PS03 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL FUNDING FOR THE WHA 3906 PROJECT LOCATED AT MAIN STATE. THE PERIOD OF PERFORMANCE HAS ALSO BEEN EXTENDED TO JUNE 30, 2014. ORIGINAL CONTRACT AMOUNT: $1,563,482.00 MODIFICATION PS01 AMOUNT: $50,837.84 MODIFICATION PS02 AMOUNT: $170,972.00 THIS MODIFICATION PS03 AMOUNT: $53,954.00 NEW CONTRACT AMOUNT: $1,839,245.84 Supplemental Agreement for work within scope $54.0k 5/27/14 PS02 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL FUNDING FOR THE WHA 3906 PROJECT LOCATED AT MAIN STATE. THE ADDITIONAL WORK WILL CONSIST OF: CE#9: ADDITION OF NEW 100AMP ELECTRICAL PANEL CLOSET CE#10: ADD A SHUT OFF TEE VALVE CE#11: PURCHASE NEW EMERGENCY LIGHTS AND NEW CONDUIT CE#12: FIX AIR LEAK AND RECONNECTION OF PNEUMATIC CONTROL LINE CE#13: RELOCATION OF EXISTING CONDUIT AND EMERGENCY CIRCUIT CE#14: TIME FOR ACCELERATED COMPLETION OF WORK CE#15: ADDITIONAL 4" CONDUIT REQUEST CE#16: ADDITIONAL PLYWOOD FOR CER ROOM AND ENTRY DOORS CE#17: RE-ROUTING OF SPRINKLER LINES CE#18: ADDITIONAL DUCT INSULATION CE#19: ADDITIONAL MILLWORK TO CONCEAL CONDUITS CE#20: RELOCATION OF VAV BOX IN CEILING AREA ORIGINAL CONTRACT AMOUNT: $1,563,482.00 MODIFICATION PS01 AMOUNT: $50,837.84 THIS MODIFICATION AMOUNT: $170,972.00 NEW CONTRACT AMOUNT: $ 1,785,291.84 ALL OTHER TERMS AND CONDITIONS WILL REMAIN THE SAME. Supplemental Agreement for work within scope $171.0k 12/20/13 PS01 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL FUNDING FOR THE WHA 3906 PROJECT LOCATED AT MAIN STATE. THE PERIOD OF PERFORMANCE HAS BEEN EXTENDED TO FEBRUARY 28, 2014. ORIGINAL CONTRACT AMOUNT: $1,563,482.00 THE MODIFICATION PS01 AMOUNT: $50,837.84 NEW CONTRACT AMOUNT: $ 1,614,319.84 ALL OTHER TERMS AND CONDITIONS WILL REMAIN THE SAME. Supplemental Agreement for work within scope $50.8k 12/20/13 Not listed CONSTRUCTION AND RENOVATION SERVICES FOR THE BUREAU OF WESTERN HEMISPHERE AFFAIRS - WHA/CAN/MEX, SUITE 3906 LOCATED IN THE HST MAIN STATE BUILDING. IN ACCORDANCE WITH THE SCOPE OF WORK (DATED JANUARY 4, 2013) AND RFP (DATED FEBRUARY 5, 2013). Not listed $1.6m 3/19/13