Indefinite delivery-indefinite quantity, fixed-price, labor hour contract for title I, II, and III architect-engineering services for western area power administration's desert southwest customer…

Ended Indefinite Delivery Contract Awarded Last action

Contract number
DEAM6511WG81915
Awardee
Awarding agency
Task orders
62 $8,491,409 obligated

Award facts

Opportunity
Combined order value
  • $10,655,866 Current, with exercised options
  • $11,905,405 Potential, with all options
Last date to order 100% complete
IDV ceiling 28% used
$30,000,000.00
Maximum order
$1,000,000.00
Award type
Single award
Who can order
Only the awarding agency
NAICS code
541330 Engineering Services
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 7 offers Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price

Award details come from SAM.gov/FPDS.

Description

Indefinite delivery-indefinite quantity, fixed-price, labor hour contract for title I, II, and III architect-engineering services for western area power administration's desert southwest customer service region in arizona, california, and nevada.

Task orders

Task order Ordering agency Obligated Awarded
Title I services to provide geologic investigations for the gila-knob 230-KV T/line rebuild, between GLA-KNB structures… DEDT0010474 Western Area Power Administration $11,938
Task order 187 - SNR, north area buildings project design services DEDT0010369 Western Area Power Administration $264,957
Task order 185, tech I & II support work for the DSW security assessment projects. DEDT0009545 Western Area Power Administration $52,851
Task order 171. A/E tech I & tech II work for the new davis maintenance building construction. DEDT0008982 Western Area Power Administration $25,466
Task order 177 provide civil/electrical engineering tech I support on the mesa sub remediation project DEDT0008983 Western Area Power Administration $22,998
Title III services for project tracking, tech I & tech II support for mead stage 15. DEDT0008836 Western Area Power Administration $128,914
Ten-year capital program office and field study preparation parker-davis DEDT0008746 Western Area Power Administration $132,448
Task order 161 civil/electrical engineering tech I and II support on the gila stage 07 project. DEDT0007935 Western Area Power Administration $7,572
Task order 162 - a & E inspection services for the new davis maintenance building, on an as needed basis when the… DEDT0007984 Western Area Power Administration $3,280
A/E title III construction inspector for the blythe-headgate rock 161KV T-line reroute project, also known as black… DEDT0007795 Western Area Power Administration $121,847
Provide civil/electrical construction project tracking, tech I & II support for gila-north gila 69KV & gila-knob… DEDT0007570 Western Area Power Administration $69,284
Tech II services to perform 1 field & office study for the reconstruction of the 34.5 gila-gila valley laterals that… DEDT0007371 Western Area Power Administration $17,225
Non-destructive wood pole testing to determine strength of existing poles in the field. DEDT0007110 Western Area Power Administration $22,500
To 141 title III SVS on the apache-saguaro transmission system study. DEDT0007043 Western Area Power Administration $0
Title III a & E servicesto provide on-site inspection for the adams TAP project. DEDT0006947 Western Area Power Administration $0
A-E title I, II, III services. This task order is specifically for title III services construction inspection… DEDT0006587 Western Area Power Administration $41,932
Civil/electrical construction tech 1 and tech 2 support for the parker breaker replacement project under contract… DEDT0006402 Western Area Power Administration $26,340
To 134 - construction inspection services for SHA-KE-FLN reconductoring (SUBSTATIONS) DEDT0006258 Western Area Power Administration $421,226
To 131 - provide inspection services for support of liberty stage 05 transformer replacement. DEDT0006253 Western Area Power Administration $187,614
To 129 - construction inspection services for the gila-gila valley project DEDT0006248 Western Area Power Administration $115,307
To - 130 provide inspection services in support of the parker stage 09 161KV breaker replacement project. DEDT0006184 Western Area Power Administration $0
To 132 - provide inspection services in support of the facility ratings mitigation construction contract. DEDT0006185 Western Area Power Administration $96,287
Fund tech I and tech II services for the liberty transformer replacement (CD & E) DEDT0006045 Western Area Power Administration $45,958
Title III services for tech I, tech II support for the gila-gila valley project (to 119) DEDT0005270 Western Area Power Administration $86,761
Title III construction inspection services for the basic substation soil remediation phase 2 project. DEDT0004982 Western Area Power Administration $147,185
Title III SVS - provide civil/electrical construction insp for year 1 of TH facility rating mitigation proj. DEDT0004800 Western Area Power Administration $0
Title III SVS, tech I & II support on headgate rock-parker DAM & bouse-parker DAM double circuit 161KV T-line reroute… DEDT0004751 Western Area Power Administration $183,846
Title III services, project tracking, tech I & II support for kofa sub 45 mvar capacitor bank addition. DEDT0004559 Western Area Power Administration $63,220
Title III services, project tracking, tech I & II support for the tucson substation rebuild project. DEDT0004561 Western Area Power Administration $135,369
Title I geologic investigations, contamination identification for tucson sub rebuild project. DEDT0004488 Western Area Power Administration $82,745
Construction inspection services for hedge-tracy opgw (FY-13) - CDE to # 93 DEDT0004389 Western Area Power Administration $173,843
Title III construction inspection services for coolidge stage 09 substation project. DEDT0004282 Western Area Power Administration $706,167
New task order # 86, title III SVS, civil/electrical ENG. Tech I, II & PM support for the facility rating mitigation… DEDT0004233 Western Area Power Administration $81,989
To #83 - tech I (TRACKING) on the blythe-headgate rock 161KV T-line reroute project. DEDT0003940 Western Area Power Administration $40,152
Task order #80 - title I/II services on the mead administation demolition. DEDT0003864 Western Area Power Administration $73,451
To #74 - inspector on the mesa substation soil remediation assessment project DEDT0003617 Western Area Power Administration $576
To# 68 field studies for crsp DEAT6512WG95366 Western Area Power Administration $0
Task order 64 DEAT6512WG95570 Western Area Power Administration $0
Task order #62 a-E inspection services for bouse TAP project. DEAT6511WG95004 Western Area Power Administration $50,829
Task order # 63 AE services for inspection for davis kingman TAP. DEAT6511WG95005 Western Area Power Administration $590,067
Task order # 61, AE services for pre-solicitation specifications & drawings review for davis-kingman 69KV… DEAT6511WG94921 Western Area Power Administration $9,918
Task order #58, AE services for mead substation fire protection water and sewer rehabilitation. DEAT6511WG94681 Western Area Power Administration $84,480
Task order #54, architect-engineer inspection for coolidge archaeological study. DEAT6511WG94182 Western Area Power Administration $24,871
Task order # 52. Basic substation soil remediation inspection services. DEAT6511WG93840 Western Area Power Administration $244,875
Task order #43 - project manager for davis-kingman TAP T-line rebuild project. DEAT6511WG93258 Western Area Power Administration $120,396
Task order #32 - title III inspection services for the tracy substation, stage 07 construction project. DEAT6511WG92517 Western Area Power Administration $854,482
Task order #42 for project management on the bouse TAP upgrade to 3 PCB ring project. DEAT6511WG93257 Western Area Power Administration $107,303
Lands and row services on the parker davis power system DEAT6511WG92709 Western Area Power Administration $1,329
Task order #23 - tech I & II for needles northern connection. DEAT6511WG92293 Western Area Power Administration $46,170
Task order #24 - construction inspection services on davis 06 project. DEAT6511WG92295 Western Area Power Administration $545,482
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

