Delivery Order 70B01C26D00000006-70B01C26F00000152
- The U.S. Customs and Border Protection (CBP) awarded a $645.9 million firm fixed-price delivery order to Barnard Construction Company, Incorporated for the design and construction of a vertical barrier border wall in the Del Rio, Texas sector (DRT-4). This delivery order, issued on March 5, 2026, is structured under the DHS CBP Southwest Border Construction 2025-2030 indefinite delivery/indefinite quantity contract, which provides CBP with a comprehensive vehicle for infrastructure projects...
- Customs and Border Protection awarded a $617.5 million firm fixed-price delivery order to Barnard Spencer Joint Venture on September 19, 2025, for the construction of 23 miles of border wall system and 81 miles of system attributes, including barbed wire fencing, in Weslaco, Texas. The work is scheduled for completion by April 7, 2028. This delivery order was issued without a set-aside designation under CBP's $4.1 billion multiple-award indefinite-delivery/indefinite-quantity master contract for...
- Customs and Border Protection (CBP) awarded a delivery order valued at $1.37 billion to Fisher Sand & Gravel Co for vertical barrier construction in the Big Bend Texas Sector (BBT-2), with an ultimate completion date of September 5, 2027. The contract, awarded February 13, 2026, is structured as a firm fixed-price delivery order with no set-aside designation, reflecting open competition. Work will be performed in Alpine, Texas, and Fisher Sand & Gravel Co will serve as the prime...
- Customs and Border Protection (CBP) awarded a delivery order valued at $219.5 million to Barnard Spencer Joint Venture for the construction and installation of approximately 60 miles of border detection, lighting, cabling, and related system attributes in Bard, California. The firm fixed-price contract, awarded on September 19, 2025, is scheduled for completion by April 12, 2028, and represents work performed under CBP's larger $4.1 billion Border Infrastructure master contract with the joint...
- This delivery order, valued at $234.84 million on a firm fixed-price basis, was awarded to Barnard Spencer Joint Venture by the Department of Homeland Security's Customs and Border Protection (CBP) on July 18, 2023, for border infrastructure construction in Tucson, Arizona. The contract was terminated in March 2024 pursuant to a court injunction under the termination for convenience of the government clause. The award was made without a set-aside designation and was ultimately scheduled for...
- Customs and Border Protection (CBP) awarded a $874.2 million delivery order to Bccg A Joint Venture on September 24, 2025, for the construction of a border barrier wall system in Weslaco, Texas. This firm fixed-price delivery order, with an ultimate completion date of October 31, 2028, operates under CBP's broader Border Infrastructure Indefinite-Delivery/Indefinite-Quantity (IDIQ) contract valued at $4.1 billion. The award was made on an unrestricted, fully competitive basis with no set-aside...
- The U.S. Department of Homeland Security's Customs and Border Protection (CBP) awarded a delivery order valued at $368.48 million to Bccg A Joint Venture for border barrier construction and tiered pricing revisions at the Weslaco, Texas location. This delivery order, issued under the larger Border Infrastructure Indefinite-Delivery/Indefinite-Quantity (IDIQ) contract valued at $4.1 billion, represents the continuation of CBP's strategic border security infrastructure development initiatives. The...
- This is a definitive, firm-fixed-price contract awarded by the U.S. Army Corps of Engineers (USACE) to Barnard Construction Company, Incorporated, a large heavy civil construction firm based in Bozeman, Montana. The $413,297,776 contract is for the design and construction of a 33-mile pedestrian fence replacement project in the Yuma Sector of Arizona. The contract has no set-aside designation and was awarded on November 13, 2018, with a completion date of March 14, 2020. Barnard Construction...
- U.S. Customs and Border Protection (CBP), a civilian agency within the Department of Homeland Security, awarded a $572.7 million Firm Fixed Price delivery order to Bccg A Joint Venture for construction of border barrier infrastructure in Weslaco, Texas. The delivery order is scheduled for completion by March 30, 2028, and was awarded without set-aside provisions on an unrestricted, competitive basis. Bccg A Joint Venture, a for-profit partnership based in Montgomery, Alabama, specializes in...
- The Department of Homeland Security Customs and Border Protection (DHS CBP) awarded a $22.6 million firm fixed price delivery order to Texas Sterling Construction Company under the Concrete Border Wall Prototype indefinite-delivery/indefinite-quantity master contract. Texas Sterling Construction will provide border construction services for DHS CBP in Doña Ana, New Mexico, with performance taking place between September 1, 2022 and May 12, 2024. The delivery order is for continued border wall...
- 70B01C26D00000006Indefinite Delivery Contract
- 70B01C26D00000006-70B01C26F00000152Delivery Order
Customs and Border Protection (CBP) awarded a delivery order valued at approximately $1.1 billion to Barnard Construction Company, Incorporated for border barrier construction in Hudspeth County, Texas, with an ultimate completion date of August 31, 2028. The contract, awarded on March 5, 2026, utilizes firm fixed-price pricing and carries no set-aside designation. The work will be performed in Sierra Blanca, Texas and falls under the DHS CBP Southwest Border Construction 2025-2030 parent vehicle, which provides CBP with comprehensive construction services to support Southwest Border infrastructure modernization and security initiatives. Barnard Construction Company, a large heavy civil construction firm headquartered in Bozeman, Montana, brings substantial experience to this engagement. The company holds the $3.364 billion indefinite delivery/indefinite quantity contract with CBP awarded in October 2025, from which this delivery order is issued, and maintains additional major indefinite delivery contracts including a $7 billion agreement with the U.S. Army Corps of Engineers and a $1 billion contract with Naval Facilities Engineering Command. Barnard's recent project portfolio demonstrates proven capacity in large-scale federal infrastructure delivery, including dam modifications, spillway projects, and border security infrastructure, with prime contract experience exceeding $2.3 billion in recent years.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $1.0b | 3/4/26 |