The file is a Preliminary Bid Results spreadsheet for the Oregon Department of Transportation (ODOT) OR 140: Culvert Repair Project, covering a 21.94-mile stretch of highway from milepost 73.09 to 95.031 in Lake County. The project solicits bids for comprehensive culvert rehabilitation work, including temporary water management facilities, CCTV culvert inspections, and cured-in-place pipe (CIPP) liner installations. Four contractors submitted bids: JR Carlon Corp, Whitaker Construction Company, LaDuke Construction LLC, and HP Civil Inc. The project requires substantial completion by September 26, 2026, with a final completion date of October 3, 2026, and bid submissions were due by May 14, 2025, through the OregonBuys eProcurement system.

The bid results show detailed pricing for 21 line items, with total bid prices ranging from $542,442.55 to $926,386.33 across the four bidders. The project involves culvert work with pipes ranging from 12" to 48" in diameter, including pipe installation, video inspection, drainage marker placement, and streambed enhancement. Contractors must be registered with the Oregon Construction Contractors Board, comply with prevailing wage rates, and adhere to Buy America provisions. The project requires performance and payment bonds each equal to 100% of the contract price, and contractors must have a qualifying drug testing program. Funding appears to be from state resources, with a focus on infrastructure maintenance and environmental considerations in BOLI Region 11.

View the file

Other files

File Type Posted
00013506 Att C Bid Pricing Form.xlsx XLSX spreadsheet
00013506 Att A Revised Plans.pdf PDF
00013506 Att C Revised Bid Pricing Form.xlsx XLSX spreadsheet
00013507 Prelim Bid Results.xlsx XLSX spreadsheet
00013506 Att B Special Provisions and Specifications.docx DOCX document
00013506 Att A Plans.pdf PDF
00013506 Invitation to Bid.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-73000-00013506
PRELIMINARY BID RESULTSJR Carlon CorpWhitaker Construction CompanyLaDuke Construction LLCHP Civil Inc.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

1Mobilization1LS$60,750.00$ 60,750.00$142,000.00$ 142,000.00$176,700.00$ 176,700.00$ 92,638.630$ 92,638.63
2Temporary Work Zone Traffic Control, Complete1LS$ 39,501.00$ 39,501.00$ 41,900.00$ 41,900.00$ 54,320.00$ 54,320.00$ 155,000.000$ 155,000.00
3Portable Changeable Message Signs2EACH$ 1,890.00$ 3,780.00$ 5,580.00$ 11,160.00$ 5,960.00$ 11,920.00$ 3,000.000$ 6,000.00
4Automated Flagger Assistance Device2EACH$ 2,025.00$ 4,050.00$ 3,070.00$ 6,140.00$ 5,600.00$ 11,200.00$ 1,250.000$ 2,500.00
5Pollution Control Plan1LS$ 450.00$ 450.00$ 2980.00$ 2,980.00$ 980.00$ 980.00$ 500.000$ 500.00
6Erosion Control1LS$ 450.00$ 450.00$ 7,910.00$ 7,910.00$ 4,600.00$ 4,600.00$ 4,000.000$ 4,000.00
7Temporary Water Management, MP 95.031LS$ 18,071.99$ 18,071.99$ 44,100.00$ 44,100.00$ 46,430.00$ 46,430.00$ 35,000.000$ 35,000.00
812 inch culvert Pipe, 5 ft depth10FOOT$ 126.04$ 1,260.40$ 245.00$ 2,450.00$ 298.00$ 2,980.00$ 500.000$ 5,000.00
918 inch culvert Pipe, 5 ft depth45FOOT$ 150.26$ 6,761.86$ 250.00$ 11,250.00$ 332.00$ 14,940.00$ 445.000$ 20,025.00
1018 inch culvert Pipe, 10 ft depth20FOOT$ 140.28$ 2,805.51$ 705.00$ 14,100.00$ 388.00$ 7,760.00$ 550.000$ 11,000.00
1124 inch culvert Pipe, 5 ft depth20FOOT$ 137.07$ 2,741.37$ 360.00$ 7,200.00$ 406.00$ 8,120.00$ 525.000$ 10,500.00
12connect to extg. Pipe6EACH$ 150.00$ 900.00$ 355.00$ 2,130.00$ 1,300.00$ 7,800.00$ 1,200.000$ 7,200.00
13Rehabilitate 18" culvert406FOOT$ 265.95$ 107,975.70$ 250.00$ 101,500.00$ 227.00$ 92,162.00$ 235.000$ 95,410.00
14Rehabilitate 24" culvert471FOOT$ 297.00$ 139,887.00$ 290.00$ 136,590.00$ 260.00$ 122,460.00$ 425.000$ 200,175.00
15Rehabilitate 48" culvert170FOOT$ 615.00$ 104,550.00$ 700.00$ 119,000.00$ 470.00$ 79,900.00$ 1,100.000$ 187,000.00
16Mainline Video Inspection1954FOOT$ 12.60$ 24,620.40$ 2.50$ 4,885.00$ 3.00$ 5,862.00$ 10.050$ 19,637.70
17Culvert Drainage Markers, Type 113EACH$ 250.00$ 3,250.00$ 230.00$ 2,990.00$ 228.00$ 2,964.00$ 200.000$ 2,600.00
18Culvert Drainage Markers, Type 212EACH$ 250.00$ 3,000.00$ 230.00$ 2,760.00$ 187.00$ 2,244.00$ 200.000$ 2,400.00
19Streambed Enhancment1LS$ 10,447.50$ 10,447.50$ 18,700.00$ 18,700.00$ 46,800.00$ 46,800.00$ 51,500.000$ 51,500.00
20Grade control structure1EACH$ 6,739.81$ 6,739.81$ 1,000.00$ 1,000.00$ 11,800.00$ 11,800.00$ 15,000.000$ 15,000.00
21Fish Rocks, Type 26EACH$ 75.00$ 450.00$ 545.00$ 3,270.00$ 1,240.00$ 7,440.00$ 550.000$ 3,300.00
TOTAL$ 542,442.55$ 684,015.00$ 719,382.00$ 926,386.33