Recovery, , MT PRA glac 10(23), gtsr rehabilitation big bend to logan pass, phase VIII

Ended Awarded Last action

Contract number
DTFH7007D00009T09004
Awardee
Awarding agency
Obligated
$42,581,647

Award facts

Opportunity
Contract value 100% obligated
$42,581,647.40 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Negotiated Proposal / Quote
Pricing
Fixed Price with Economic Price Adjustment
Place of performance
Babb, MT 59411, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 67 · Critical functions MT PRA glac 10(23) big bend to logan pass phase VIII -$2,833,349
Other Administrative Action 66 · Critical functions MT PRA glac 10(23) gtsr big bend to logan pass, phase VIII $0
Supplemental Agreement for work within scope 59 $0
Supplemental Agreement for work within scope 65 -$22,866
Supplemental Agreement for work within scope 64 -$264
Supplemental Agreement for work within scope 63 -$21
Supplemental Agreement for work within scope 61 -$13
Supplemental Agreement for work within scope 62 -$35
Supplemental Agreement for work within scope 60 -$460
Supplemental Agreement for work within scope 27 $0
Supplemental Agreement for work within scope 34 $0
Supplemental Agreement for work within scope 38 $0
Supplemental Agreement for work within scope 49 $113,978
Supplemental Agreement for work within scope 57 $49,223
Supplemental Agreement for work within scope 55 · Critical functions MT PRA glac 10(23) big bend to logan pass phase VIII -$100
Supplemental Agreement for work within scope 52 $14,530
Definitize Change Order 54 $0
Definitize Change Order 51 $0
Supplemental Agreement for work within scope 58 $20,850
Supplemental Agreement for work within scope 47 $334,010
Supplemental Agreement for work within scope 53 -$89,300
Definitize Change Order 48 · Critical functions MT PRA glac 10(23) big bend to logan (VIII) $0
Supplemental Agreement for work within scope 56 $0
Supplemental Agreement for work within scope 50 · Critical functions MT PRA glac 10(23) big bend to logan pass, phase VIII -$113
Supplemental Agreement for work within scope 42 · Critical functions MT PRA glac 10(23) big bend to logan (VIII) -$27
Supplemental Agreement for work within scope SA1 · Critical functions MT PRA glac 10(23) big bend to logan pass phase VIII $0
Supplemental Agreement for work within scope 30 · MT PRA glac 10(23) big bend to logan pass phase VIII -$35
Supplemental Agreement for work within scope 45 -$78
Supplemental Agreement for work within scope 41 -$14
Supplemental Agreement for work within scope 40 · MT PRA glac 10(23) gtsr wall repair phase VIII -$140
Funding Only Action 37 $275,000
Funding Only Action 36 $270,000
Funding Only Action 35 $33,000
Supplemental Agreement for work within scope 33 · MT PRA glac 10(23) big bend to logan pass, phase VIII -$170
Supplemental Agreement for work within scope 28 $28,000
Supplemental Agreement for work within scope 31 $62,075
Supplemental Agreement for work within scope 23 $19,200
Supplemental Agreement for work within scope 4 · MT PRA glac 10(23) gtsr wall repair phase VIII $350,700
Supplemental Agreement for work within scope 29 $24,690
Definitize Change Order 25 -$64,085
Supplemental Agreement for work within scope 22 · Recovery MT PRA glac 10(23) gtsr wall repair phase VIII $40,680
Change Order CM024 · MT PRA glac 10(23) gtsr wall repair phase VIII $200,000
Supplemental Agreement for work within scope 14 · MT PRA glac 10(23) big bend to logan (VIII) -$222,682
Other Administrative Action 20 $242,894
Other Administrative Action 20A · MT PRA glac 10(23) big bend to logan pass, phase VIII accounting change -$242,894
Other Administrative Action 19 $484,568
Other Administrative Action 19A -$484,568
Supplemental Agreement for work within scope 17 $1,265,600
Supplemental Agreement for work within scope 7 $2,282,171
Supplemental Agreement for work within scope 7A · MT PRA glac 10(23) big bend to logan pass, phase VIII $5,596,492
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

This is a $42,581,647.40 delivery order awarded by the Federal Highway Administration (FHWA), a civilian agency within the U.S. Department of Transportation (DOT), to H-K Contractors, Inc., a for-profit construction company. The delivery order is part of a larger Going-To-The-Sun Road Rehabilitation multiple-award task order contract, which has a $590 million total ceiling value.

The purpose of this delivery order is to fund the Recovery, Transportation, and Accessibility Services (TAS) program's Glacier 10(23) project, specifically the rehabilitation of the Going-To-The-Sun Road from Big Bend to Logan Pass, Phase VIII. This work is being performed in Babb, Montana. No set-aside was used for this award. H-K Contractors has been awarded over $200 million in federal contracts from the FHWA and has experience in national park and environmentally sensitive infrastructure projects.

Quick answers

Who was awarded contract DTFH7007D00009T09004?

DTFH7007D00009T09004 was awarded to H-K Contractors, Inc. by Federal Highway Administration (Department of Transportation) on July 9, 2009.

How much is contract DTFH7007D00009T09004 worth?

The government has obligated $42,581,647 on DTFH7007D00009T09004.

Is contract DTFH7007D00009T09004 an order under another contract?

Yes. DTFH7007D00009T09004 is a delivery order under DTFH7007D00009, an indefinite delivery contract, on Going-To-The-Sun Road Rehabilitation.

Was contract DTFH7007D00009T09004 competed?

The extent of competition for DTFH7007D00009T09004 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award