The chino valley ranger district/upper verde river corridor fence reconstruction and removal project- replacement of livestock fence and the removal of existing electric fence and four strand barbed…

Ended Purchase Order Awarded Last action

Contract number
127EAU24P0128
Awardee
Awarding agency
Obligated
$13,500

Award facts

Contract value 100% obligated
$13,500.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Funding agency
Region 3 - Southwestern Region Forest Service, Department of Agriculture
Set-aside
Total Small Business
Competition
Competed under SAP · 8 offers Simplified Acquisition
Pricing
Firm Fixed Price
Place of performance
Groom Creek, AZ 86303, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00002 -$4,100
Funding Only Action P00001 · DE obligated remaining funds from project and start closeout. The chino valley ranger district/upper verde river corridor fence reconstruction and removal… -$13,500
Original award $31,100

About this award

This is a $13,500 firm-fixed-price purchase order awarded by the U.S. Department of Agriculture Forest Service to Salter Corey, doing business as Salter & Sons Construction, for the Chino Valley Ranger District/Upper Verde River Corridor Fence Reconstruction and Removal Project. The contract is a total small business set-aside and will replace approximately 0.5 miles of livestock fence and remove 1.57 miles of existing electric wire and four-strand barbed wire fence within the Prescott National Forest in Arizona. The work is to be completed by December 31, 2024. Salter & Sons Construction is an experienced small business federal contractor, having received 17 prior awards totaling over $1.3 million from agencies including the National Park Service, Forest Service, and Fish & Wildlife Service to provide construction, repair, and renovation services.

Description

The chino valley ranger district/upper verde river corridor fence reconstruction and removal project- replacement of livestock fence and the removal of existing electric fence and four strand barbed wire fence.

Quick answers

Who was awarded contract 127EAU24P0128?

127EAU24P0128 was awarded to Salter Corey by Forest Service (Department of Agriculture) on September 25, 2024.

How much is contract 127EAU24P0128 worth?

The government has obligated $13,500 on 127EAU24P0128.

Which agency awarded contract 127EAU24P0128?

Forest Service (Department of Agriculture) awarded 127EAU24P0128, with funding from Region 3 - Southwestern Region (Forest Service).

Was contract 127EAU24P0128 competed?

The extent of competition for 127EAU24P0128 was competed under sap. The government received 8 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award