an asphalt anti-strip additive, with test results posted on the Warm Mix Asphalt Technologies category on the AASHTO Product Evaluation and Audit Solutions (APEAS) website.
· APEAS test results indicate an increase of 10 percent or greater in TSR (AASHTO T 283) performed on durable Aggregate, not limestone.
· Be approved for use by another State DOT as an anti-stripping additive.
If a product meets these criteria, it may be used in the JMF development according to the ODOT Contractor Mix Design Guidelines for Asphalt Concrete. The standard addition rate of LASA for the JMF is the rate used in the APEAS testing. If no rate is published, the minimum rate will be 0.5% of the virgin binder. If the APEAS published rates are 0.5% of total binder or higher, the minimum rate may be reduced to 0.5% of the virgin binder.
Approval of the JMF is also dependent on Hamburg wheel-track testing results conducted at the ODOT Central Materials Laboratory. When tested according to AASHTO T 324 for 20,000 passes at a test temperature of 50 °C the minimum requirements are:
| Rut depth (Level 4 wearing Course) | 5mm max. |
| Rut depth (All others) | 7mm max. |
| Stripping inflection point (All levels) | none |
(2) Addition to Asphalt Cement – Blend the LASA at the asphalt terminal prior to delivery to the mixing plant. Use LASA compatible with the asphalt cement. Comply with all asphalt cement requirements for the blended product. Do not change the LASA addition rate without prior approval from the Engineer.
(3) Field Testing During Production – At the Agency’s discretion, production mixture may be tested at the Central Materials Laboratory. Failure to meet the criteria listed above may require a change in addition rate, a change of approved LASA, or lime‑treatment of Aggregate to continue production.
00745.12(a) Mix Type - Replace this subsection, except for the subsection number and title, with the following: Use Level 3, ½” Lime Treated ACP Wearing Course.
00745.46(b) Depositing - Replace the paragraph that begins "Deposit ACP from..." with the following paragraph:
Deposit ACP from the hauling vehicles so segregation is prevented. Do not deliver the ACP directly into the paving machine for wearing Courses where the continuous length of the Panel is greater than 500 feet. Deliver the ACP to the paving machine by either a windrow pick-up machine or an end-dump transfer machine.
00745.46(c) Placing – Add the following project specific ACP placement table:
| Section |
| Grind Depth |
| ACP Depth |
| Width |
| MP 22.00 – 22.50 SB & NB lanes |
| 2.5” |
| 2.5” |
| 33’ |
| MP 22.50 – 23.20 SB & NB lanes |
| 2.5” |
| 2.5” |
| 45’ |
| MP 23.20 – 24.47 SB & NB lanes |
| 2.5” |
| 2.5” |
| 33’ |
| MP 24.47 – 25.50 SB & NB lanes |
| 3.0” |
| 3.0” |
| 33’ |
00745.47(a)(2) Wearing Course ‑ Replace this subsection, except for the subsection number and title, with the following:
Construct longitudinal joints six inches from permanent lane markings, or as shown or directed.
00745.48(c) Bridge Deck Overlays ‑ Replace the paragraph that begins "Saw cut the wearing Course of Pavement …" with the following paragraph:
Sawcut the wearing or base Course of Pavement directly over the joints in bridge decks, bridge end joints and end Panel end joints as soon as practical but within 48 hours of paving each stage of the wearing or base Course, unless otherwise directed. Saw the cut 3/8 inch wide, ± 1/8 inch, by 1/2 inch less than the thickness of the Panel of Pavement depth or 1 1/2 inches deep, whichever is less.
00745.49(b)(2)(b) Core Correlation of Nuclear Gauge Readings - Replace this subsection, except for the subsection number and title, with the following:
For each Lift on the Project that contains more than 2,500 Tons of ACP, correlate each nuclear gauge that will be used on that Lift. Perform core correlations and determine core correlation factors according to AASHTO T 355 and ODOT TM 327. Provide bulk specific gravity values to the Engineer within 24 hours of coring. If an Aggregate source or the asphalt cement source changes, new core correlations are required.
Apply correlation factors to all nuclear gauge readings for the Lift on which the core correlation was performed.
