00 0011 Agreement.pdf
PDF 137 KB Posted
- Solicitation number
- PE-72600-NONST-2026-000000029
- Issued by
- Spalding County, Georgia
About this file
This document is an Agreement between the Spalding County Board of Commissioners (Owner) and an unspecified Contractor for the demolition and reconstruction of the Heritage Park Gymnasium in Griffin, Spalding County, Georgia. The project involves creating a 9,805 sq.ft. facility with comprehensive site work and improvements, including building and site demolition, new utilities, grading, drainage, storm sewer systems, sidewalks, foundations, structural steel framing, masonry veneers, exterior windows/doors, roofing systems, building insulation, interior walls and finishes, millwork, plumbing, HVAC, electrical distribution, lighting, and fire protection systems. The contract stipulates a project completion timeline of 360 days for substantial completion and 420 days for final completion, with the work to be designed by Warren Epstein & Associates, Architects and Croy Engineering.
The contract includes liquidated damages of $1,000 per day for delays beyond the specified completion dates. Payment will be made based on the Contractor's bid, with progress payments processed monthly, typically covering 90% of completed work and materials, with retainage held until substantial completion. The Owner will make final payment upon complete and satisfactory project completion. The Contract Documents comprise multiple components, including the Agreement, Contractor's Bid, performance and payment bonds, General and Supplementary Conditions, Specifications, 32 drawing sheets titled "RENOVATIONS TO THE HERITAGE PARK GYMNASIUM", and potential addenda and exhibits. The contract emphasizes the Contractor's representations of thorough document review, site familiarity, and compliance with all relevant laws and regulations.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-1
Project No. 17100.00
AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is by and between SPALDING COUNTY BOARD OF COMMISSIONERS
(“Owner”) and (“Contractor”).
Owner and Contractor hereby agree as follows:
ARTICLE 1 – WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows:
The project consists of but is not limited to the demolition and reconstruction of the Heritage Park Gymnasium Building creating a 9,805 sq.ft. facility, along with related site work and improvements, in a site located in Heritage Park, in Griffin, Spalding County, Georgia and includes building/site demolition, new utilities with connections to municipal services, new grading/drainage, new storm sewer systems, new concrete sidewalks, selective demolition of limited building components, new foundations, new slab on grade, new load bearing foundations/Structural Steel/Cold Formed Steel Roof Framing, new metal framed stairs, new masonry veneers, new exterior window/door systems, new roof/fascia/eave systems, new building insulation, new interior metal stud framed walls, new interior floor/base/wall/ceiling finishes, new interior architectural millwork, new interior doors, new interior accessories/equipment, new plumbing fixture/piping systems, new HVAC/ductwork systems, , new fire protection, new primary/secondary/general electrical distribution systems, new lighting systems and fire alarm devices/systems.
ARTICLE 2 – THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
DEMOLITION AND RECONSTRUCTION OF THE HERITAGE PARK GYMNASIUM
FOR THE
SPALDING COUNTY BOARD OF COMMISSIONERS
GRIFFIN, SPALDING COUNTY, GEORGIA
2.02 The Project has been designed by Warren Epstein & Associates, Architects (Architect) and Croy
Engineering. (Engineer), which are to act as Owner’s representative, assume all duties and
AG-2
responsibilities, and have the rights and authority assigned to Engineer in the Contract Documents in connection with the completion of the Work in accordance with the Contract Documents.
ARTICLE 3 – CONTRACT TIMES
3.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Days to Achieve Substantial Completion and Final Payment
A. The Work will be substantially completed within 360 days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions within 420 days after the date when the Contract Times commence to run.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner and Contractor agree that as liquidated damages for delay (but not as a penalty), Contractor shall pay Owner $1,000.00 for each day that expires after the time specified in Paragraph 4.02 above for Substantial Completion until the Work is substantially complete. After Substantial Completion, if Contractor shall neglect, refuse, or fail to complete the remaining Work within the Contract Time or any proper extension thereof granted by Owner, Contractor shall pay Owner $1,000.00 for each day that expires after the time specified in Paragraph 4.02 above for completion and readiness for final payment until the Work is completed and ready for final payment.
ARTICLE 5 – CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to Paragraphs 5.01.A below:
A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit.
SUM OF ALL PRICES AS STATED IN CONTRACTOR’S BID:
(words & figures)
AG-3
As provided in paragraph 11.03 of the General Conditions estimated quantities are not guaranteed, and determinations of actual quantities and classification are to be made by Engineer as provided in paragraph 9.08 of the General Conditions. Unit prices have been computed as provided in paragraph 11.03B of the General Conditions.
ARTICLE 6 – PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the 10th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below. All such payments will be measured by the schedule of values established as provided in Paragraph 2.07.A of the General Conditions (and in the case of Unit Price Work based on the number of units completed) or, in the event there is no schedule of values, as provided in the General Requirements.
