Belt line corridor from lindbergh center to I-85, CST
Active Project Grant Awarded
- Award ID
- 693JJ22640000RA12GA0009395
- Recipient
-
Georgia Department Of Transportation UEI DEKQU1ZMTF89
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $31,250,000
Award facts
- Assistance listing
- 20.933 National Infrastructure Investments
- Completion date 13% complete
- Funding
-
- $25,000,000.00 Federal
- $6,250,000.00 Non-federal
- Funding agency
- Immediate Office of the Secretary of Transportation Department of Transportation
- Place of performance
- Georgia, USA
Award details come from USAspending.gov.
About this award
The Department of Transportation Immediate Office of the Secretary Transportation awarded the Georgia Department of Transportation, Division of Intermodal, a $31.25 million Project Grant on January 30, 2026, under the National Infrastructure Investments program (CFDA 20.933). The award funds the Belt Line Corridor from Lindbergh Center to I-85 construction project. The project delivers the proposed Atlanta BeltLine NE Trail, a 14-foot-wide concrete shared-use path of approximately 2.70 miles, plus approximately 2.10 miles of 12-foot-wide spur trail, along with several walls, bridges, and a tunnel. The trail begins at the existing terminus of the Eastside Trail at the intersection of 10th Street and Monroe Drive. Place of performance is Georgia, USA, and the ultimate completion date is March 31, 2032.
The program's BUILD grants fund capital investments in surface transportation infrastructure with significant local or regional impact, and the award is one of those capital awards. The Atlanta Development Authority, doing business as A D A, is the sub-grantee under a pass-through sub-award dated January 30, 2026, titled for the same Belt Line Corridor from Lindbergh Center to I-85 project.
Description
- Project description
- Belt line corridor from lindbergh center to I-85, CST; the proposed mainline atlanta beltline NE trail is a 14 FT wide concrete shared-use path approximately 2.70 miles in length. The project includes approximately 2.10 miles of spur trail 12 FT in width. The project also includes several walls and bridges and a tunnel. The proposed atlanta beltline NE trail begins at the existing terminus of the eastside trail at the intersection of 10TH street and monroe drive.
Subawards
| Subrecipient | Amount | Awarded |
|---|---|---|
| The Atlanta Development Authority | $25,000,000 |
Quick answers
Who received award 693JJ22640000RA12GA0009395?
693JJ22640000RA12GA0009395 was awarded to Georgia Department Of Transportation by Federal Highway Administration (Department of Transportation) on January 30, 2026.
How much is award 693JJ22640000RA12GA0009395 worth?
$31,250,000 has been obligated on 693JJ22640000RA12GA0009395: $25,000,000 in federal funding and $6,250,000 in non-federal funding.
Which agency awarded 693JJ22640000RA12GA0009395?
Federal Highway Administration (Department of Transportation) awarded 693JJ22640000RA12GA0009395, with funding from Immediate Office of the Secretary of Transportation (Department of Transportation).
On GovTribe
See this award's full record
- Every transaction and subaward
- The recipient's other awards and teaming partners
- Similar grant awards