00003126 preliminary BID_TAB.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- US30 MP 1. 97 Pavement Repair
- Solicitation number
- S-73000-00003126
- Issued by
- Multnomah County, Oregon
About this file
This document appears to be a bid tabulation for the US30 MP 1.97 Pavement Repair project, which is being put out to bid by the state of Oregon, with the jurisdictions of Multnomah County and the City of Portland. The project involves various pavement repair activities, including mobilization, temporary traffic control, pollution control, soil handling and disposal, subgrade stabilization, cold planing, and paving. The bid closing date was June 8, 2022, and the bid tabulation includes pricing information for two bidders, Kerr Contractors and Oregon Granite Construction Company.
The bid items include unit pricing for various quantities of work, with the total bid amounts for the two bidders being $418,790.00 and $444,444.00, respectively. The pricing includes costs for items such as contaminated soil disposal, aggregate base, and asphalt concrete paving. The project appears to be funded and administered by the state and local jurisdictions involved, though specific funding sources and requirements are not provided in the document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3127 preliminary BID_TAB.xlsx | XLSX spreadsheet | |
| 3126_Invitation to Bid~2.docx | DOCX document | |
| Attachment A - Special Provisions~10.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Date Issued: | 6/8/22 | |||
| ITB No. | S-73000-00003126 | BIDDER | ||
| NAME: | Kerr Contrators Oregon | Granite Construction Company | ||
| Bid Closing: | June 8, 2022 | CITY/STATE: | ||
| Description: | US30 MP 1.97 Pavement Repair | CCB#: | ||
| This bid tabulation is not an indicator of award. It is only a tabulation of the bids submitted for consideration. |
| Bid Item # | Description | Est | |
| QTY | UNIT | UNIT | |
| PRICE | TOTAL | ||
| PRICE | UNIT | ||
| PRICE | TOTAL |
PRICE
| 1 | MOBILIZATION | 1 | LS | $ 35,000.00 | $ 35,000.00 | $ 43,794.00 | $ 43,794.00 |
| 2 | TEMPORARY PROTECTION AND DIRECTION OF TRAFFIC | 1 | LS | $ 100,000.00 | $ 100,000.00 | $ 75,000.00 | $ 75,000.00 |
| 3 | POLLUTION CONTROL PLAN | 1 | LS | $ 1,500.00 | $ 1,500.00 | $ 3,500.00 | $ 3,500.00 |
| 4 | SEGREGATE AND STOCKPILE CONTAMINATED SOIL | 1 | LS | $ 35,000.00 | $ 35,000.00 | $ 3,500.00 | $ 3,500.00 |
| 5 | SOIL SAMPLE COLLECTION AND ANALYTICAL TESTING | 1 | EACH | $ 1,500.00 | $ 1,500.00 | $ 6,000.00 | $ 6,000.00 |
| 6 | HEALTH AND SAFETY PLAN | 1 | LS | $ 1,500.00 | $ 1,500.00 | $ 2,000.00 | $ 2,000.00 |
| 7 | CONTAMINATED SOIL DISPOSAL | 204 | TON | $ 150.00 | $ 30,600.00 | $ 250.00 | $ 51,000.00 |
| 8 | 24 INCH SUBGRADE STABILIZATION | 117 | SQYD | $ 220.00 | $ 25,740.00 | $ 400.00 | $ 46,800.00 |
| 9 | COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEP | 590 | SQYD | $ 22.00 | $ 12,980.00 | $ 40.00 | $ 23,600.00 |
| 10 | COLD PLANE PAVEMENT REMOVAL, 5 INCHES DEEP | 530 | SQYD | $ 50.00 | $ 26,500.00 | $ 40.00 | $ 21,200.00 |
| 11 | AGGREGATE BASE | 120 | TON | $ 161.00 | $ 19,320.00 | $ 85.00 | $ 10,200.00 |
| 12 | LEVEL 4, 1/2 INCH DENSE ACP | 287 | TON | $ 450.00 | $ 129,150.00 | $ 550.00 | $ 157,850.00 |
| TOTAL | $ 418,790.00 | $ 444,444.00 |