Project NP indu 0945(1): the project consists of removal and replacement of curb and gutter, removal and replacement of concrete sidewalk, milling asphalt pavement, structural excavation, structural…

Active Awarded Last action

Contract number
693C7323F00049N
Awardee
Awarding agency
Obligated
$2,753,837

Award facts

Opportunity
  • 693C7323R000011 Solicitation number
Contract value 100% obligated
$2,753,837.00 Current and potential, with all options
Completion date 75% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Gary, IN 46403, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00004 · NP-indu 0945(1) - CM #4: 693C7320D000024/693C7323F00049N the purpose of this no cost contract modification is to: 1) extend the period of performance for… $0
Funding Only Action P00003 · NP-indu 0945(1) 693C7320D000024/693C7323F00049N CM #3 increase contract amount by $9,032.07 no change to contract time $9,032
Funding Only Action P00002 · NP-indu 0945(1) 693C7320D000024/693C7323F00049N CM #2 decrease contract amount by $9,032.07 no change to contract time -$9,032
Other Administrative Action P00001 · NP-indu 0945(1) 693C7320D000024/693C7323F00049N CM #1 no change to contract amount no change to contract time extend period of performance to december 31, 2026 $0
Original award $2,753,837

About this award

The Federal Highway Administration awarded a delivery order to John Cecil Construction, LLC on April 25, 2023, with a $2.75 million ceiling value, for Project NP INDU 0945(1) and replacement of the Paul H. Douglas Center pedestrian bridge. The order is firm-fixed-price, was issued without a set-aside, and is performed in Gary, Indiana, 46403.

Scope includes removal and replacement of curb, gutter, and concrete sidewalk; milling of asphalt pavement; structural excavation and concrete; prefabricated steel truss work; and asphalt concrete placement, along with replacement of the pedestrian bridge. Contract Modification 4, a no-cost action, extended the period of performance to December 31, 2027, and all other terms remain unchanged. The prime holds Veteran-Owned Small Business and SBA 8(a) certifications and is also certified as minority-owned, a self-certified small disadvantaged business, a DOT-certified DBE, and HUBZone.

Description

Project NP indu 0945(1): the project consists of removal and replacement of curb and gutter, removal and replacement of concrete sidewalk, milling asphalt pavement, structural excavation, structural concrete, prefabricated steel truss, asphalt concr

Quick answers

Who was awarded contract 693C7323F00049N?

693C7323F00049N was awarded to John Cecil Construction, LLC by Federal Highway Administration (Department of Transportation) on April 25, 2023.

How much is contract 693C7323F00049N worth?

The government has obligated $2,753,837 on 693C7323F00049N.

Is contract 693C7323F00049N an order under another contract?

Yes. 693C7323F00049N is a delivery order under 693C7320D000024, an indefinite delivery contract.

Was contract 693C7323F00049N competed?

The extent of competition for 693C7323F00049N was full and open competition.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award