Design/bid/build upgrade HVAC system and SRM windows replacement

Ended Awarded Last action

Contract number
0008
Awardee
Awarding agency
Obligated
$7,345,546

Award facts

Opportunity
Contract value 100% obligated
$7,345,546.09 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Z1AA Maintenance Of Office Buildings
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Philadelphia, PA 19111, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action 19 · Modification to recoup funding for work not completed/needed -$17,200
Other Administrative Action 18 · Payment for 3 REA's; remove lead incased medium voltage cables, asbestos floor tiles, asbestos insulation. $41,574
Supplemental Agreement for work within scope 17 · Other functions option year 1 (7/22/11 - 7/21/12) $8,393
Other Administrative Action 16 · MOD to fund 3 request for equitable adjustments. Reas for swale cleanup, door replacement and materials needed for extreme weather $9,237
Additional Work (new agreement, FAR part 6 applies) 15 · MOD to fund PC's for wallace suite receptacles - $3,753.74 and repair window water infiltration - $59,091.00 $62,845
Additional Work (new agreement, FAR part 6 applies) 14 · MOD to link PC31, 32, 34, 35, 36 and fund REA 02 for $81,908.31 $81,908
Additional Work (new agreement, FAR part 6 applies) 13 · MOD to fund electrical changes/electrical panels/light fixtures/CMU walls $326,136
Additional Work (new agreement, FAR part 6 applies) 12 · MOD to fund the repairs needed to fix 2 windows in bldg 26 $29,785
Additional Work (new agreement, FAR part 6 applies) 11 · This modification will fund 10 proposed changes that were found during the renovation. All changes are needed to finish critical path actions. $45,163
Additional Work (new agreement, FAR part 6 applies) 10 · Modification to task order to include funding need for storm water permit needed for renovations $22,180
Additional Work (new agreement, FAR part 6 applies) 9 · Modification to incorporate additional work - renovations now include light fixtures $87,622
Additional Work (new agreement, FAR part 6 applies) 8 · MOD to provide funding for electrical panel installation at bldg 26 nsap $12,414
Additional Work (new agreement, FAR part 6 applies) 7 $367,547
Supplemental Agreement for work within scope 6 $20,404
Supplemental Agreement for work within scope 5 $11,105
Additional Work (new agreement, FAR part 6 applies) 4 $224,352
Additional Work (new agreement, FAR part 6 applies) 3 $236,542
Exercise an Option 2 · Option year 1 (7/22/11 - 7/21/12) $1,001,000
Other Administrative Action 1 · This administrative modification is issued to transfer ACO authority/responsibilities to PWD philadelphia. $0
Original award $4,774,540
Show all 20

Quick answers

Who was awarded contract 0008?

0008 was awarded to WU & Associates Inc. by Naval Facilities Engineering Command (Department of the Navy) on June 1, 2012.

How much is contract 0008 worth?

The government has obligated $7,345,546 on 0008.

Is contract 0008 an order under another contract?

Yes. 0008 is a delivery order under N4008510D9451, an indefinite delivery contract, on NAVFAC MIDLANT NE Construction 2010-2016.

Was contract 0008 competed?

The extent of competition for 0008 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award