P891 siop shipyard electrical backbone, puget sound naval shipyard (psns), bremerton, WA.

Active Awarded Last action

Contract number
N4425524F4392
Awardee
Awarding agency
Obligated
$147,153,972

Award facts

Opportunity
Contract value 99% obligated
$149,383,141.30 Current and potential, with all options
Completion date 46% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Bremerton, WA 98337, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00016 · The purpose of this modification is to incorporate far clause 52.222-90 into the task order $0
Supplemental Agreement for work within scope P00015 $840,223
Supplemental Agreement for work within scope P00014 $333,825
Supplemental Agreement for work within scope P00013 · The purpose of this modification is to incorporate proposed change (PC) 20 design deficiency and PC-23 unforeseen condition changes into the scope of work. $209,645
Change Order P00012 · The purpose of this modification is to incorporate proposed change (PC) 15, 18, 19, and 21 design deficiency changes into the scope of work. $546,074
Other Administrative Action P00011 · The purpose of this modification is to incorporate dfars 252.225-7013 duty-free entry (AUG 2025) clause into task order N4425524F4392. $0
Change Order P00010 $43,662
Supplemental Agreement for work within scope P00009 $174,860
Change Order P00008 · The purpose of this modification is to incorporate proposed change (PC) 13 unforeseen conditions, into the scope of work. $80,738
Change Order P00007 · The purpose of this modification is to incorporate proposed change (PC) 03 design deficiency changes, PC 04, PC 05, and PC 06 value engineering changes, and… -$1,079,381
Change Order P00006 · The purpose of this modification is to incorporate proposed change (PC) 10 design deficiency changes into the scope of work. $189,196
Change Order P00005 $141,570
Change Order P00004 $133,308
Change Order P00003 $52,924
Change Order P00002 · The purpose of this modification is to incorporate proposed change (PC) 02 design deficiency changes into the scope of work. $220,328
Other Administrative Action P00001 · Extend period of performance from 04 april 2029 to 13 april 2029 $0
Original award $145,267,000
Show all 17

About this award

Naval Facilities Engineering Command issued a $147.7 million delivery order to Absher Construction Co on September 16, 2024, under the NAVFAC MACC Construction IDIQ for design and construction of the P891 SIOP Shipyard Electrical Backbone at Puget Sound Naval Shipyard, Bremerton, Washington. Work is firm fixed price with an ultimate completion date of April 22, 2029.

NAVFAC MACC Construction is an indefinite delivery contract vehicle for military construction and facility services issued by Naval Facilities Engineering Command. Place of performance is Bremerton, WA. The order incorporates FAR Clause 52.222-90 via modification.

Absher Construction Co is a for-profit Subchapter S Corporation and a substantial federal military construction prime contractor specializing in design-build and design-bid-build facility work for Navy and Army installations across the Pacific Northwest and Hawaii. The company holds the parent NAVFAC MACC vehicle valid through September 2031 and competes full-and-open across its portfolio with no set-aside designations.

Subcontractors include Safari Electric LLC for substation systems and medium voltage cabling, Potelco Inc. for high-voltage and medium-voltage supply, and a multi-vendor team providing specialized services in electrical systems, structural steel, mechanical and plumbing, masonry, roofing, asphalt paving, rebar reinforcement, HVAC and controls, sheet metal, security fencing, and site demolition and abatement.

Subawards

Subcontractor Amount Awarded
Olson Brothers Pro-Vac, LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Vault Testing and Pumping $36,346
Railworks Track Systems LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Railroad Tracks $255,786
Subcontractor not on record P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Site Concrete $364,943
Clark Services NW LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Damp Proofing & Joints $64,666
Dickson Company P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Demo (Select) and Abatement $738,350
Sabelhaus West Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Painting $60,360
Perimeter Security Group, LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Security Fencing $98,644
Apex Steel, Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Steel Install (Complete) $247,311
Stirrett-Johnsen, Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Plumbing $478,000
Northwest Asphalt, Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Asphalt Paving $646,928
Pacific Steel Group, LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Rebar Reinforcement $378,664
Subcontractor not on record P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Roofing (Complete) $249,340
Safari Electric LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Medium Voltage Cabling $5,028,000
Safari Electric LLC P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Substation Systems $5,006,237
Architectural Sheet Metal Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Flashing and Sheetmetal $93,730
Miller Sheetmetal Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. HVAC and Controls $600,632
Keystone Masonry, Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Masonry (Complete) $944,548
Pivetta Brothers Construction Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Civil (Complete) $19,160,770
Potelco Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. High Voltage: Complete, Med Voltage: Supply $47,629,814
Nuuco Electric Co P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Ductback/Gear Set $17,327,337
Donald B. Murphy Contractors, Inc. P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. Shoring (Complete) $2,899,695
Show all 21

Quick answers

Who was awarded contract N4425524F4392?

N4425524F4392 was awarded to Absher Construction Co by Naval Facilities Engineering Command (Department of the Navy) on September 16, 2024.

How much is contract N4425524F4392 worth?

The government has obligated $147,153,972 on N4425524F4392. Its current value, with exercised options, is $149,383,141.

Is contract N4425524F4392 an order under another contract?

Yes. N4425524F4392 is a delivery order under N4425523D1700, an indefinite delivery contract, on NAVFAC MACC Construction.

Was contract N4425524F4392 competed?

The extent of competition for N4425524F4392 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities