Petaluma DBB construction contract recap wastewater treatment plant replacement
Ended Awarded Last action
- Contract number
- HSCG5012JPPTLM1
- Awardee
-
CDM Constructors Inc. UEI FNR6BRLYXXT3
- Awarding agency
-
Coast Guard
Department of Homeland Security
- Obligated
- $37,111,021
Award facts
- Contract value 100% obligated
- $37,111,021.05 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 3 offers Multiple Award, Fair Opportunity
- Pricing
- Firm Fixed Price
- Place of performance
- Petaluma, CA, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $335,510 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $131,950 | |
| Supplemental Agreement for work within scope | $9,000 | |
| Supplemental Agreement for work within scope | $10,310 | |
| Supplemental Agreement for work within scope | $21,990 | |
| Supplemental Agreement for work within scope | $25,885 | |
| Supplemental Agreement for work within scope | $26,074 | |
| Supplemental Agreement for work within scope | $23,340 | |
| Supplemental Agreement for work within scope | $26,328 | |
| Definitize Change Order | $0 | |
| Supplemental Agreement for work within scope | $114,696 | |
| Supplemental Agreement for work within scope | $303,018 | |
| Supplemental Agreement for work within scope | $330,000 | |
| Definitize Change Order | -$100,000 | |
| Definitize Change Order | -$7,728 | |
| Supplemental Agreement for work within scope | -$148,355 | |
| Supplemental Agreement for work within scope | $7,077 | |
| Supplemental Agreement for work within scope | $78,231 | |
| Change Order | $45,000 | |
| Supplemental Agreement for work within scope | $163,327 | |
| Supplemental Agreement for work within scope | $161,251 | |
| Change Order | $50,000 | |
| Change Order | $100,000 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Change Order | $0 | |
| Supplemental Agreement for work within scope | $49,500 | |
| Change Order | $35,000 | |
| Change Order | $75,000 | |
| Definitize Change Order | -$2,657 | |
| Supplemental Agreement for work within scope | $191,655 | |
| Change Order | $83,000 | |
| Supplemental Agreement for work within scope | -$111,794 | |
| Supplemental Agreement for work within scope | $49,411 | |
| Modification | $35,035,000 | |
| Close Out | $0 |
Show all 37
About this award
This is a $37,111,021.05 firm-fixed-price delivery order contract awarded by the U.S. Coast Guard to CDM Constructors Inc., a subsidiary of CDM Smith Inc., for a design-build construction project to replace the Petaluma Wastewater Treatment Plant. The contract was issued under the Department of Homeland Security's Design-Build and Construction indefinite delivery, indefinite quantity (IDIQ) contract vehicle. The project has a December 11, 2014 completion date and does not have a set-aside designation.
Quick answers
Who was awarded contract HSCG5012JPPTLM1?
HSCG5012JPPTLM1 was awarded to CDM Constructors Inc. by Coast Guard (Department of Homeland Security) on May 24, 2012.
How much is contract HSCG5012JPPTLM1 worth?
The government has obligated $37,111,021 on HSCG5012JPPTLM1.
Is contract HSCG5012JPPTLM1 an order under another contract?
Yes. HSCG5012JPPTLM1 is a delivery order under HSCG4709D3EFK03, an indefinite delivery contract, on DHS Design-Build and Construction IDIQ.
Was contract HSCG5012JPPTLM1 competed?
The extent of competition for HSCG5012JPPTLM1 was full and open competition. The government received 3 offers.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award