Task order for the egress and accessibility upgrades project at the U.S. Embassy in kinshasa, the democratic republic of the congo.

Ended Awarded Last action

Contract number
SAQMMA15F4142
Awardee
Awarding agency
Obligated
$6,022,255

Award facts

Contract value 100% obligated
$6,022,254.64 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Bureau of Overseas Building Operations Department of State
Set-aside
Partial Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kinshasa, Democratic Republic of the Congo

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out P00007 · This modification hereby deobligates remaining funds on the task order -$350,700
Other Administrative Action P00006 · This modification hereby incorporates the IPP code for invoicing into the task order. For the emergency egress and accessibility upgrades project at the U.S.… $0
Supplemental Agreement for work within scope P00005 · Modification to kinshasa egress and accessibility upgrade project to incorporate RFP 8, settle REA 1 & 1B, REA 3, and REA 4 $102,870
Supplemental Agreement for work within scope P00004 · This modification hereby incorporates RFP 12 work, for TSS design changes, into the task order for the emergency egress and accessibility upgrades project at… $17,652
Supplemental Agreement for work within scope P00003 · This modification hereby incorporates rfps 002-003, and RFP 009 work into the task order for the emergency egress and accessibility upgrades project at the U.S.… $36,587
Supplemental Agreement for work within scope M002 · This modification hereby incorporates rfps 004-006 work into the task order for the emergency egress and accessibility upgrades project at the U.S. Embassy in… $14,914
Other Administrative Action M001 · This is unilateral modification to incorporate administrative changes to the scope of work for the emergency egress and accessibility upgrades project at the… $0
Original award $6,200,931

About this award

The Department of State's Bureau of Overseas Building Operations issued a delivery order to Trison Construction Inc., a women-owned small business, on September 30, 2015, for egress and accessibility upgrades at the U.S. Embassy in Kinshasa, Democratic Republic of the Congo, with a ceiling value of $6,022,254.64.

The order was issued under the Worldwide Design Build and Construction 2014-2019 IDIQ and was set aside as a partial small business procurement. Work was performed in Kinshasa, Democratic Republic of the Congo, with an ultimate completion date of May 30, 2017. The order was priced as firm fixed price. A subsequent modification deobligated remaining funds on the task order.

Quick answers

Who was awarded contract SAQMMA15F4142?

SAQMMA15F4142 was awarded to Trison Construction Inc. by Office of Acquisition Management (Department of State) on September 30, 2015.

How much is contract SAQMMA15F4142 worth?

The government has obligated $6,022,255 on SAQMMA15F4142.

Which agency awarded contract SAQMMA15F4142?

Office of Acquisition Management (Department of State) awarded SAQMMA15F4142, with funding from Bureau of Overseas Building Operations (Department of State).

Is contract SAQMMA15F4142 an order under another contract?

Yes. SAQMMA15F4142 is a delivery order under SAQMMA14D0052, an indefinite delivery contract, on Worldwide Design Build and Construction 2014-2019.

Was contract SAQMMA15F4142 competed?

The extent of competition for SAQMMA15F4142 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Partial Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award