The project will replace 15 switches that have reached the end of their useful life within thebanana yard

Ended Project Grant Awarded Last action

Award ID
69A36523420010CCDWA
Recipient
Awarding agency
Obligated
$4,269,855

Award facts

Completion date
Originally
Funding
  • $2,500,000.00 Federal
  • $1,769,854.82 Non-federal
Place of performance
Tacoma, WA, USA

Award details come from USAspending.gov.

Description

Failed switches can result in excessive downtime and maintenance costs, further complicated by heavy rail volumes within the northwest seaport alliance(seattle tacoma) freight gateway. Once completed, the replaced switches will enable the yardto reduce and or eliminate the need for monthly repairs and ensure yard capacity remainsclose to 100 at all times. In addition, the project will help minimize rail dwell times and thecost of shipping by rail. The rail switch upgrade will support the long-term competitiveness ofthe port of tacoma and the northwest seaport alliance, and thus the long-term economiccompetitiveness of our region.

Transactions

Action Federal Non-federal Date
Amendment $0 $0
Amendment $0 $0
Original award $2,500,000 $1,769,855

Quick answers

Who received award 69A36523420010CCDWA?

69A36523420010CCDWA was awarded to Port Of Tacoma USA by Federal Railroad Administration (Department of Transportation) on February 1, 2023.

How much is award 69A36523420010CCDWA worth?

$4,269,855 has been obligated on 69A36523420010CCDWA: $2,500,000 in federal funding and $1,769,855 in non-federal funding.