Both the Engineer and the Contractor may request additional core correlation of nuclear gauge readings. Core correlations requested by the Contractor or that are required due to a change in Aggregate or asphalt cement source will be at no additional cost to the Agency.
Add the following subsection:
00745.51 Opening Sections to Traffic - Schedule Work so that, during the same shift, the surfaces being paved are paved full width and length through the wearing Course before opening to traffic.
00745.70 Pavement Smoothness - Replace this subsection, except for the subsection number and title, with the following:
Construct the Pavement wearing surface of Traffic Lanes to a profile that does not deviate from longitudinal and transverse smoothness more than the specified limits of 00745.73.
Perform profiling and straightedge testing under the supervision of the Engineer with Equipment furnished and operated by the Contractor at no additional cost to the Agency, according to ODOT TM 772. Complete all required smoothness testing no later than 14 Calendar Days following final completion of all Traffic Lane paving on the Project, or by October 15 of each calendar year for multiple year projects, whichever is earlier. The Contractor accepts the risk that the smoothness may be affected by exposure to traffic between the date the Traffic Lanes are paved and the date the smoothness testing is completed. If the Contractor elects to perform smoothness measurements on a Day other than the Day the Pavement is placed, additional traffic control required for smoothness measurement, and not required for other Work, will be at no additional cost to the Agency.
Add the following subsection:
00745.72 Smoothness Testing Equipment - Furnish all Equipment and supplies for determining smoothness.
(a) Straightedge - Provide one 12 foot straightedge.
(b) Profiler - Provide a profiling device meeting the requirements of ODOT TM 772 and certified according to ODOT TM 769.
Provide competent and experienced operator(s) for the Equipment, certified with the profiler according to ODOT TM 769. The profiler operator shall meet with the Engineer at a mutually agreed upon time prior to beginning smoothness measurements to discuss all aspects of smoothness measurement on the Project.
Add the following subsection:
00745.73 Smoothness Testing and Surface Tolerances - Test according to the following:
(a) General - Test the Base Course with a 12 foot straightedge as directed. Test the wearing Course with the profiler meeting the requirements of 00745.72(b). Compute the IRI from the profile data according to the procedures described in ODOT TM 772. Price adjustment for smoothness will be made according to 00745.96.
Before performing any smoothness measurements on the Project, verify calibration of the profiler according to the manufacturer’s recommendations and ODOT TM 772.
(b) Surface Test:
(1) Transverse - Test the Base Course with the 12-foot straightedge perpendicular to the centerline, as directed. The Pavement surface shall not vary by more than 1/4 inch.
(2) Longitudinal - Test all Base or wearing Course sections of Pavement that are not required to be profiled according to 00745.73(c) with the 12-foot straightedge parallel to the centerline and lane dividers, as directed. The Pavement surface shall not vary by more than 1/4 inch.
(c) Wearing Course Surface Test:
(1) Transverse - Test with the 12-foot straightedge perpendicular to the centerline, as directed. The Pavement surface shall not vary by more than 1/4 inch.
(2) Longitudinal - Perform testing as follows:
a. Quality Control - Run the profiling device over each Traffic Lane for the full length of the Project.
In the presence of the Engineer and according to ODOT TM 772, obtain profiles on the Pavement surface in the right and left wheel path of the Traffic Lane along a line parallel to permanent longitudinal Pavement markings, at 3-foot and 9-foot offsets from the left edge of the Traffic Lane. Take the profile on transition areas of entrance and exit ramps, as close to the right and left wheel path of the through Traffic Lane as practical. Submit data files to the Engineer at the completion of each shift in which profiling has taken place. For the Pavement sections tested, provide the raw data files and provide electronic copies of the profile data in PPF and manufacturer proprietary formats, as required by the Engineer.
Analyze profiles according to 00745.73(d), and give the results to the Engineer no later than 24 hours following completion of required smoothness. The results shall consist of a table showing areas of Localized Roughness in each wheel path, and the left wheel path IRI, right wheel path IRI, and mean IRI (average of left and right wheel path IRI) at 0.10 mile intervals.
b. Quality Assurance - At the discretion of the Engineer, the Agency may perform Quality Assurance of Profiles on projects according to ODOT TM 772.
