Recovery-construction manager as constructor (CMC) services, pre-construction phase services, HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 west jackson blvd. Chicago, IL.

Ended Awarded Last action

Contract number
GSP0510SI5020
Awardee
Awarding agency
Obligated
$2,161,634

Award facts

Contract value 100% obligated
$2,161,634.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Chicago, IL 60604, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order PC12 -$10,427
Change Order PC11 · Recovery - GS05P07SID0022/GSP0510SI5020, arra HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 W. Jackson blvd, chicago, IL. This modification… $0
Change Order PC10 · Recovery - GS05P07SID0022/GSP0510SI5020, HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 W. Jackson blvd., chicago, IL. Reference page 4, the… $10,427
Change Order PC09 · Recovery - GS05P07SID0022/GSP0510SI5020, arra HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 W. Jackson blvd, chicago, IL. This modification… $0
Change Order PC08 · GS05P07SID0022/GSP0510SI5020, HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 W. Jackson blvd., chicago, IL. Reference page 4, the GSA form… $347,801
Other Administrative Action PA07 · PA07 - administrative MOD to change the contract expiration date $0
Change Order PC06 · Change order CE5003 $80,244
Other Administrative Action PA05 $0
Other Administrative Action PA04 $0
Change Order PC03 · GS05P07SID0022/GSP0510SI5020 HVAC & lighting upgrades, ralph H. Metcalfe federal building, 77 W. Jackson blvd., chicago, IL. Reference page 3, GSA form 1137,… $29,422
Change Order PC02 · Extension of backbone lighting system from floors 2 through 28. $41,207
Exercise an Option PS01 · Recovery- construction manager as constructor (CMC) services, construction phase services, HVAC and lighting upgrades, ralph H. Metcalfe federal building, 77… $1,638,000
Original award $24,960
Show all 13

About this award

This is a federal contract award to Madison Services Inc., a self-certified small disadvantaged, woman-owned small business, for Construction Manager as Constructor (CMC) services, pre-construction phase services, HVAC and lighting upgrades for the Ralph H. Metcalfe Federal Building in Chicago, Illinois. The contract, awarded by the General Services Administration (GSA) Region 5, has a ceiling value of $2,161,634.00 and is a firm fixed-price delivery order. The contract is not set-aside and is part of a larger $50 million multiple-award Indefinite Delivery/Indefinite Quantity (IDIQ) contract with GSA Region 5 for repair and alteration services across six Midwestern states. Madison Services Inc. also holds a separate $37.5 million IDIQ contract for repair and alterations specifically in Michigan, Minnesota, and Wisconsin.

Quick answers

Who was awarded contract GSP0510SI5020?

GSP0510SI5020 was awarded to Madison Services Inc. by Region 5 (Public Buildings Service) on November 25, 2009.

How much is contract GSP0510SI5020 worth?

The government has obligated $2,161,634 on GSP0510SI5020.

Is contract GSP0510SI5020 an order under another contract?

Yes. GSP0510SI5020 is a delivery order under GS05P07SID0022, an indefinite delivery contract.

Was contract GSP0510SI5020 competed?

The extent of competition for GSP0510SI5020 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award