P454 multi-mission dry dock - early contractor involvement

Active Awarded Last action

Contract number
N4425523F4028
Awardee
Awarding agency
Obligated
$3,525,000

Award facts

Contract value 100% obligated
$3,525,000.00 Current and potential, with all options
Completion date 96% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Honolulu, HI 96813, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00013 $0
Supplemental Agreement for work within scope P00012 · This firm-fixed-price task order obtains ECI pre-construction services for the mcon p-454 M2D2. $0
Other Administrative Action P00011 · The purpose of this modification is to incorporate notice to proceed, revised performance work statement (85% design review) and applicable clauses IAW far… $0
Supplemental Agreement for work within scope P00010 · The intent of this modification is to increase the total task order not to exceed (NTE) by $100K which covers the cost of travel for the ECI contractor, to… $100,000
Supplemental Agreement for work within scope P00009 · P454 multi-mission dry dock - early contractor involvement. Modification provides additional ECI constructability review effort associated with up to 80% and… $3,000,000
Supplemental Agreement for work within scope P00008 · P454 multi-mission dry dock - ECI time extension $0
Supplemental Agreement for work within scope P00007 · P454 multi-mission dry dock - ECI $0
Supplemental Agreement for work within scope P00006 · P454 multi-mission dry dock - early contractor involvement. Modification increases the not to exceed value by $275K from $150K to $425K for the 50%… $275,000
Other Administrative Action P00005 · P454 multi-mission dry dock - early contractor involvement - extend period of performance $0
Supplemental Agreement for work within scope P00004 $0
Supplemental Agreement for work within scope P00003 · P454 multi-mission dry dock - early contractor involvement - 35% review $0
Supplemental Agreement for work within scope P00002 $0
Supplemental Agreement for work within scope P00001 · P454 multi-mission dry dock - early contractor involvement. Increase funds by $75K in support of 15% and 35% design reviews. $75,000
Original award $75,000
Show all 14

About this award

The Naval Facilities Engineering Command issued a $3.525 million firm-fixed-price delivery order to Dragados / Hawaiian Dredging / Orion JV on December 16, 2022, under the Shipyard Infrastructure Optimization Program Hawaii MACC for early contractor involvement pre-construction services on the P-454 Multi-Mission Dry Dock.

The Shipyard Infrastructure Optimization Program Hawaii MACC is a multiple award construction contract with an $8 billion ceiling supporting infrastructure upgrades at Pearl Harbor and other Hawaii shipyards through 2029. Place of performance is Honolulu, Hawaii. The order is firm-fixed-price with an ultimate completion date of December 31, 2026.

Quick answers

Who was awarded contract N4425523F4028?

N4425523F4028 was awarded to Dragados / Hawaiian Dredging / Orion JV by Naval Facilities Engineering Command (Department of the Navy) on December 16, 2022.

How much is contract N4425523F4028 worth?

The government has obligated $3,525,000 on N4425523F4028.

Is contract N4425523F4028 an order under another contract?

Yes. N4425523F4028 is a delivery order under N6274222D1311, an indefinite delivery contract, on Shipyard Infrastructure Optimization Program Hawaii MACC.

Was contract N4425523F4028 competed?

The extent of competition for N4425523F4028 was full and open competition. The government received 5 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award