Delivery Order W9128F25DA021-W9128F25FA129
- Not listed
- This is a firm fixed-price delivery order for $16,305,609.00 awarded by the U.S. Army Corps of Engineers, Omaha District to Western Contracting Corp, a for-profit organization based in Sioux City, Iowa. The task order is for repairs to the Missouri River Bank Stabilization and Navigation Project (BSNP) in the Boyer Billabong Structure area near Nebraska City, Nebraska. The work, which has an ultimate completion date of November 21, 2025, includes placing rock riprap, constructing revetments...
- This is a task order awarded to Western Contracting Corp, a for-profit organization based in Sioux City, Iowa, for the BSNP Missouri River South Repairs project. The contract, which is a delivery order, has a ceiling value of $14,959,165.00 and a completion date of November 21, 2025. It was awarded on September 20, 2023 by the U.S. Army Corps of Engineers (USACE), Omaha District, a defense agency. The task order is part of a larger Multiple Award Task Order Contract (MATOC) Indefinite Delivery...
- The Department of the Army Corps of Engineers awarded a $2.5 million firm fixed price delivery order against its Minimum Guarantee Missouri River BSNP MATOC IDIQ vehicle to Western Contracting Corp. to provide unspecified services in Omaha, Nebraska. The contract runs from July 2023 through July 2028 and was awarded using the Multiple Award Task Order Contract indefinite delivery/indefinite quantity contracting vehicle. No set aside designation or subcontractors were identified. The MATOC was...
- The U.S. Army Corps of Engineers (USACE) Omaha District awarded a $13,679,386 firm-fixed-price contract to Western Contracting Corp, a small business contractor, for the FY22 Bank Stabilization & Navigation Project (BSNP) along the Missouri River from River Mile 600 to 740 in Iowa, Missouri, and Nebraska. This work, set aside for small businesses, involves repairing critical bank stabilization and navigation structures damaged by the 2019 floods, including rehabilitating revetments, dikes,...
- The U.S. Army Corps of Engineers awarded a $12,425,468.27 firm fixed price contract to Western Contracting Corp to perform bank stabilization and navigation structure repairs along the Missouri River in Nebraska, Iowa, and Missouri. This contract supports the Corps' Missouri River Bank Stabilization and Navigation Project (BSNP), which aims to maintain the Missouri River's navigability and control flooding. The work involves adding quarried rock to rehabilitate damaged revetments, dikes,...
- The U.S. Army Corps of Engineers (USACE) Omaha District awarded a $19,586,438.64 firm fixed-price contract to Western Contracting Corp, a small business, for the FY22 Bank Stabilization & Navigation Project (BSNP) along the Missouri River from River Mile 498 to 600 in Iowa, Missouri, and Nebraska. The contract, which has an ultimate completion date of May 3, 2026, will rehabilitate critical damaged BSNP structures, including revetments, dikes, kickers, L-head dikes, and vanes, by adding...
- This is a firm fixed price delivery order awarded by the U.S. Army Corps of Engineers (USACE) to Western Contracting Corporation, a small business prime contractor, under the Corps' Missouri River Recovery Program (MRRP). The $560,592.62 award funds construction services for the Middle Decatur Embankment project in Iowa, which involves repairs and rehabilitation of flood control infrastructure along the Missouri River. The project has a completion date of November 3, 2017. Western Contracting...
- This is a firm fixed-price delivery order awarded to Western Contracting Corp, a for-profit small business organization based in Sioux City, Iowa, for the BSNP MR South Chute Repairs project. The $6,905,061.15 contract was awarded on September 21, 2023 by the U.S. Army Corps of Engineers (USACE) Omaha District, a defense agency, with an ultimate completion date of August 17, 2025. The task order is part of a larger $49,000,000 Multiple Award Task Order Contract (MATOC) Indefinite Delivery...
- This is a firm fixed-price definitive contract awarded by the U.S. Army Corps of Engineers to Western Contracting Corp, a small business prime contractor, for the Missouri River Bank Stabilization and Navigation Project Repair Structures for the 2019 Season (RM 522 to 498) in Nebraska and Missouri. The $2,379,513.12 contract, which was set aside for total small business participation, involves the procurement, transportation, and placement of stone riprap to repair damaged dikes, revetments,...
- This is a firm fixed price delivery order awarded by the U.S. Army Corps of Engineers (USACE) to Western Contracting Corp, a small business prime contractor, under the Missouri River Recovery Program (MRRP) indefinite delivery/indefinite quantity (IDIQ) contract. The $2,319,717.40 award is for the BASE, Langdon Bend TWW Phase 2 project, which involves construction services for flood control infrastructure repair and rehabilitation along the Missouri River in Nemaha, Nebraska. The work is related...
The U.S. Army Corps of Engineers, Omaha District (ENDIST Omaha), awarded a $2.62M delivery order to Western Contracting Corp on September 2, 2025, for maintenance and repair of navigation channels and bank stabilization along the Missouri River from Rulo, Nebraska (River Mile 498.2) to Lower Ponca Bend (River Mile 750.0). This delivery order is issued under Western Contracting Corp's existing Multiple Award Task Order Contract (MATOC) Indefinite Delivery Contract with the Corps, which was awarded on July 21, 2023, with a $49M ceiling and an ultimate completion date of July 20, 2028. The contract utilizes a firm fixed-price structure with no set-aside designation, though the underlying IDC is reserved for small businesses. Western Contracting Corp, a Sioux City, Iowa-based construction and infrastructure firm, has demonstrated specialized expertise in river bank stabilization and navigation project maintenance through prior work on the Missouri River Bank Stabilization and Navigation Project (BSNP). The contractor has received multiple task orders under its IDC totaling approximately $38M to date, focusing on placing stone, constructing revetments and dikes, and performing rehabilitation work on critical infrastructure along inland waterways. This delivery order, with an ultimate completion date of January 12, 2027, continues the Corps' mission to maintain navigable waterway channels and address bank stabilization needs in the Missouri River region, work that has been particularly important following the 2019 floods and ongoing infrastructure recovery efforts.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $2.6m | 9/2/25 |