The contractor will complete a comprehensive installation and performance of energy conservation measures (ecms) in accordance with (IAW) the referenced department of energy (DOE) super energy savings…
Active Awarded Last action
- Contract number
- SP060010F8250
- Awardee
-
Johnson Controls Government Systems, LLC UEI RXNUR4G46NG3
- Awarding agency
-
Energy
Defense Logistics Agency, Department of Defense
- Obligated
- $19,590,983
Award facts
- Opportunity
-
- SP060008R0811 Solicitation number
- Contract value 59% obligated
- $33,472,656.62 Current and potential, with all options
- Completion date 69% complete
- Current and potential, with all options
- Contracting staff
- Funding agency
- Southwest Region Installation Management Command, Department of Defense
- NAICS code
- Not on record
- PSC
- R499 Support- Professional: Other
- Competition
- Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
- Pricing
- Firm Fixed Price
- Place of performance
- Fort Hood, TX 76544, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Funding Only Action | -$326,290 | |
| Funding Only Action | $782,443 | |
| Funding Only Action | $365,382 | |
| Funding Only Action | $365,382 | |
| Funding Only Action | $390,903 | |
| Other Administrative Action | $0 | |
| Funding Only Action | $390,903 | |
| Funding Only Action | $377,196 | |
| Funding Only Action | $401,984 | |
| Funding Only Action | $352,409 | |
| Funding Only Action | $1,423 | |
| Funding Only Action | $739,750 | |
| Other Administrative Action | $0 | |
| Funding Only Action | $363,977 | |
| Funding Only Action | $363,977 | |
| Other Administrative Action | $0 | |
| Funding Only Action | $715,202 | |
| Funding Only Action | $351,225 | |
| Funding Only Action | $351,225 | |
| Change Order | $0 | |
| Funding Only Action | $373,939 | |
| Funding Only Action | $361,640 | |
| Funding Only Action | -$18,821 | |
| Funding Only Action | $293,498 | |
| Change Order | $0 | |
| Funding Only Action | $338,926 | |
| Funding Only Action | $45,429 | |
| Funding Only Action | $337,623 | |
| Funding Only Action | $5,000 | |
| Funding Only Action | $305,000 | |
| Funding Only Action | $300,001 | |
| Funding Only Action | $22,062 | |
| Funding Only Action | $305,001 | |
| Funding Only Action | -$16,228 | |
| Funding Only Action | -$60 | |
| Funding Only Action | -$226,665 | |
| Funding Only Action | $1,010,739 | |
| Funding Only Action | $272,761 | |
| Funding Only Action | $315,665 | |
| Funding Only Action | $313,774 | |
| Funding Only Action | $41,627 | |
| Funding Only Action | $546,720 | |
| Funding Only Action | $20,814 | |
| Funding Only Action | $881,085 | |
| Funding Only Action | $20,216 | |
| Funding Only Action | $293,932 | |
| Funding Only Action | $869,785 | |
| Funding Only Action | $283,661 | |
| Funding Only Action | -$168,966 | |
| Funding Only Action | $830,060 |
Show 40 more
Latest 50 listed here. See the rest on GovTribe.
About this award
The Department of Energy issued a delivery order to Johnson Controls Government Systems, LLC on December 30, 2009, under the DOE Super Energy Savings Performance Contracting (ESPC) Indefinite Delivery/Indefinite Quantity vehicle with a ceiling value of $33,472,656.62. The order has a total estimated value of $33,460,247.50 across a 23-year performance period commencing after construction completion, with an ultimate completion date of April 30, 2034.
The delivery order requires installation and performance of energy conservation measures at Fort Hood, Texas, including a Utility Monitoring Control System upgrade (ECM 3.1), energy-efficient lighting upgrade (ECM 5.1), and solar thermal water heating (ECM 11.1). Under the express contractual terms, annual cost savings are guaranteed and must exceed annual contractor payments in each performance year. Construction comprises "Year Zero," during which the contractor receives pre-performance payments for energy savings and cost savings accrued; remaining pre-performance payments are due at the first performance period payment. The pricing structure is firm fixed price. This modification deobligates fiscal year 2026 funding from CLIN 28 for contractor payments initially obligated in error.
Description
The contractor will complete a comprehensive installation and performance of energy conservation measures (ecms) in accordance with (IAW) the referenced department of energy (DOE) super energy savings performance contracting (espc) indefinite delivery / indefinite quantity (IDIQ) vehicle. Specific ecms to be implemented under this desc delivery order (do) SP0600-10-f-8250 include: ECM 3.1 - utility monitoring control system (umcs) upgrade; ECM 5.1 - energy-efficient lighting upgrade; and ECM 11.1 - solar thermal water heating. The performance period of 23 years will commence at the end of the construction period. The construction period will be identified as "year zero", and pre-performance payments will be made to the contractor for energy savings and cost savings accrued during year zero. Pre-performance period payments remaining at the end of year zero, to include construction period savings, will be payable at the time of the first performance period contractor payment. By the express terms of the SP0600-10-f-8250 contractual agreement, "annual cost savings" are "guaranteed". Therefore, annual cost savings must exceed "annual contractor payments" for each year of the delivery order (do) performance period. The contract award value is the total amount of all annual contractor payments to be made under this delivery order. Pursuant to desc contracting instruction (CI) 09-01 depi 4.6 "contract reporting (fpds-NG)", total estimated dollars awarded under SP0600-10-f-8250 is $33,460,247.50. Consistent with "reporting data" at 4.606(a)(2)(III) of the aforementioned CI, at the time of this espc award a "zero" dollar amount is entered into fpds for the instant action obligation. Consistent with CI 09-01A "additional guidance - federal procurement data system (fpds) and contract action report (car)", the total estimated contract value of $33,460,247.50 is entered at the "base and all options value" block in the "amounts" section of this transaction.
Quick answers
Who was awarded contract SP060010F8250?
SP060010F8250 was awarded to Johnson Controls Government Systems, LLC by Energy (Defense Logistics Agency) on December 30, 2009.
How much is contract SP060010F8250 worth?
The government has obligated $19,590,983 on SP060010F8250. Its current value, with exercised options, is $33,472,657.
Which agency awarded contract SP060010F8250?
Energy (Defense Logistics Agency) awarded SP060010F8250, with funding from Southwest Region (Installation Management Command).
Is contract SP060010F8250 an order under another contract?
Yes. SP060010F8250 is a delivery order under DEAM3698G010329, an indefinite delivery contract.
Was contract SP060010F8250 competed?
The extent of competition for SP060010F8250 was full and open competition. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award