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Engineer may determine or Owner may withhold, including but not limited to liquidated damages, in accordance with Paragraph 14.02 of the General Conditions.
a. Ninety percent (90%) of Work completed (with the balance being retainage). If the Work has been fifty percent (50%) completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, then as long as the character and progress of the Work remain satisfactory to Owner and Engineer, there will be no additional retainage; and
b. Ninety percent (90%) of cost of materials and equipment not incorporated in the Work (with the balance being retainage).
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts as Engineer shall determine in accordance with Paragraph 14.02.B.5 of the General Conditions and less 200 percent of Engineer’s estimate of the value of Work to be completed or corrected as shown on the tentative list of items to be completed or corrected attached to the certificate of Substantial Completion.
AG-4
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with Paragraph 14.07 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 14.07.
ARTICLE 7 – INTEREST
7.01 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear interest equal to the Current Market Rate for ninety (90) day certificates of deposit at Wells Fargo Bank of Griffin, Georgia as of the effective date of this Agreement.
ARTICLE 8 – CONTRACTOR’S REPRESENTATIONS
8.01 In order to induce Owner to enter into this Agreement, Contractor makes the following representations:
A. Contractor has examined and carefully studied the Contract Documents and the other related data identified in the Bidding Documents.
B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work.
D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities), if any, that have been identified in Paragraph SC-4.02 of the Supplementary Conditions as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in Paragraph SC-4.06 of the Supplementary Conditions as containing reliable "technical data."
E. Contractor has considered the information known to Contractor; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site-related reports and drawings identified in the Contract Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, including any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Contract Documents; and (3) Contractor’s safety precautions and programs.
F. Based on the information and observations referred to in Paragraph 8.01.E above, Contractor does not consider that further examinations, investigations, explorations, tests, studies, or data
AG-5
are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents.
G. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents.
H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
I. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
ARTICLE 9 – CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages AG-1 to AG-8, inclusive).
2. Contractor’s Bid (pages A-1 to A-2, inclusive and Exhibit A).
3. Performance bond (pages Exhibit C-1 to Exhibit C-3, inclusive).
4. Payment bond (pages Exhibit B-1 to Exhibit B-3, inclusive).
5. General Conditions (pages 1 to 67, inclusive).
6. Supplementary Conditions (pages 1 to 5, inclusive).
7. Specifications as listed in the table of contents of the Project Manual.
8. Drawings consisting of 32 SHEETS with each sheet bearing the following general title:
RENOVATIONS TO THE HERITAGE PARK GYMNASIUM
9. Addenda (numbers to , inclusive).
10. Exhibits to this Agreement (enumerated as follows):
a. Other exhibits to this Agreement marked EXHIBIT D, EXHIBIT E and EXHIBIT F.
11. The following which may be delivered or issued on or after the Effective Date of the Agreement and are not attached hereto:
a. Work Change Directives.
AG-6
b. Change Orders.
B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents may only be amended, modified, or supplemented as provided in Paragraph 3.04 of the General Conditions.
ARTICLE 10 – MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions.
10.02 Assignment of Contract
A. No assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment, no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.
10.03 Successors and Assigns
A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.
10.05 Contractor’s Certifications
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05:
AG-7
1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the Contract execution;
2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;
3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and
4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.
AG-8
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement. Counterparts have been delivered to Owner and Contractor. All portions of the Contract Documents have been signed or have been identified by Owner and Contractor or on their behalf.
This Agreement will be effective on (which is the Effective Date of the Agreement).
