Award contract for facade repair services to complete design, construction services, contract coordination and supervision/management, professional design services to replace the stone FA ADE to…

Active Awarded Last action

Contract number
SAQMMA17F4798
Awardee
Awarding agency
Obligated
$45,376,285

Award facts

Contract value 100% obligated
$45,469,588.38 Current and potential, with all options
Completion date 89% complete
Current and potential, with all options
Contracting staff
Funding agency
Bureau of Overseas Building Operations Department of State
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Cuba

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00037 · HVAC extended period of performance $448,595
Funding Only Action P00036 · Facilities management support and medium voltage switch gear design build $1,398,115
Supplemental Agreement for work within scope P00035 · Havana fire alarm replacement $3,439,555
Funding Only Action P00034 · Funding for an electrical storage system (ESS) battery and a site-appropriate structure for the embassy compound. $6,099,577
Funding Only Action P00033 $229,850
Funding Only Action P00032 · Funding MOD. $236,425
Other Administrative Action P00031 · Admin MOD. $0
Funding Only Action P00030 · Funding for design, furnishing, installation, testing and commissioning of battery energy storage systems (ESS) at four (4) residences at U.S. Embassy havana. $3,303,264
Funding Only Action P00029 · Funding for backup power capability to overcome loss of city utility or primary backup generator function/failures. $166,902
Other Administrative Action P00028 · Extend POP clin 37 at no cost. $12,130
Funding Only Action P00027 $339,184
Supplemental Agreement for work within scope P00026 $1,918,415
Funding Only Action P00025 $141,569
Funding Only Action P00024 · Add funding for additional in-scope work. $0
Funding Only Action P00023 · Add funding for repair deteriorated or damaged building or site elements including walkways, sea door, exterior stairway and perimeter fence-related work. $307,148
Supplemental Agreement for work within scope P00022 · Additional funding $819,390
Other Administrative Action P00021 · POP extension $0
Funding Only Action P00020 · OBO/SPC - reilly- paul - LE - funding only action. $927,348
Other Administrative Action P00019 · OBO/SPC - reilly- paul - LE - admin MOD. $0
Other Administrative Action P00018 $2,813,198
Funding Only Action P00017 · OBO/SPC - powell - paul - LE - funding only action. $7,055,114
Funding Only Action P00016 $98,613
Funding Only Action P00015 $622,036
Other Administrative Action P00014 · OBO/SPC - powell - paul - LE -the purpose of this no-cost MOD is to extend the period of performance to 538 days. The new completion date is now november 19,… $0
Funding Only Action P00013 · This modification is to recognize the novation agreement dated february 23, 2018 to transfer this havana facade repairs task order - SAQMMA17F4798 from… $891,690
Other Administrative Action P00012 · The purpose of this modification is to fund in the amount of $965,998.44 to modify the contract with reimbursable clin for contractor rental housing for the… $965,998
Supplemental Agreement for work within scope P00011 · This modification is to obligate funding. $82,500
Other Administrative Action P00010 $0
Supplemental Agreement for work within scope P00009 · This modification is to recognize the novation agreement dated february 23, 2018 to transfer this havana facade repairs task order - SAQMMA17F4798 from… $239,000
Funding Only Action P00008 · This is for funding the project $83,203
Other Administrative Action P00007 $0
Supplemental Agreement for work within scope P00006 · This is for havana facade repair $3,411,892
Supplemental Agreement for work within scope P00005 · The funding is to provide drivers for the project. $190,313
Supplemental Agreement for work within scope P00004 · The purpose of the MOD is to increase funding on the existing working. $4,526,716
Supplemental Agreement for work within scope P00003 · The modification is for febr repairs in havana $774,183
Supplemental Agreement for work within scope P00002 · The modification is for facade wall repairs $1,387,736
Other Administrative Action P00001 · This modification is to recognize the novation agreement dated february 23, 2018 to transfer this havana facade repairs task order - SAQMMA17F4798 from… $0
Original award $2,446,628
Show all 38

About this award

The Bureau of Overseas Building Operations issued a delivery order to Enviro-Management & Research, Inc. on September 29, 2017, under the Worldwide Design Build and Construction 2014–2019 IDIQ for facade repair services at the Havana Chancery with a ceiling value of $45.47 million.

The order covers design, construction services, contract coordination and supervision, and professional design services to replace the deteriorating stone facade and remedy life, health, and safety concerns. Work includes inspection of all stone panels, repair of damaged areas, implementation of limited construction site access through a security screening facility, support for technical security system infrastructure and equipment relocation, and activation of a consolidation and receiving point in Miami, Florida to support logistics and shipment requirements. Place of performance is Cuba. The order is set aside for Total Small Business with an ultimate completion date of December 7, 2027. Pricing is firm fixed price.

Description

Award contract for facade repair services to complete design, construction services, contract coordination and supervision/management, professional design services to replace the stone FA ADE to remedy the life health safety concern presented by the deteriorating havana chancery. The FA ADE repairs include inspection of all stone panels, repairing damaged areas. Implement limited access to the construction site through a security screening facility. Contractor required to support technical security system (TSS) infrastructure and equipment relocation for construction, activate the consolidation and receiving point (CRP) in support of logistics/shipment requirements based in miami, florida. All work will be in accordance with statement of work (SOW). 19X05352-1030-17ERA33-241000-7902-2503-XJ1Q0006 COR: forrest mclain - 703-875-4323 ________________________ OBO/pdcs/SPC G. Paul ________________________ OBO/pdcs/SPC F. Mclain ________________________ OBO/pdcs/SPC J. Salcedo ________________________ OBO/pdcs/SPC M. Wilson ________________________ OBO/RM/FM J. Reba ________________________ OBO/pdcs a. Dizon ________________________ OBO/RM J. Hochuli ________________________ OBO/DD a. Kanga ________________________ OBO/director W. Moser

Quick answers

Who was awarded contract SAQMMA17F4798?

SAQMMA17F4798 was awarded to Enviro-Management & Research, Inc. by Office of Acquisition Management (Department of State) on September 29, 2017.

How much is contract SAQMMA17F4798 worth?

The government has obligated $45,376,285 on SAQMMA17F4798. Its current value, with exercised options, is $45,469,588.

Which agency awarded contract SAQMMA17F4798?

Office of Acquisition Management (Department of State) awarded SAQMMA17F4798, with funding from Bureau of Overseas Building Operations (Department of State).

Is contract SAQMMA17F4798 an order under another contract?

Yes. SAQMMA17F4798 is a delivery order under SAQMMA14D0061, an indefinite delivery contract, on Worldwide Design Build and Construction 2014-2019.

Was contract SAQMMA17F4798 competed?

The extent of competition for SAQMMA17F4798 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award