Delivery Order AG05M6C160041-1205M618F0001

Award Date 10/27/17
Potential Completion Date 11/3/17
Potential Value $29K
Ultimate Awardee
Not listed
Federal Contract Vehicle
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
Everett, WA 98201, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
3
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This is a firm fixed-price purchase order contract awarded by the U.S. Department of Agriculture Forest Service, Region 2 - Rocky Mountain Region, to Big R Manufacturing LLC, doing business as Big R Bridge, for the supply of a culvert for the Beaver Creek Fire BAER (Burned Area Emergency Response) implementation project. The contract has a ceiling value of $20,721.00 and was awarded on February 13, 2017, with a completion date of March 13, 2017. The contract does not have a set-aside...
The U.S. Department of Agriculture Forest Service awarded a $219,160 firm fixed price delivery order to Ketchikan Ready-Mix & Quarry, Inc. to remove and dispose of an existing corrugated metal pipe on Road 3036 at milepost 0.27 in Coffman Cove, Alaska and replace it with a 55-foot structural plate arch culvert composed of a corrugated metal arch and concrete footings. The contractor will also restore the streambed upstream and downstream. There was no set-aside designation for this award...
The Department of Agriculture Forest Service R6-Pacific Northwest Region awarded a $122,217.36 firm fixed price delivery order contract to Great West Engineering Inc. to design a hydraulic culvert at a site 18.89 miles up the 101 Road adjacent to an AOP structure in Kamiah, Idaho. The stream channel above the culvert site is too steep to support good fish habitat, so the culvert must be sized to accommodate the 100-year flood flow event while allowing for fish passage. As part of its mission...
This firm-fixed-price delivery order was awarded to Price Contracting Inc., a veteran-owned small business, by the United States Forest Service (USFS) Northern Region for the BAER: Steep Gulch Culvert Replacement project. The $82,005 contract will replace an undersized culvert to allow increased water flows to pass under the road without causing damage to the crossing. This work is being performed under the agency's road maintenance and infrastructure upgrade programs, which are funded through...
The U.S. Department of Agriculture Forest Service awarded a $98,117.80 firm fixed price delivery order contract to Jack Bowen Excavating of Mt Tabor, Vermont. The contract calls for the replacement of an existing five-foot diameter culvert with a new seven-foot, three-inch wide by five-foot, three-inch high by seventy-eight-foot long aluminized steel pipe arch culvert. Additional work includes removal of an existing temporary bridge and its relocation. The contract was awarded on April 26,...
This is a definitive contract awarded by the U.S. Forest Service's Region 1 - Northern Region to Bairco Construction Inc., a woman-owned small business and HUBZone-certified construction firm based in Lovell, Wyoming. The $306,668.77 firm-fixed-price contract is for the Cabin Creek Fish Barrier project on the Gallatin National Forest's Hebgen Lake Ranger District. The award was made under the 8(a) sole source program and has an ultimate completion date of October 15, 2015. Bairco Construction is...
Aaecon General Contracting LLC, doing business as Aacon General Contractors, has been awarded a $94,391.40 firm fixed price delivery order against the Great American Outdoors Act Multiple Award Task Order Contract vehicle. The funding agency, the U.S. Department of Agriculture Forest Service Eastern Region, will utilize this order to demolish and dispose of an existing triple concrete box culvert at Grant Creek in Wilmington, Illinois. Work will include removing the bridge structure under the...
This is a federal contract awarded by the U.S. Department of Agriculture's Southern Region (Region 8) to Cove Creek Construction Inc., a veteran-owned small business. The contract, valued at $149,955.00, is for the Cripple Branch Fish Passage Project, which involves the removal of an undersized culvert and the construction of a bottomless aluminum box culvert to promote fish passage upstream. The contract is a delivery order under the Ouachita and Ozark-St. Francis National Forests...
This is a definitive contract awarded by the Operations Center Intermountain, a civilian agency, to Boulder Creek Engineering And Bridge Company, PC, a small business. The contract was awarded on April 16, 2010 with a ceiling value of $44,500.00 and a firm fixed price pricing type. The contract is for the provision of TAS::12 1102::TAS GOOSE LAKE ROAD CATTLEGUARDS, with a final completion date of June 1, 2010. The place of performance is McCall, ID 83638, USA. This contract does not appear to be...
This is a Firm Fixed Price Delivery Order awarded by the U.S. Department of Agriculture Forest Service Pacific Northwest Region to Q. King Trucking & Construction, Inc., a minority-owned and woman-owned small business. The $19,150.00 contract is for the GOAT ROCKS BAER TREATMENT to install a relief culvert on National Forest System Road 4600000 at Milepost 4.9 to convey anticipated increased flows. This work supports the Forest Service's transportation infrastructure and land management...

GOAT CREEK BAER IMPLEMENTATION - CULVERT REMOVAL

Posted 10/27/17, 12:00 AM