Other Administrative Action
50 · Blue grass chemical agent destruction pilot plant (legacy) change issue by and administer by dodaac
$0
Supplemental Agreement for work within scope
49
$0
Supplemental Agreement for work within scope
48
-$1,214,421
Supplemental Agreement for work within scope
47
-$232,558
Supplemental Agreement for work within scope
46 · This contract is for the design, construction, systemization, operations and closure of the blue grass chemical agent destruction pilot plant (bgcapp). The…
-$321,235
Supplemental Agreement for work within scope
45 · Phase IV proposal cost and fee; administrative funding
-$689,430
Supplemental Agreement for work within scope
44 · Authorize cost PBI payment and funding deobligations.
-$3,834,187
Supplemental Agreement for work within scope
43 · Transfer of scope
$0
Other Administrative Action
42 · Authorize PBI
$0
Other Administrative Action
41 · Authorize invoicing of PBI and administrative correction
$0
Other Administrative Action
40 · Update PBI definitions.
$0
Supplemental Agreement for work within scope
39 · Lntp phase III bgcapp
$4,218,160
Supplemental Agreement for work within scope
38 · In accordance with dfars 232.906(a)(i), far clause 52.232-25 prompt payment ALT i and far clause 52.232-27 prompt payment for construction contracts are…
$0
Supplemental Agreement for work within scope
37 · The purpose of modification 36 to task order 0004 is to authorize billing for MDB vertical TAR PBI approval and add rdte funding for phase iiib
$2,068,456
Supplemental Agreement for work within scope
36 · The purpose of modification 36 to task order 0004 is to: 1. Formalize negotiations to complete phase iiib construction. This proposed work is within the basic…
$9,828,224
Supplemental Agreement for work within scope
35 · Formalize negotiations to complete phase II construction addendum.
$0
Supplemental Agreement for work within scope
34 · The purpose of modification 34 to task order 0004 is to do the following: 1. DE-obligate FY 08 MCD funds in the amount of $43,020,072.00 from support efforts of…
-$44,538,671
Supplemental Agreement for work within scope
33 · The purpose of modification 33 to task order 0004 is to do the following: 1. FY 08 MCD funds are hereby obligated in the amount of $9,000,000.00 to support…
$31,000,000
Supplemental Agreement for work within scope
32 · 1. Formalize negotiation to complete phase iiia construction. The proposed work is within the basic contract SOW of contract DAAA09-03-d-0023, task order…
$1,518,599
Supplemental Agreement for work within scope
31 · The purpose of modification 31 to task order 0004 is to do the following: 1. FY 09 rdte funds are hereby obligated in the amount of $7,610,441.60 to support…
$7,610,442
Supplemental Agreement for work within scope
30 · 1. The purpose of modification 30 to task order 0004 is to obligate FY 08 MCD funds in the amount of $43,020,072.00 to support efforts for phase IV construction…
$43,020,072
Supplemental Agreement for work within scope
29 · The purpose of modification 29 to task order 0004 is to do the following: 1. Provide FY 07 MCD funds to cover assessed interest payments as indicated below:…
$4,303
Supplemental Agreement for work within scope
27 · The purpose of modification 27 to task order 0004 is to do the following: 1. Obligated FY 07 rdte funds in the amount of $4,430,458.40 to support continued…
$17,764,858
Supplemental Agreement for work within scope
28 · DE-obligate funds not used within the program.
-$11,664,960
Supplemental Agreement for work within scope
26 · Provide funds in the amount of $1,886,263 for enhanced earned value management system (evms) implementation.
$1,886,263
Supplemental Agreement for work within scope
25 · 1. To identify an error in task order 0004 modification 23. Item #9 summary of PBI schedule, milestone #4 value is corrected from $665,367.00 to $887,155.00. 2.…
$0
Supplemental Agreement for work within scope
24 · Add RDT & e and MCD funding in the amount of $44,153,300.00
$44,153,300
Supplemental Agreement for work within scope
23 · Add MCD and rdte funding.
$15,036,872
Supplemental Agreement for work within scope
22 · Formalize negotiations to complete changes to access roads and earthwork construction IAW engineering change proposals (ECP) 009 and 010. This proposed work…
$0
Supplemental Agreement for work within scope
21 · 1. The purpose of modification 21 task order 0004 is to: a. Provide funds in the amount of $4,188,560 for phase III construction MDB concrete and direct project…
$4,188,560
Supplemental Agreement for work within scope
20 · 1. The purpose of modification 20 task order 0004 is to: a. Provide funds in the amount of $12,000,000.00 for phase III construction - project services…
$12,000,000
Funding Only Action
19 · 1. The purpose of modification 19 task order 0004 is to: a. Transfer $483,582.51 from the access road & earthworks (AR & e) effort to the phase 2 construction…
$0
Supplemental Agreement for work within scope
18 · 1. The purpose of modification 18 task order 0004 is to: a. Extend the period of performance for the access road and earthworks (AR & e) effort limited notice…
$0
Funding Only Action
17 · 1. Provide funds in the amount of $5,223,000.00 for phase III construction - part a (138KV substation) limited notice to proceed (lntp). 2. The period of…
$5,223,000
Change Order
16 · Extend the period of performance for the access road and earthworks (AR & e) effort limited notice to proceed (lntp).
$0
Funding Only Action
15 · 1. Payment in the amount of $215,000.00 is hereby authorized and accepted by the government for the access road and earthwork (AR & e) performance based…
$0
Funding Only Action
14 · 1. Provide funds for phase IIB construction lntp. 2. The period of performance of performance for phase IIB lntp is: from: april 02, 2007 to: october 31, 2007
$28,507,200
Funding Only Action
13 · 1. Provide $321,006 funds for phase III construction planning and preparation lntp. 2. The period of performance for this effort is january 15, 2005 through…
$321,006
Funding Only Action
12 · Provide funds in the amount of $266,000.00 for the access road and earthwork effort (AR & e) effort to support the implementation of engineering change proposal…
$266,000
Change Order
11 · 1. Extend the period of performance for the access road and earthworks (AR & e) effort limited notice to proceed (lntp). 2. Extend the period of performance for…
$0
Funding Only Action
10 · Transfer money from phase 2 construction to access road & earhworks.