00_Stairs_and_Rails_SOW.pdf

PDF 57 KB Posted

Attached to
Fort Fremont Stairs and Rails Design/Build
Solicitation number
070226
Issued by
Barnwell County, South Carolina

About this file

This Scope of Work document outlines the design-build requirements for Beaufort County, South Carolina's Fort Fremont Stairs and Rails project located on St. Helena Island. The project encompasses the design, engineering, fabrication, and installation of stairs, railings, security doors, and security window systems at Fort Fremont Preserve. The selected Design-Build contractor must provide comprehensive services including all labor, supervision, materials, equipment, transportation, engineering, fabrication, permitting assistance, site protection, demolition, and incidental work necessary for project completion. The improvements aim to enhance public safety and pedestrian circulation, improve accessibility and visitor flow along the fort battery, protect historic structures from damage, provide secure enclosures for designated exhibit rooms, and maintain the historic and visual character of the preserve in compliance with all applicable codes and standards.

The County will select the proposal offering the best overall value based on qualifications, technical approach, experience, schedule, price, and understanding of project requirements. The document establishes specific performance standards and requirements that the Design-Build contractor must meet, though detailed response deadlines, site visit schedules, and award dates are not included in this Scope of Work document itself. The project requires strict adherence to historic preservation standards and accessibility requirements, indicating the sensitive nature of work at this preserved military installation.

View the file

Other files

File Type Posted
Fort_Fremont_Stairs_and_Rails_Design_Build_(Addendum_#2_Revision).pdf PDF
Stairs_and_Rails_Map.pdf PDF
ZIP_-_Fort_Freemont_SOW_and_Images.zip ZIP file
18_door_sketch.png PNG image
17_door_sketch.png PNG image
05_stairs2_crossing.jpeg JPEG file
16_windows.jpeg JPEG file
15_door_and_window.jpeg JPEG file
19_Door_Design_Example.pdf PDF
01_stairs1.jpeg JPEG file
11_railings.jpeg JPEG file
02_stairs2.jpeg JPEG file
09_stairs4.jpeg JPEG file
03_stairs2.jpeg JPEG file
10_stairs4.jpeg JPEG file
07_stairs3.jpeg JPEG file
06_stairs3_crossing.jpeg JPEG file
12_railings.jpeg JPEG file
14_door.jpeg JPEG file
13_railings.jpeg JPEG file
04_stairs2.jpeg JPEG file
08_stairs4_crossing.jpeg JPEG file
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Fremont Stairs and Rails Scope of Work

1. Stairs #1 (see picture #1)

a. Location from ground to Gun Pit 1 landing

b. Metal steps with railings over existing concrete wedge

c. 15.5 feet long by 4 feet wide

d. Paint black

2. Stairs #2 (see pictures #2-5)

a. Location from Gun Pit 1 landing to top of fort on north end

b. Wood, metal or mixed materials steps with railings over existing earthen path

c. 50 feet long by 4 feet wide

d. Including a 4x4 foot crossing over the concrete drainage ditch

e. Paint black or treat for weather dependent upon material type

3. Stairs #3 (see pictures #6-7)

a. Location on top of fort down river side of berm at beach access gate

b. Wood, metal or mixed materials steps with railings over existing earthen path

c. 65 feet long by 4 feet wide

d. Including a 4x4 foot crossing over the concrete drainage ditch

e. Paint black or treat for weather dependent upon material type

4. Stairs #4 (see pictures #8-10)

a. Location from top of fort to ground and sidewalk on south end

b. Demo existing steps

c. Wood, metal or mixed materials steps with railings over existing earthen path

d. 104 feet long by 6 feet wide

e. Including a 4x6 foot crossing over the concrete drainage ditch

f. Including a 26 foot long by 6 foot wide concrete sidewalk connection from bottom of steps to existing sidewalk

g. Paint black or treat for weather dependent upon material type

5. Gun Pit 1 Railings (see pictures #11-13)

a. Location on Gun Pit 1 landing

b. 98 feet of railings in the same style and design as the existing railings

c. Including opening for and connection to Stairs #1

d. Paint black

6. Exhibit Room Doors and Windows (see pictures #14-18)

a. Location on Battery Fornance and Battery Jesup ground level rooms

b. The two (2) doors are approximately 48 inches wide by 84 inches tall

c. The three (3) windows are approximately 42 inches wide by 42 inches tall

d. Doors should be metal angle-iron with hinges and gate locking hardware that will accommodate a pad-lock

e. Windows should be metal angle-iron bolted directly into the fort structure

f. Gaps between the bars should be 5 ¾ inches wide to accommodate bat use

g. See Door Design Example pdf for bat friendly sample design

h. Paint all doors and windows black