The project is part of an early action package meant to facilitate the reconstruction of the east river tunnels, which were damaged by superstorm sandy in 2012 and which have reached the end of its…

Active Project Grant Awarded

Award ID
69A36525421260FSPDC
Recipient
Awarding agency
Obligated
$21,375,900

Award facts

Assistance listing
20.326 Federal-State Partnership for Intercity Passenger Rail
Completion date 76% complete
Funding
  • $10,687,950.00 Federal
  • $10,687,950.00 Non-federal
Place of performance
New York, USA

Award details come from USAspending.gov.

Description

The project is part of an early action package meant to facilitate the reconstruction of the east river tunnels, which were damaged by superstorm sandy in 2012 and which have reached the end of its useful life after over 112 years in operation. Under the project, the amtrak will construct the traction power cable relocation and replacement (S3 phase B) in the east river tunnel 1 and complete final design and construct the sunnyside yard track connection (sub 4).

Quick answers

Who received award 69A36525421260FSPDC?

69A36525421260FSPDC was awarded to National Railroad Passenger Corporation by Federal Railroad Administration (Department of Transportation) on July 15, 2025.

How much is award 69A36525421260FSPDC worth?

$21,375,900 has been obligated on 69A36525421260FSPDC: $10,687,950 in federal funding and $10,687,950 in non-federal funding.

On GovTribe

See this award's full record

  • Every transaction and subaward
  • The recipient's other awards and teaming partners
  • Similar grant awards
  • Ask GovTribe AI about this award