Recovery, , MT PRA glac 10(23), gtsr rehabilitation big bend to logan pass, phase VIII
Ended Awarded Last action
- Contract number
- DTFH7007D00009T09004
- Awardee
-
H-K Contractors, Inc. UEI FPM7V1ZC8WU2
- Awarding agency
-
Federal Highway Administration
Department of Transportation
- Obligated
- $42,581,647
Award facts
- Opportunity
-
- DTFH7008R00032 Solicitation number
- RECOVERY - MT PRA-GLAC 10(23), GTSR Rehabilitation, Big Bend to Logan Pass, Phase VIII Award Notice · Posted Sep 30, 2008
- Contract value 100% obligated
- $42,581,647.40 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Y222 Construct/Highways-Rds-Sts-Brdgs-Ra
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 1 offer Negotiated Proposal / Quote
- Pricing
- Fixed Price with Economic Price Adjustment
- Place of performance
- Babb, MT 59411, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Close Out | -$2,833,349 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$22,866 | |
| Supplemental Agreement for work within scope | -$264 | |
| Supplemental Agreement for work within scope | -$21 | |
| Supplemental Agreement for work within scope | -$13 | |
| Supplemental Agreement for work within scope | -$35 | |
| Supplemental Agreement for work within scope | -$460 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | $113,978 | |
| Supplemental Agreement for work within scope | $49,223 | |
| Supplemental Agreement for work within scope | -$100 | |
| Supplemental Agreement for work within scope | $14,530 | |
| Definitize Change Order | $0 | |
| Definitize Change Order | $0 | |
| Supplemental Agreement for work within scope | $20,850 | |
| Supplemental Agreement for work within scope | $334,010 | |
| Supplemental Agreement for work within scope | -$89,300 | |
| Definitize Change Order | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$113 | |
| Supplemental Agreement for work within scope | -$27 | |
| Supplemental Agreement for work within scope | $0 | |
| Supplemental Agreement for work within scope | -$35 | |
| Supplemental Agreement for work within scope | -$78 | |
| Supplemental Agreement for work within scope | -$14 | |
| Supplemental Agreement for work within scope | -$140 | |
| Funding Only Action | $275,000 | |
| Funding Only Action | $270,000 | |
| Funding Only Action | $33,000 | |
| Supplemental Agreement for work within scope | -$170 | |
| Supplemental Agreement for work within scope | $28,000 | |
| Supplemental Agreement for work within scope | $62,075 | |
| Supplemental Agreement for work within scope | $19,200 | |
| Supplemental Agreement for work within scope | $350,700 | |
| Supplemental Agreement for work within scope | $24,690 | |
| Definitize Change Order | -$64,085 | |
| Supplemental Agreement for work within scope | $40,680 | |
| Change Order | $200,000 | |
| Supplemental Agreement for work within scope | -$222,682 | |
| Other Administrative Action | $242,894 | |
| Other Administrative Action | -$242,894 | |
| Other Administrative Action | $484,568 | |
| Other Administrative Action | -$484,568 | |
| Supplemental Agreement for work within scope | $1,265,600 | |
| Supplemental Agreement for work within scope | $2,282,171 | |
| Supplemental Agreement for work within scope | $5,596,492 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
This is a $42,581,647.40 delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency within the U.S. Department of Transportation (DOT), to H-K Contractors, Inc., a for-profit construction company. The delivery order is part of a larger Going-To-The-Sun Road Rehabilitation multiple-award task order contract, which has a $590 million total ceiling value.
The purpose of this delivery order is to fund the Recovery, Transportation, and Accessibility Services (TAS) program's Glacier 10(23) project, specifically the rehabilitation of the Going-To-The-Sun Road from Big Bend to Logan Pass, Phase VIII. This work is being performed in Babb, Montana. No set-aside was used for this award. H-K Contractors has been awarded over $200 million in federal contracts from the FHWA and has experience in national park and environmentally sensitive infrastructure projects.
Quick answers
Who was awarded contract DTFH7007D00009T09004?
DTFH7007D00009T09004 was awarded to H-K Contractors, Inc. by Federal Highway Administration (Department of Transportation) on July 9, 2009.
How much is contract DTFH7007D00009T09004 worth?
The government has obligated $42,581,647 on DTFH7007D00009T09004.
Is contract DTFH7007D00009T09004 an order under another contract?
Yes. DTFH7007D00009T09004 is a delivery order under DTFH7007D00009, an indefinite delivery contract, on Going-To-The-Sun Road Rehabilitation.
Was contract DTFH7007D00009T09004 competed?
The extent of competition for DTFH7007D00009T09004 was full and open competition. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award