GSA awarded a single-award indefinite-delivery contract to Engie Resources LLC on November 1, 2026, with a ceiling of $1,090,128.16 and an ultimate completion date of May 31, 2032. The contract procures electricity commodity components, transmission, distribution, and ancillary services for 354 end-use utility accounts across 44 federal agencies in eight states, with no set-aside used.
Place of performance spans three regional transmission organizations: PJM Interconnection (District of Columbia, Delaware, Pennsylvania, New Jersey, Maryland, Ohio), Midcontinent Independent System Operator (MISO), and New York Independent System Operator (NYISO), with primary administrative oversight in Washington, DC.
The originating solicitation, posted January 21, 2026 with bids due February 26, 2026, required offerors to demonstrate current ISO/RTO approval as an electricity supplier, financial strength (A or better credit rating or audited financial statements dated January 1, 2024 or later), firm transmission service agreements, and documented experience supplying firm electricity to at least ten retail customers with peak demands exceeding 1,000 kW or one customer with multiple accounts exceeding 15,000 kW peak load within the applicable region during the prior 12 months. GSA evaluated offers on technical acceptability (pass/fail) followed by lowest price among acceptable offerors.
The contract runs through May 2032. Pricing is firm fixed-price per kilowatt-hour for each pricing group across the entire contract period, with fixed components including energy, ancillary services, scheduling, balancing and congestion costs, line losses, transmission, capacity, and RECs; economic price adjustments for transmission enhancements, capacity in some regions, and regulatory compliance costs; and pass-through costs for applicable taxes and region-specific charges. The energy procurement support contractor fee is $0.00085 per kWh.