BIA Design Build Construction Projects for the Navajo Region
Ended Master IDIQ Awarded
- Federal agency
-
Navajo Region
- Awardees
- 11
- Task orders
- 50
- Obligated
- $51,599,410
Vehicle facts
- Agency
-
- Navajo Region Bureau of Indian Affairs and Indian Education, Department of the Interior
- Combined task order value
-
- $51,599,410 Current, with exercised options
- $51,634,610 Potential, with all options
- Last date to order 100% complete
- Shared ceiling 21% used
- $250,000,000.00
IDV award and task order details come from SAM.gov/FPDS.
About this vehicle
The Department of the Interior Bureau of Indian Affairs Navajo Region established a Master IDIQ for design-build construction projects in the Navajo Region on December 17, 2014, with a shared ceiling of $250 million. Ordering closed on December 17, 2018, and the vehicle is no longer accepting new task orders.
All 50 task orders awarded under this vehicle funded BIA Navajo Region programs exclusively, with combined potential value of $51.6 million fully obligated as of the most recent award in September 2019. The vehicle saw steady ordering activity through 2017, with 12 to 13 orders per year, then declined to 5 orders in 2018 before a final 8 orders in 2019. The most recent delivery order (Nazlini Staff Quarter Renovation) was issued September 20, 2019, with an obligation of $4.85 million and ultimate completion in July 2023.
Awarded scope centers on infrastructure repair, renovation, and demolition at Bureau of Indian Education schools and Bureau of Indian Affairs facilities across the Navajo Nation. Recent orders include structural upgrades (Many Farms High School, $12.3 million), building demolition (Kayenta School, $4.86 million; Tohatchi School, $2.17 million), HVAC and mechanical systems (Aneth School, $1.89 million; fan coil replacements), roofing and quarters renovation, environmental remediation, sewer and water line upgrades, and fire safety systems. Work is performed across multiple Navajo Nation communities including Chinle, Kayenta, Tuba City, Greasewood Springs, and Shiprock.
Cherokee CRC LLC dominates the award portfolio with 19 orders valued at $21.8 million, followed by Barnhart-Taylor, Inc. with 10 orders at $17.8 million. These two firms capture 76% of combined potential value. Rock Gap Engineering LLC, Cherokee General Corp, and a small tail of additional contractors complete the awardee base of nine primes. Ninety-eight percent of orders carried no set-aside designation; one order was awarded to a total small business contractor. All delivery orders used firm fixed-price contracts.
IDV awards
Show all 11
Latest task orders
Show 15 more
Latest 25 of 50 listed here. See the rest on GovTribe.
Top awardees by obligations
| Rank | Awardee | Obligated | Share |
|---|---|---|---|
| 1 | Cherokee CRC LLC | $21,768,771 | 42% |
| 2 | Barnhart-Taylor, Inc. | $17,834,796 | 35% |
| 3 | Cherokee General Corp | $4,085,625 | 8% |
| 4 | Rock Gap Engineering LLC | $3,790,039 | 7% |
| 5 | Fortis Networks, Inc. | $1,606,778 | 3% |
| 6 | Lam / Rockford Construction, LLC | $1,297,346 | 3% |
| 7 | Weil Construction Inc. | $734,014 | 1% |
| 8 | Whiteriver Construction, Inc. | $259,384 | 1% |
| 9 | Mirador-Nasco JV | $222,655 | <1% |
Top funding agencies by obligations
| Rank | Funding agency | Obligated | Share |
|---|---|---|---|
| 1 | Department of the Interior | $51,599,410 | 100% |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2023 | $300,899 |
| FY2022 | $160,196 |
| FY2021 | $638,588 |
| FY2020 | $1,596,975 |
| FY2019 | $9,029,363 |
| FY2018 | $5,603,901 |
| FY2017 | $22,537,998 |
| FY2016 | $4,278,961 |
| FY2015 | $7,452,528 |
Quick answers
What is the BIA Design Build Construction Projects for the Navajo Region contract vehicle?
BIA Design Build Construction Projects for the Navajo Region is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by Navajo Region (Bureau of Indian Affairs and Indian Education), awarded on December 17, 2014.
Which companies hold BIA Design Build Construction Projects for the Navajo Region?
11 companies hold BIA Design Build Construction Projects for the Navajo Region's IDV awards, one each. The latest went to Cherokee General Corp on December 18, 2014. The awardees whose task orders obligated the most are Cherokee CRC LLC, Barnhart-Taylor, Inc. and Cherokee General Corp.
How much has been spent through BIA Design Build Construction Projects for the Navajo Region?
50 task orders have been placed under BIA Design Build Construction Projects for the Navajo Region, obligating $51,599,410.
What is the shared ceiling of BIA Design Build Construction Projects for the Navajo Region?
BIA Design Build Construction Projects for the Navajo Region's shared ceiling is $250,000,000; its task orders have used 21% of it.
Which agencies use BIA Design Build Construction Projects for the Navajo Region the most?
The departments whose task orders under BIA Design Build Construction Projects for the Navajo Region obligated the most are Department of the Interior ($51,599,410).
On GovTribe
See this vehicle's full record
- Every IDV award and task order
- Funding by agency, awardee, NAICS and set-aside
- Teaming partners on this vehicle
- Ask GovTribe AI about this vehicle