OWNER: CONTRACTOR:
Spalding County Board of Commissioners
By: By:
Title: Title:
(If Contractor is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)
Attest: Attest:
Title: Title:
Address for giving notices: Address for giving notices:
119 E. Solomon Street
Griffin, GA 30223
License No.:
(If Owner is a corporation, attach evidence of authority to sign. If Owner is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)
Agent for service of process:
| Article 1 – Work |
| 1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: |
| The project consists of but is not limited to the demolition and reconstruction of the Heritage Park Gymnasium Building creating a 9,805 sq.ft. facility, along with related site work and improvements, in a site located in Heritage Park, in Griffin, Sp... |
| Article 2 – The Project |
| 2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows: |
| 2.02 The Project has been designed by Warren Epstein & Associates, Architects (Architect) and Croy Engineering. (Engineer), which are to act as Owner’s representative, assume all duties and responsibilities, and have the rights and authority assigned ... |
| Article 3 – Contract Times |
| 3.01 Time of the Essence |
| A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract. |
| 4.02 Days to Achieve Substantial Completion and Final Payment |
| A. The Work will be substantially completed within 360 days after the date when the Contract Times commence to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with Paragraph 14.07 of... |
| 4.03 Liquidated Damages |
| A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above and that Owner will suffer financial loss if the Work is not completed within the times specified in Paragraph 4.02 above, plus any extensions thereof allo... |
| Article 5 – Contract Price |
| 5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to Paragraphs 5.01.A below: |
| A. For all Work, at the prices stated in Contractor’s Bid, attached hereto as an exhibit. |
| SUM OF ALL PRICES AS STATED IN CONTRACTOR’S BID: |
| (words & figures) |
| As provided in paragraph 11.03 of the General Conditions estimated quantities are not guaranteed, and determinations of actual quantities and classification are to be made by Engineer as provided in paragraph 9.08 of the Gen... |
| Article 6 – Payment Procedures |
| 6.01 Submittal and Processing of Payments |
| A. Contractor shall submit Applications for Payment in accordance with Article 14 of the General Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions. |
| 6.02 Progress Payments; Retainage |
| A. Owner shall make progress payments on account of the Contract Price on the basis of Contractor’s Applications for Payment on or about the 10th day of each month during performance of the Work as provided in Paragraph 6.02.A.1 below. All such paymen... |
| 1. Prior to Substantial Completion, progress payments will be made in an amount equal to the percentage indicated below but, in each case, less the aggregate of payments previously made and less such amounts as Engineer may determine or Owner may with... |
| a. Ninety percent (90%) of Work completed (with the balance being retainage). If the Work has been fifty percent (50%) completed as determined by Engineer, and if the character and progress of the Work have been satisfactory to Owner and Engineer, the... |
| b. Ninety percent (90%) of cost of materials and equipment not incorporated in the Work (with the balance being retainage). |
B. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments to Contractor to 100 percent of the Work completed, less such amounts as Engineer shall determine in accordance with Paragraph 14.02.B.5 of the General Con...
| 6.03 Final Payment |
| A. Upon final completion and acceptance of the Work in accordance with Paragraph 14.07 of the General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as provided in said Paragraph 14.07. |
| Article 7 – Interest |
| 7.01 All moneys not paid when due as provided in Article 14 of the General Conditions shall bear interest equal to the Current Market Rate for ninety (90) day certificates of deposit at Wells Fargo Bank of Griffin, Georgia as of the effective date of ... |
| Article 8 – Contractor’s Representations |
| 8.01 In order to induce Owner to enter into this Agreement, Contractor makes the following representations: |
| A. Contractor has examined and carefully studied the Contract Documents and the other related data identified in the Bidding Documents. |
| B. Contractor has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work. |
| C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect cost, progress, and performance of the Work. |
| D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Unde... |
| E. Contractor has considered the information known to Contractor; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Contract Documents; and the Site... |
| F. Based on the information and observations referred to in Paragraph 8.01.E above, Contractor does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Cont... |
| G. Contractor is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Contract Documents. |
| H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor. |
| I. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. |
| Article 9 – Contract Documents |
| 9.01 Contents |
| A. The Contract Documents consist of the following: |
| 1. This Agreement (pages AG-1 to AG-8, inclusive). |
| 2. Contractor’s Bid (pages A-1 to A-2, inclusive and Exhibit A). |
| 3. Performance bond (pages Exhibit C-1 to Exhibit C-3, inclusive). |
| 4. Payment bond (pages Exhibit B-1 to Exhibit B-3, inclusive). |
| 5. General Conditions (pages 1 to 67, inclusive). |
| 6. Supplementary Conditions (pages 1 to 5, inclusive). |
| 7. Specifications as listed in the table of contents of the Project Manual. |
| 8. Drawings consisting of 32 SHEETS with each sheet bearing the following general title: |
| RENOVATIONS TO THE HERITAGE PARK GYMNASIUM |
| 9. Addenda (numbers to , inclusive). |
| 10. Exhibits to this Agreement (enumerated as follows): |
| a. Other exhibits to this Agreement marked EXHIBIT D, EXHIBIT E and EXHIBIT F. |
| 11. The following which may be delivered or issued on or after the Effective Date of the Agreement and are not attached hereto: |
| a. Work Change Directives. |
| b. Change Orders. |
| B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly noted otherwise above). |
| C. There are no Contract Documents other than those listed above in this Article 9. |
| D. The Contract Documents may only be amended, modified, or supplemented as provided in Paragraph 3.04 of the General Conditions. |
| Article 10 – Miscellaneous |
| 10.01 Terms |
| A. Terms used in this Agreement will have the meanings stated in the General Conditions and the Supplementary Conditions. |
| 10.02 Assignment of Contract |
| A. No assignment by a party hereto of any rights under or interests in the Contract will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become d... |
| 10.03 Successors and Assigns |
| A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to all covenants, agreements, and obligations co... |
| 10.04 Severability |
| A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon Owner and Contractor, who agree that the... |
| 10.05 Contractor’s Certifications |
| A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05: |
| 1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process or in the Contract execution; |
| 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels... |
| 3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish Bid prices at artificial, non-competitive levels; and |
| 4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. |