(3) Transverse Joints - Test with the 12-foot straightedge parallel to the centerline, as directed. The Pavement surface shall not vary by more than 1/4 inch.
(d) Determination of the International Roughness Index:
(1) General - Determine the IRI in 0.10 mile segments and partial segments of the wearing Course. Begin segments 50 feet into the Project and run consecutively in the direction of travel. A segment ends as a partial segment and a new segment begins when the segment sequence is interrupted by stage construction or by profiled areas excluded from the smoothness requirements. Minimize the number of partial segments.
The following areas of Pavement are excluded from IRI smoothness requirements and are not profiled:
· Profiles extending beyond the Project ends.
· Bridge decks, Bridge end panels, and Pavement within 50 feet of Bridge end panels.
· First and last 50 feet of the ACP paving limits of the Project.
· The 50 feet before and after No Work Areas within the Project limits.
· Ramps and auxiliary lanes that are less than 2500 feet in length.
· First 800 feet of entry ramps and the last 800 feet of exit ramps.
· The 25 feet before and after Utility appurtenances in the Traffic Lane.
· Continuous portions of Traffic Lanes with less than 0.05 mile between excluded areas.
· Portions of the Project with posted speed limits less than 45 mph.
Locate ACP IRI profiling excluded areas prior to smoothness measurement. Areas excluded from longitudinal profile measurement shall meet the straightedge requirements of 00745.73(b)(2).
(2) Method of Analysis - Determine the IRI for each wheel path and areas of Localized Roughness for each wheel path according to ODOT TM 772. Submit the results to the Engineer for review.
(e) Shoulders and Paved Medians - Test the Base and wearing Course with the 12‑foot straightedge parallel to and perpendicular to the centerline for Shoulders and paved Medians, as directed by the Engineer. The Pavement surface shall not vary by more than 1/4 inch.
00745.75 Correction of Pavement Roughness - Replace this subsection, except for the subsection number and title, with the following:
If testing described in 00745.73 shows that the Pavement does not conform to the prescribed limits, the following applies:
(a) General - The Contractor is responsible for locating areas that require corrective work.
(b) Base Course - If the requirements of 00745.73(b) are not met, correct according to one of the following and retest:
(1) Cold Plane Removal - Profile grind with Equipment meeting the requirements of 00620.20 to a maximum depth of 0.4 inch.
(2) Grinder - Profile grind with abrasive grinder(s), equipped with a cutting head comprised of multiple diamond blades to a maximum depth of 0.4 inch.
(c) Wearing Course - After locating each area of Localized Roughness and the 0.10 mile segments that have an average IRI value greater than 95.0 inches per mile, meet with the Engineer at a mutually agreed upon time and drive the Project together. During the drive-through, evaluate each area of Localized Roughness between 160.0 and 189.9 inches per mile and partial segments with an average IRI value greater than 95.0 inches per mile to determine if corrective Work is required. All 0.10 mile segments with an IRI value more than 95.0 inches per mile and all areas of Localized Roughness equal to or greater than 190.0 inches per mile require corrective action. Disagreements will be resolved by the Engineer.
Correct all areas of Localized Roughness, segments and partial segments identified for corrective work, and any transverse joint and excluded areas that exceed the requirements of 00745.73, by one of the methods listed below and to the specified limits:
(1) Remove and Replace - Remove and replace the wearing surface lift.
(2) Grind - Profile grind with abrasive grinder(s) equipped with a cutting head comprised of multiple diamond blades to a maximum depth of 0.3 inch and apply an emulsion fog seal according to Section 00705, or as directed. Half or full lane width corrective grinding is required for areas requiring correction in one or both wheel paths as shown by the Localized Roughness, respectively. Perform corrective grinding in such a manner that the shedding of water is not interrupted across the travel lanes due to the grinding.
Following corrective work, the Engineer will re-evaluate all corrected areas for acceptance. The Engineer may require retesting per ODOT TM 772 and 00745.73. Further corrective Work may be required. Perform all corrective Work and retesting, including traffic control, at no additional cost to the Agency.
(d) Time Limit - Complete correction of all surface roughness prior to application of permanent Pavement markings within 14 Calendar Days following notification, unless otherwise directed.