Transactions

Action Obligated Date
Exercise an Option 6 $0
Change Order 5 $0
Exercise an Option 4 $0
Exercise an Option 3 · Title I, II, and III architect & engineering services. $0
Exercise an Option 2 · Modifiation to exercise the first option year. Title I, II, and III architect & engineering services. $0
Other Administrative Action M001 · Modification M001 increases the task order maximum value limit and eliminates the annual clin maximum amount. $0
Original award $0

Quick answers

Who was awarded contract DEAM6511WG81915?

DEAM6511WG81915 was awarded to Civil Design & Engineering Inc. by Western Area Power Administration (Department of Energy) on January 10, 2011.

How much is contract DEAM6511WG81915 worth?

Orders under DEAM6511WG81915 have obligated $8,491,409. Their combined current value, with exercised options, is $10,655,866. Their combined potential value, with all options, is $11,905,405. DEAM6511WG81915's own ceiling is $30,000,000. A single order can be worth up to $1,000,000.

How many orders have been placed under contract DEAM6511WG81915?

62 orders have been placed under DEAM6511WG81915, the latest on November 19, 2015.

Who can order from contract DEAM6511WG81915?

DEAM6511WG81915 is a single award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract DEAM6511WG81915 competed?

The extent of competition for DEAM6511WG81915 was full and open competition after exclusion of sources. The government received 7 offers. It was set aside: Total Small Business.