ID/IQ contract for architect-engineering services for pacific northwest region, U.S. Bureau of reclamation. Base year with four 1-year options.

Ended Indefinite Delivery Contract Awarded Last action

Contract number
INR13PC10008
Awardee
Awarding agency
Task orders
20 $9,518,179 obligated

Award facts

Combined order value
  • $9,518,178 Current, with exercised options
  • $9,748,953 Potential, with all options
Last date to order 100% complete
IDV ceiling 38% used
$25,000,000.00
Maximum order
$5,000,000.00
Award type
Multiple award
Who can order
Only the awarding agency
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 18 offers Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price

Award details come from SAM.gov/FPDS.

Task orders

Task order Ordering agency Obligated Awarded
Block 31 elevator construction oversight 140R1019F0001 Bureau of Reclamation $4,242
AP# 3918 - GC radio modernization 140R1018F0063 Bureau of Reclamation $1,141,116
KRD upper yakima storage system study, yakima river basin integrated water resource management plan, yakima, washington 140R1018F0064 Bureau of Reclamation $170,524
Grand coulee third powerplant crane controls part II inspection, evaluation, and design modifications, grand coulee… 140R1018F0049 Bureau of Reclamation $1,463,150
Boise river storage feasibility study -- land, structure, infrastructure, and real estate survey/analysis 140R1018F0045 Bureau of Reclamation $318,500
Fire station construction support INR17PD00080 Bureau of Reclamation $2,479,934
Potholes supplemental feed route hydraulic analysis follow up INR16PD00865 Bureau of Reclamation $51,824
Task order for phase II of block 31 elevator modernization, grand coulee DAM, WA. INR16PD01021 Bureau of Reclamation $434,227
Task order for grand coulee feeders replacement study, grand coulee DAM, WA. INR16PD00985 Bureau of Reclamation $185,765
Replaces task order R12PD10185 for administrative convenience pursuant to far 4.1601(C)for implementation of a new… INR16PD00305 Bureau of Reclamation $83,272
This task order is to provide an equitable adjustment. INR16PD00194 Bureau of Reclamation $129,061
Task order for nepa & nhpa assistance for units G1-18 modernization, grand coulee power office, WA INR16PD00134 Bureau of Reclamation $303,706
Task order for phase I of grand coulee power office space utilization study, grand coulee WA. INR15PD00913 Bureau of Reclamation $108,288
Task order for asssitance with nepa process for lewiston orchards water exchange & title transfer, idaho. INR15PD00649 Bureau of Reclamation $192,252
Task order for design of a fire station, grand coulee power office, WA. INR15PD00549 Bureau of Reclamation $1,246,037
Block 31 elevator modernization project, grand coulee DAM, WA INR14PD00853 Bureau of Reclamation $120,521
Task order for engineering assessment of 5 cranes at hungry horse DAM, MT. INR14PD00802 Bureau of Reclamation $399,039
Task order for preparation of a cost estimate for adding a 3RD hydropower generating unit to black canyon DAM, emmett… INR14PD00546 Bureau of Reclamation $359,873
Task order for programmatic ENV. Assessment for hydrocarbon exploration, choke canyon reservoir, texas. INR13PD10077 Bureau of Reclamation $265,132
Task order for assistance with phase II of henrys fork basin study, idaho. INR13PD10045 Bureau of Reclamation $61,717
Show all 20

Transactions

Action Obligated Date
Exercise an Option P00006 · MOD 6 to exercise the far 52.217-8 option to extend services clause for the period of 6 months. $0
Other Administrative Action 5 · MOD 5 to correct the system generated performance period date of modification 0004 to reflect the intended period performance end date of 05/30/2018. $0
Supplemental Agreement for work within scope 4 · MOD 4 is a bilateral MOD to exercise the 4TH (final) option year period. $0
Exercise an Option 3 · Modification 003 is a bilateral MOD to exercise the 3RD option year period. $0
Exercise an Option 2 · Modification 002 exercises the second option year period. $0
Exercise an Option 1 · Modification 001 exercises the first option year period. $0
Original award $0

Subawards

Subcontractor Amount Awarded
TCA Architecture Planning Inc. IGF::OT::IGF FIRE STATION CONSTRUCTION SUPPORT Drafting Services $0
TCA Architecture Planning Inc. FIRE STATION CONSTRUCTION SUPPORT - MODIFICATION P00028- PERIOD OF PERFORMANCE EXTENSION. Drafting Services $4,000
TCA Architecture Planning Inc. FIRE STATION CONSTRUCTION SUPPORT - MODIFICATION P00024- PERIOD OF PERFORMANCE EXTENSION. Drafting Services $0

Quick answers

Who was awarded contract INR13PC10008?

INR13PC10008 was awarded to Ch2M Hill, Inc. by Bureau of Reclamation (Department of the Interior) on May 31, 2013.

How much is contract INR13PC10008 worth?

Orders under INR13PC10008 have obligated $9,518,179. Their combined current value, with exercised options, is $9,518,178. Their combined potential value, with all options, is $9,748,953. INR13PC10008's own ceiling is $25,000,000. A single order can be worth up to $5,000,000.

How many orders have been placed under contract INR13PC10008?

20 orders have been placed under INR13PC10008, the latest on November 30, 2018.

Who can order from contract INR13PC10008?

INR13PC10008 is a multiple award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract INR13PC10008 competed?

The extent of competition for INR13PC10008 was full and open competition. The government received 18 offers.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV