The overall objective of the project is to perform the preliminary development work for an integrated carbon dioxide (CO2) capture project at the lake charles power station (lcps)

Ended Cooperative Agreement Awarded Last action

Award ID
DECD0000006
Recipient
Awarding agency
Obligated
$18,442,657

Award facts

Assistance listing
81.255 Clean Energy Demonstrations
Completion date
Funding
  • $9,221,328.00 Federal
  • $9,221,329.00 Non-federal
Place of performance
New Orleans, LA 70113, USA

Award details come from USAspending.gov.

Description

During the proposed project, the team will apply its knowledge base built from previous front end engineering design (feed) studies to complete the conceptual design of a carbon capture system intended to be capable of capturing a minimum of 95% of the CO2 emissions. The project team consists of entergy services, LLC (entergy), mitsubishi heavy industries america, INC. (mhia), talos energy, INC. (talos), and sargent & lundy (s & l). The feed study for the CO2 capture system will be completed by mhia and s & l including design deliverables consistent with the level needed to develop an association for the advancement of cost engineering (aace) class 3 estimate with an accuracy of ±15% for the entire scope of the capture facility and balance of plant. Talos intends to develop a feed study for the CO2 transportation infrastructure needed to access the sequestration off-take, evaluate the storage location, and develop the class VI permit application. The proposed project also includes execution of the community benefits plan (CBP). The completed feed study is intended to advance the lake charles power station CO2 capture project to be ready to move into the next phase of project development, permitting, and financing and ultimately construction and operation. In addition, the learnings from this project will benefit the five entergy utility operating companies as they explore implementation of CO2 capture across their fleet as part of their strategy to meet their customers' increasing need for sustainable energy and to achieve entergy's environmental, social, and governance (ESG) initiatives. Furthermore, the results of the study will have applicability for the US power generating fleet as this project is intended to demonstrate the ability to use this technology to reduce CO2 emissions from existing natural gas combined cycle generating facilities. The KM CDR process utilizing KS-21 solvent is currently at a technology readiness level (TRL) of 7, 6 when utilized with natural gas fired exhaust.

Transactions

Action Federal Non-federal Date
Amendment $0 $588,809
Amendment $0 $0
Amendment $0 $0
Amendment $0 $0
Amendment Entergy services, LLC: update the invoice approving official. Control number: 2738-1530 project title: lake charles power station integrated CO2 capture project… $0 $0
Amendment Entergy services, LLC: updating payment method from asap to vipers. Control number: 2738-1530 project title: lake charles power station integrated CO2 capture… $0 $0
Amendment $0 $0
Original award $9,221,328 $8,632,520

Subawards

Subrecipient Amount Awarded
Gulf Coast Sequestration, LLC T&S scope for FEED study $6,722,666
Mitsubishi Heavy Industries America, Inc. Carbon capture technology provider for FEED $5,249,857

Quick answers

Who received award DECD0000006?

DECD0000006 was awarded to Entergy Services, LLC by Department of Energy on January 1, 2024.

How much is award DECD0000006 worth?

$18,442,657 has been obligated on DECD0000006: $9,221,328 in federal funding and $9,221,329 in non-federal funding.

On GovTribe

See this award's full record

  • Every transaction and subaward
  • The recipient's other awards and teaming partners
  • Similar grant awards
  • Ask GovTribe AI about this award