Delivery Order N6945019D0517-N6945021F1857

Award Date 2/26/21
Potential Completion Date 8/25/21
Potential Value $57K
Ultimate Awardee
Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Millington, TN 38054, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
5
Legislative Mandate
Service Contract Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
<p>The Department of the Navy Naval Sea Systems Command (DON NAVSEA) awarded a $284,000 firm fixed price delivery order to Butt Construction Co Inc. under the Design-Bid-Build MACC NSA Mid-South 2019-2024 multiple award indefinite delivery indefinite quantity contract. Butt Construction Co Inc. will replace the main disconnect at the Millington, TN facility for the DON NAVSEA as part of this delivery order, which has a period of performance from May 15, 2023 through April 3, 2024.</p>
This federal contract award N6945019D0517|N6945024F0785 was issued by the Bureau of Naval Personnel, a Defense agency, to Butt Construction Company, Incorporated, a for-profit Subchapter S Corporation. The $66,000.00 firm-fixed-price delivery order is for the replacement of a pedestrian bridge at a location in Millington, Tennessee. This award is under the Design-Bid-Build MACC NSA Mid-South 2019-2024 multiple award construction contract, a $990 million IDIQ vehicle held by Butt Construction....
The Department of the Navy Naval Facilities Engineering Command awarded a $279,000 firm fixed price delivery order against the Design-Bid-Build MACC NSA Mid-South 2019-2024 master indefinite delivery/indefinite quantity contract to Butt Construction Co Inc. for sanitary sewer repairs in Millington, Tennessee. Butt Construction will perform UT FY21 SANITARY SEWER REPAIRS in Millington under the delivery order, which runs from August 11, 2021 through December 11, 2021. As the Naval Facilities...
This is a firm fixed-price delivery order contract awarded to Butt Construction Co Inc., a for-profit Subchapter S Corporation, by the Naval Facilities Engineering Command (NAVFAC). The contract has a ceiling value of $684,057 and a period of performance through February 13, 2025. The contract is a task order issued under the Design-Bid-Build Multiple Award Construction Contract (MACC) for the NSA Mid-South region, which has a total ceiling value of $990 million. Butt Construction Co Inc. is the...
Butt Construction Co Inc. was awarded a $1,000 firm fixed price delivery order against the Design-Bid-Build MACC NSA Mid-South 2019-2024 multiple award construction contract vehicle. This total small business set-aside award from the Department of the Navy Installations Command is for minimum guarantee work to be performed in Millington, Tennessee by August 21, 2024. The Design-Bid-Build MACC is a master indefinite delivery/indefinite quantity construction contract awarded by Naval Facilities...
The Department of the Navy, Naval Facilities Engineering Command awarded a $126,815 delivery order against the Design-Bid-Build MACC NSA Mid-South 2019-2024 master indefinite-delivery/indefinite-quantity contract to Core Engineering &amp; Construction, Inc. The firm fixed-price order is for the removal and replacement of an overhead door at the Naval Support Activity installation in Millington, Tennessee. Work will be performed from August 24, 2023 through November 24, 2023 at the specified...
This federal contract award was made by the Naval Facilities Engineering Command (NAVFAC), a defense agency, to Butt Construction Company, Incorporated, a for-profit Subchapter S Corporation. The $285,000.00 firm fixed price delivery order is for the repair of the west stairwell in Building 452 at the Naval Support Activity Mid-South facility in Millington, Tennessee. The contract is part of the Design-Bid-Build Multiple Award Construction Contract (MACC) for the NSA Mid-South region, which...
The Department of the Navy, Naval Facilities Engineering Command awarded a $136,175 firm fixed price delivery order against the Design-Bid-Build MACC NSA Mid-South 2019-2024 master indefinite delivery/indefinite quantity contract to Core Engineering &amp; Construction, Inc. The delivery order is for the X008 Building 787 Army warehouse build out in Millington, Tennessee, with work to be completed between September 2023 and December 2023. The Design-Bid-Build MACC NSA Mid-South 2019-2024...
This federal contract award was issued by the Bureau of Naval Personnel, a defense agency, to Butt Construction Company, Incorporated, a for-profit Subchapter S Corporation. The $1,380,500.00 firm-fixed-price delivery order is part of the $990 million Design-Bid-Build MACC NSA Mid-South 2019-2024 contract vehicle, which enables Butt Construction to compete for task orders across different military installations and federal facilities. The contract is for BLDG 769 ADDITIONAL COOLING TOWER at...
<p>The Department of the Navy Installations Command awarded a $883,963 firm fixed price delivery order to Core Engineering &amp; Construction, Inc. under the Design-Bid-Build MACC NSA Mid-South 2019-2024 master indefinite delivery indefinite quantity contract. Core Engineering &amp; Construction, Inc. will provide repair of the roof and expansion joints at Building 456 located in Millington, Tennessee. The period of performance is from June 15, 2023 through February 15, 2024.</p>

The Department of the Navy Naval Facilities Engineering Command awarded a $57,336 delivery order against the Design-Bid-Build MACC NSA Mid-South 2019-2024 master indefinite-delivery/indefinite-quantity contract to Butt Construction Co Inc. for the removal and replacement of Pedestrian Bridge 1841 at the Millington, Tennessee facility. Work will be performed from February 26, 2021 through August 25, 2021 under the firm fixed-price contract. The Naval Facilities Engineering Command will utilize this order to carry out bridge infrastructure repairs at the Navy support site in Millington as part of its facilities sustainment programs.

Generated 12/30/23, 6:13 AM