National capital region 11 energy savings performance contract for the installation of energy conservation measures and long term measurement and verification services.

Active Awarded Last action

Contract number
47PM0721F0094
Awardee
Awarding agency
Obligated
$70,835,856

Award facts

Opportunity
Contract value 29% obligated
  • $70,835,855.81 Current, with exercised options
  • $241,752,328.00 Potential, with all options
Completion date 22% complete
Current and potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 12 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20407, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action PA0029 · Funding modification for year 3 (FY2026) $6,059,815
Other Administrative Action PA0028 · Incorporation of assignment of claims $0
Supplemental Agreement for work within scope PS0026 · This modification decouples the white house complex from district steam. $0
Change Order PO0025 · Allocation of base project contingency funds. $0
Additional Work (new agreement, FAR part 6 applies) PS0024 · This modification purchases new cooling towers for eisenhower executive office building, upgrades the building automation system and repairs multiple HVAC… $4,934,731
Other Administrative Action PA0021 · Update of accounting strings $0
Funding Only Action PO0017 · Year 1 performance period payment. $5,963,625
Supplemental Agreement for work within scope PS0016 · RRB cooling tower replacement - hpgb IRA funded $18,855,230
Funding Only Action PA0015 · Deobligate funds from clin 0001 for cost allocation -$40,813
Supplemental Agreement for work within scope PS0014 · Electrical outage support $61,952
Other Administrative Action PA0012 · Cost allocation correction $40,813
Funding Only Action PO0011 · Funding for (year 1) construction period savings, principal and interests, omrr and performance period services for MV and MA $7,723,285
Additional Work (new agreement, FAR part 6 applies) PS0010 · Inflation reduction act signage for ronald reagan building. $0
Supplemental Agreement for work within scope PS0009 · Ronald reagan building electrification by installing heat pumps and electric boilers. $22,688,397
Funding Only Action PO0008 · Construction period savings for FY 23 $1,648,011
Funding Only Action PO0007 · Guaranteed utility rebates $134,000
Funding Only Action PO0006 · Construction period savings FY 22 $55,867
Other Administrative Action PS0005 · Add security language for contractor performance on EOP campus $0
Other Administrative Action PA0004 · Change CO from denise avery-craft to adam carlson $0
Supplemental Agreement for work within scope PS0003 · BAS upgrade for espc $1,395,110
Supplemental Agreement for work within scope PS0002 $0
Other Administrative Action PA0001 · This modification transfers contracting officer authority from tannis taylor to denise avery-craft $0
Original award $1,315,833
Show all 23

About this award

The National Capital Region issued a funding modification delivery order to Johnson Controls Government Systems, LLC on May 1, 2021, under the Department of Energy's Energy Savings Performance Contracts 2017-2022 (ESPC) for National Capital Region 11 energy conservation measures and long-term measurement and verification services. The order carries a $241.75 million ceiling value and firm fixed price terms, with ultimate completion scheduled for April 30, 2046.

Place of performance is Washington, DC. The order funds installation of energy conservation measures across federal facilities in the National Capital Region, including HVAC and building system upgrades, cooling tower replacements, boiler commissioning, building automation system replacements, and long-term energy performance monitoring and verification.

In FY2024, the order invoiced $10.1 million across 9.4 FTEs and 19,463 contractor hours, with a derived government-paid rate of $516.56 per hour. Pricing has risen from $248.08 per hour in FY2021. Johnson Controls self-performed all reported hours without subcontractor support on the SCI inventory.

Major subcontractors include Powersecure Inc. (cooling tower and steam plant decoupling work), Schneider Electric Federal Inc. (building automation system and cooling tower replacement), Mucat Technologies Inc. (mechanical and HVAC labor, and consulting services), and Onix II Inc., an SBA-certified HUBZone firm (boiler commissioning).

Subawards

Subcontractor Amount Awarded
Mucat Technologies, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $40,000
Mucat Technologies, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $1,876,623
Aqualogix LLC NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $84,979
Onix II, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $134,540
Powersecure, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $12,172,369
Powersecure, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $27,308,800
Schneider Electric Federal, Inc. NATIONAL CAPITAL REGION 11 ENERGY SAVINGS PERFORMANCE CONTRACT FOR THE INSTALLATION OF ENERGY CONSERVATION MEASURES AND LONG TERM MEASUREMENT AND VERIFICATION… $752,273
James Vito Inc. RONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS. Plumbing, Heating and Air Conditioning Services $157,445
Onix, Inc. RONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS. Commissioning $55,893
Northstar Contracting Group, Inc. RONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS. Remediation Services, Site Preparation Contractors, Facilities Support… $575,000
Subcontractor not on record RONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS. Installation of technologies to seal the building shell and improve energy… $1,676,183
Mucat Technologies, Inc. RONALD REAGAN BUILDING ELECTRIFICATION BY INSTALLING HEAT PUMPS AND ELECTRIC BOILERS. Consulting Services $3,077,130
Show all 12

Quick answers

Who was awarded contract 47PM0721F0094?

47PM0721F0094 was awarded to Johnson Controls Government Systems, LLC by National Capital Region (Public Buildings Service) on May 1, 2021.

How much is contract 47PM0721F0094 worth?

The government has obligated $70,835,856 on 47PM0721F0094. Its potential value, with all options, is $241,752,328.

Is contract 47PM0721F0094 an order under another contract?

Yes. 47PM0721F0094 is a delivery order under DEEE0008032, an indefinite delivery contract, on DOE Energy Savings Performance Contracts 2017-2022 (ESPC).

Was contract 47PM0721F0094 competed?

The extent of competition for 47PM0721F0094 was full and open competition. The government received 12 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award