Delivery Order 69056719D000003-69056722F00110N
- Not listed
- This federal contract was awarded by the Department of Transportation Federal Highway Administration (FHWA) to Oftedal Construction, Inc., a for-profit construction company. The contract is a delivery order under the Yellowstone, Grand Teton, and Surrounding Area 2014-2019 indefinite delivery, indefinite quantity (IDIQ) contract, with a firm fixed price of $43,328,477.58. The contract scope includes road construction, repair, and rehabilitation work on the East Entrance Road in Yellowstone...
- The Department of Transportation Federal Highway Administration awarded a $3.5 million firm fixed price delivery order contract to Oftedal Construction, Inc. for work at Yellowstone National Park. Under the contract, Oftedal Construction will repave the Roosevelt Lodge parking lot, located at Yellowstone National Park in Wyoming. As the prime contractor, Oftedal Construction will perform the work directly. Funding comes from the Federal Highway Administration to support infrastructure...
- The Department of Transportation Federal Highway Administration awarded a $30,000 delivery order contract to Oftedal Construction, Inc. for road construction services in Yellowstone National Park, Wyoming. Under the contract, Oftedal Construction will complete Phase 3 of the Norris to Golden Gate road project in Yellowstone National Park between January 29, 2021 and April 15, 2021. As a firm fixed price contract, Oftedal Construction will provide road construction services for a set price. The...
- This is a firm fixed price contract awarded by the Department of Transportation Federal Highway Administration (FHWA) to the prime contractor Oftedal Construction, Inc., a for-profit construction company. The contract, titled "WY FLAP US212(8) BEARTOOTH HIGHWAY," is for road construction, repair, and rehabilitation work to be performed in Yellowstone National Park, Wyoming. The contract was awarded on March 28, 2017 with a completion date of August 18, 2019, and has a potential value...
- The Federal Highway Administration (FHWA) awarded a $46.9 million fixed-price delivery order contract to H-K Contractors, Inc. for road rehabilitation work on the Grand Loop Road between Old Faithful and West Thumb in Yellowstone National Park, Wyoming. The project scope encompasses core drilling, milling, sub-excavation, and paving work to address frost heave damage, along with associated warranty work. This delivery order was issued under H-K Contractors' existing Multiple Award Task Order...
- This is a $19,059,297.50 fixed-price delivery order contract awarded by the Federal Highway Administration (FHA), an agency within the U.S. Department of Transportation, to H-K Contractors, Inc. for emergency road repairs on the Old Gardiner Road in Yellowstone National Park. The contract has a period of performance through May 2023 and does not utilize any set-aside designations. H-K Contractors is a for-profit construction firm that has extensive experience performing infrastructure projects...
- This is a $37,689,772.53 fixed price with economic price adjustment delivery order contract awarded by the Department of Transportation Federal Highway Administration to H-K Contractors, Inc., a for-profit construction company. The contract is for the completion of Phase 2 of the WY PRA YELL 10(19) Grand Loop Road project, which involves road construction and rehabilitation work within Yellowstone National Park. No set-aside designation was used. H-K Contractors utilized several subcontractors...
- This is a firm fixed price delivery order contract awarded by the Federal Highway Administration (FHWA), a civilian agency, to M.A. Deatley Construction, Inc. for emergency structural bridge deck repairs on the Madison River Bridge in Yellowstone National Park. The contract has a ceiling value of $34,070,787.63 and a completion date of November 7, 2025. No set-aside was used. Major subcontractors include Poteet Construction Inc., which will provide curb, gutter, sidewalk, concrete, and traffic...
- H-K Contractors, Inc. was awarded a $25.8 million firm fixed price delivery order against the National Park Service's indefinite delivery/indefinite quantity contract for road and trail construction and improvements in Yellowstone National Park, Wyoming. The prime contractor and seven major subcontractors will perform work including clearing, grubbing, mulching, installing curb and gutter, concrete work, pavement markings and striping, fencing, milling, and masonry tasks. The Department of...
- The Department of Transportation Federal Highway Administration awarded a $12.4 million firm fixed price contract to H-K Contractors, Inc. to perform improvements at the North Entrance of Yellowstone National Park in Montana. The solicitation sought offers for construction services including renovating entrance facilities, widening approximately 12 miles of roadways, and performing earthwork. Major subcontractors include Poteet Construction Inc. for concrete work and traffic control, Highmark...
- 69056719D000003Indefinite Delivery Contract
- 69056719D000003-69056722F00110NDelivery Order
This is a $25,184,950.39 fixed price redetermination delivery order contract awarded by the Federal Highway Administration, a civilian agency, to Oftedal Construction, Inc. for road repairs and rehabilitation at Yellowstone National Park. The contract does not have a set-aside designation. Major subcontractors include Fisher Sand & Gravel Co. for drilling and blasting, H-K Contractors, Inc. for asphalt paving, and other vendors providing services like hauling, seeding, masonry, pavement marking, and traffic control. This contract is part of a larger indefinite delivery indefinite quantity vehicle from the Federal Highway Administration for up to $350 million in road construction and rehabilitation projects at Yellowstone and Grand Teton National Parks.
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
WY ERFO NP YELL 2022-1(212) YELLOWSTONE NP NORTHEAST ENTRANCE ROAD REPAIRS, PHASE 1 | 69056722F00110N | Department of Transportation Federal Highway Administration | Limited / Sole Source Justification 1/1 | 7/27/22, 7:34 PM |
ContractNumber | Description | Subcontractor | Prime Award | Dollars Obligated | Updated At |
|---|---|---|---|---|---|
2202810123S | Fisher Sand & Gravel Co | Delivery Order 69056719D000003-69056722F00110N | $174.7k | 8/15/23 | |
2202812570S | Iron Spur Enterprise Co | Delivery Order 69056719D000003-69056722F00110N | $900.0k | 1/26/23 | |
2202810752S | Hinckley James Inc. | Delivery Order 69056719D000003-69056722F00110N | $130.4k | 10/13/22 | |
2202811537S | Highmark Traffic Services, Inc. | Delivery Order 69056719D000003-69056722F00110N | $20.3k | 9/20/22 | |
2202810172S | H-K Contractors, Inc. | Delivery Order 69056719D000003-69056722F00110N | $1.8m | 9/20/22 |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00017 | Close Out | ($3m) | 4/4/25 | |
| P00016 | Supplemental Agreement for work within scope | $0 | 7/1/24 | |
| P00015 | Supplemental Agreement for work within scope | $0 | 10/27/23 | |
| P00014 | Supplemental Agreement for work within scope | $0 | 10/27/23 | |
| P00013 | Supplemental Agreement for work within scope | $0 | 10/23/23 |