Grand coulee third powerplant crane controls part II inspection, evaluation, and design modifications, grand coulee power office (gcpo), grand coulee, WA

Ended Awarded Last action

Contract number
140R1018F0049
Awardee
Awarding agency
Obligated
$1,463,150

Award facts

Contract value 100% obligated
$1,463,149.77 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Grand Coulee, WA 99133, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00021 · Grand coulee third power plant crane controls a/e to - P00020 closeout $0
Other Administrative Action P00019 · The purpose of this modification is to correct all clins to the existing period of performance. $0
Supplemental Agreement for work within scope P00018 · The purpose of this modification is to change the period of performance and authorize additional construction support through the completion of construction. $35,360
Other Administrative Action P00017 · The purpose of this modification is to change the contracting officer from scott cooper to colby clifford. $0
Definitize Change Order P00016 · The purpose of this modification is definitize unilateral modifications P00013 and P00015. -$1,699
Change Order P00015 · The purpose of this change order is to extend the period of performance for construction support services to coincide with the projected construction completion… $0
Supplemental Agreement for work within scope P00014 · The purpose of this modification is to exercise optional task 6 for 30 additional RFI reviews. $62,124
Change Order P00013 $49,793
Supplemental Agreement for work within scope P00012 · The purpose of this modification is to extend the period of performance for construction support services to coincide with the construction completion date. $37,925
Other Administrative Action P00011 · The purpose of this modification is to correct all clins to the existing period of performance. $0
Supplemental Agreement for work within scope P00010 · The statement of work adds reviews of submittals, rfis, proposals and a site visit. An optional task has been included to review additional rfis if required.… $346,669
Supplemental Agreement for work within scope P00009 · The purpose of this modification is to settle a request for equitable adjustment as proposed by the contractor. $98,010
Supplemental Agreement for work within scope P00008 · The purpose of this modification is to extend the period of performance from 03/24/2023 to 10/23/2023 and the contracting officer duties are being transferred… $0
Supplemental Agreement for work within scope P00007 · The purpose of this modification is to descope engineering support for third power plant rahco 2000-ton crane. Defining task 5 optional task - engineering… -$99,280
Other Administrative Action P00006 · The purpose of this administrative modification is to complete the actions needed to extend the period of performance executed in modification P00005. $0
Supplemental Agreement for work within scope P00005 · The purpose of this modification is to extend the period of performance to 03/24/2023. $0
Exercise an Option P00004 · Grand coulee third powerplant crane controls, modification P00004 exercises optional task - engineering support during construction. $442,936
Other Administrative Action P00003 · Grand coulee third powerplant crane controls, modification P00003 changes contracting authority to colby a. Clifford. $0
Other Administrative Action P00002 · Grand coulee third powerplant crane controls, modification P00002 changes contracting authority to connie gordon from previously name contracting officer. $0
Supplemental Agreement for work within scope P00001 · Modification P00001 revises SOW, changes delivery date for clin 00010, and clarifies delivery description of CLIN00020. $130,253
Original award $361,059
Show all 21

About this award

The Bureau of Reclamation issued a delivery order to Ch2M Hill, Inc. on August 10, 2018, with a ceiling value of $1,463,149.77 for inspection, evaluation, and design modifications to Grand Coulee Third Powerplant crane controls.

Place of performance is Grand Coulee, WA. The order is priced firm fixed price with an ultimate completion date of December 19, 2025. No set-aside was used.

Service Contract Inventory reporting shows minimal labor activity across the order's life: $3 thousand invoiced in FY2018 and $239 thousand in FY2020, with 3 contractor hours reported in FY2021 at zero derived hourly rate. The prime self-performed all reported hours with no subcontractors.

Quick answers

Who was awarded contract 140R1018F0049?

140R1018F0049 was awarded to Ch2M Hill, Inc. by Bureau of Reclamation (Department of the Interior) on August 10, 2018.

How much is contract 140R1018F0049 worth?

The government has obligated $1,463,150 on 140R1018F0049. Its current value, with exercised options, is $1,463,150.

Is contract 140R1018F0049 an order under another contract?

Yes. 140R1018F0049 is a delivery order under INR13PC10008, an indefinite delivery contract.

Was contract 140R1018F0049 competed?

The extent of competition for 140R1018F0049 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award