Task order for phase 1 for the 0% through functional analysis concept development (FACD) phase for FY15 mcon P-861, facility modifications for VMU, mwsd, and CH53E, marine corps base hawaii,…

Ended Awarded Last action

Contract number
0007
Awardee
Awarding agency
Obligated
$4,271,156

Award facts

Contract value 100% obligated
$4,271,156.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition Architect-Engineer FAR 6.102
Pricing
Firm Fixed Price
Place of performance
MCBH K BAY, HI 96863, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 10 · Extend task order completion date. $0
Supplemental Agreement for work within scope 9 · Second option year performance period $0
Supplemental Agreement for work within scope 8 · Task order modification to extend completion date. $0
Supplemental Agreement for work within scope 7 · Task order modification to redesign the underground tanks located in the B-373 site. Task order 0007 is for FY15 mcon P-861 facility modifications for VMU, mwsd… $40,972
Supplemental Agreement for work within scope 6 · Task order modification for post construction award services (PCAS). Task order 0007 is for FY15 mcon P-861 facility modifications for VMU, mwsd and CH53E,… $517,780
Supplemental Agreement for work within scope 5 · Task order modification for post construction award services (PCAS) for the off-site drainage utilities small business set-aside DBB RFP package. Task order… $30,256
Supplemental Agreement for work within scope 4 · Task order modification to incorporate leed enhanced commissioning services during design, construction, occupany and operations. Task order 0007 is for FY15… $158,307
Supplemental Agreement for work within scope 3 · Task order modification to prepare a small business set-aside DBB RFP package for the 6TH street and 3RD & B street storm water system upgrades. Task order 0007… $17,615
Supplemental Agreement for work within scope 2 · Task order modification for additional topographic surveying. Task order 0007 is for FY15 mcon P-861 facility modifications for VMU, mwsd and CH53E, marine… $15,746
Supplemental Agreement for work within scope 1 · Task order modification for phase 2 to complete the design from facd to final design. Task order 0007 provided for phase 1 for the 0% through facd phase for… $3,086,537
Original award $403,943
Show all 11

Description

Task order for phase 1 for the 0% through functional analysis concept development (FACD) phase for FY15 mcon P-861, facility modifications for VMU, mwsd, and CH53E, marine corps base hawaii, kaneohe, hawaii. Contract N62742-11-D-0006 is an IDIQ contract for design, engineering, specification writing, cost estimating at various locations under the cognizance of navfacpac.

Quick answers

Who was awarded contract 0007?

0007 was awarded to Design Partners, Incorporated by Naval Facilities Engineering Command (Department of the Navy) on February 4, 2014.

How much is contract 0007 worth?

The government has obligated $4,271,156 on 0007.

Is contract 0007 an order under another contract?

Yes. 0007 is a delivery order under N6274211D0006, an indefinite delivery contract.

Was contract 0007 competed?

The extent of competition for 0007 was full and open competition.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award