This firm fixed price delivery order is being awarded to trio general contracting associates (one of four awardees under an multiple-award IDIQ contract for repairs and alterations), to install a fall…

Ended Awarded Last action

Contract number
GSP0211PV5026
Awardee
Awarding agency
Obligated
$124,331

Award facts

Contract value 100% obligated
$124,330.59 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
PSC
Not on record
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
New York, NY 10004, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA02 · This administrative MOD is being issued to deobligate $0.01 so that the contract BAN be closed-out. The contractor's invoice reflected one penny less that the… -$0
Change Order PS01 · Installation of a fall safety protection system for the rotunda/skylight alexander hamilton united states custom house one bowling green new york, new york… $4,351
Original award $119,980

About this award

This firm fixed price delivery order was awarded by the General Services Administration Public Buildings Service Region 2 (GSA-PBS) to Trio Asbestos Removal Corp., doing business as Trio Asbestos Removal Corp, to install a fall safety protection system for the rotunda/skylight at the Alexander Hamilton United States Custom House located at One Bowling Green in New York, New York. The period of performance for completion of the project was ninety calendar days from April 18, 2011 through July 18, 2011, with a total of $119,980.01 in obligated funds. The contract type was a delivery order under an indefinite-delivery, indefinite-quantity multiple award contract for repairs and alterations. The place of performance was Bowling Green, New York and the pricing structure was firm fixed price. The set aside was for total small business. This delivery order aimed to enhance safety at a GSA-PBS facility through installation of fall protection at the historic Alexander Hamilton United States Custom House building.

Description

This firm fixed price delivery order is being awarded to trio general contracting associates (one of four awardees under an multiple-award IDIQ contract for repairs and alterations), to install a fall safety protection system for the rotunda/skylight at the alexander hamilton united states custom house, one bowling green; new york, new york 10004-1415. The period of performance to completion is ninety (90) calendar days, effective from april 18, 2011 through july 18, 2011. The total obligated funds for this project is $119,980.01.

Quick answers

Who was awarded contract GSP0211PV5026?

GSP0211PV5026 was awarded to Trio Asbestos Removal Corp. by Region 2 (Public Buildings Service) on April 15, 2011.

How much is contract GSP0211PV5026 worth?

The government has obligated $124,331 on GSP0211PV5026.

Is contract GSP0211PV5026 an order under another contract?

Yes. GSP0211PV5026 is a delivery order under GS02P07PVD0010, an indefinite delivery contract.

Was contract GSP0211PV5026 competed?

The extent of competition for GSP0211PV5026 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award