00745.80 Measurement - Add the following paragraph to the beginning of this subsection:
The quantities of ACP shown in the Contract Schedule of Items were computed on the basis of Aggregates having a specific gravity of 2.75.
Add the following paragraph to the end of this subsection:
The quantities of core correlation of nuclear gauge readings will be measured on the unit basis for each core correlation test that is completed and accepted according to ODOT TM 327. Core correlations that are requested by the Contractor or that are required due to a change in Aggregate or asphalt cement source will not be measured.
00745.90 Payment -
Add the following Pay Item to the Pay Item list:
(c) Core Correlation of Nuclear Gauge Readings……………..Each
Add the following paragraph after the paragraph that begins "In item (b)…":
Item (c) includes developing core correlation factors for all gauges to be correlated for the lift on which the core correlation was performed, according to the procedure in ODOT TM 327.
In the paragraph that begins "No separate or additional payment…", add the following bullet to the end of the bullet list:
· Aggregate treatment - latex polymer
In the paragraph that begins "No separate or additional payment…", add the following bullet to the end of the bullet list:
· liquid anti-stripping asphalt cement additives
Add the following subsection:
00745.96 Smoothness Price Adjustment - No separate or additional payment will be made for smoothness testing.
(a) General - A price adjustment based on the results of the IRI will be made for each 0.10 mile segment or partial segment of Traffic Lane ACP requiring IRI measurement according to 00745.73. The price adjustment will be based on the IRI values determined according to ODOT TM 772 for each 0.10 mile segment and partial segment. Partial segments less than 0.10 mile in length shall be evaluated with the IRI price adjustment value multiplied by the ratio of the partial segment length to 0.10 mile.
A smoothness price adjustment will be made for all segments, or partial segments based on the average IRI value and the following equations:
Schedule 1
Averaged IRI (inches/mile) Equation
| ≤ 35.00 |
| Y = $500.00 |
| 35.01 ‑ 60.00 |
| Y = ( $20.00 × X) + $1,200.00 |
| 60.01 ‑ 65.00 |
| Y = $0.00 |
| 65.01 ‑ 95.00 |
| Y = ( $20.00 × X) + $1,300.00 |
| > 95.00 |
| Corrective Action |
Y = The price adjustment for the segment or partial segment X = The averaged IRI value for the segment or partial segment
Any positive smoothness price adjustment due to the Contractor will be made on the next monthly progress estimate following the satisfactory completion of all corrective Work and the submission of all test data for all Traffic Lane paving on the Project.
00745.96(b) applies when corrective action is taken by the Contractor, or the Engineer elects to not correct identified Areas of Localized Roughness according to 00745.75(c).
(b) Adjustments for Sections Requiring Corrective Work or with Areas of Localized Roughness - Segments or partial segments in which corrective Work is performed according to 00745.75(c) are subject to the price adjustments described in 00745.96(a) except that no positive price adjustment (bonus) will be due to the Contractor If a segment or partial segment containing corrective Work is retested according to ODOT TM 772 and 00745.73, the retested average IRI value will be used for payment, except that no positive price adjustment will be made for a segment or partial segment containing corrective work.
No segment or partial segment containing an area of Localized Roughness with a value of 160.0 inches per mile or greater will be eligible for positive price adjustment, even if corrective action is not required by the Engineer.
Segments or partial segments containing corrective Work with an IRI value of more than 95.0 inches per mile are subject to additional corrective action and retesting according to 00745.75(c). The Engineer may waive corrective action in partial segments with the application of a smoothness price adjustment based on an IRI value of 95.0 inches per mile.
SECTION 00748 - ASPHALT CONCRETE PAVEMENT REPAIR
Comply with Section 00748 of the Standard Specifications modified as follows:
00748.00 Scope – Add the following project specific work location:
One Asphalt Concrete Pavement Repair section is required at the following location:
South Bound B-Lane ~ MP 23.13 – 23.15, with dimensions of approximately 130’ long by 12’ wide. (Painted on site)
· 6.0” Level 3, ½” Lime Treated ACP (two equal lifts)
· 6.0” Cold Plane Pavement Removal
Rev 1/4/2019