This project is to upgrade existing egress lighting and provide emergency power for egress lighting, existing elevators, and other loads such as basement lift pumps at the GHW & GW bush & g. Mahon…
Active Awarded Last action
- Contract number
- 47PH0925F0003
- Awardee
-
A.r.e. Design & Build, LLC UEI PFFLN9MQXJD9
- Awarding agency
-
Region 7
Public Buildings Service, General Services Administration
- Obligated
- $799,639
Award facts
- Opportunity
-
- 47PH0924R0051 Solicitation number
- Contract value 100% obligated
- $799,638.64 Current and potential, with all options
- Completion date 95% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Set-aside
- Total Small Business
- Competition
- Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
- Pricing
- Firm Fixed Price
- Place of performance
- Midland, TX 79701, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
- Service Contract Inventory FAR subpart 4.17
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $38,898 | |
| Other Administrative Action | $0 | |
| Original award | $760,741 |
About this award
GSA Region 7 issued a delivery order to A.R.E. Design & Build, LLC, a HUBZone-certified small business, on November 13, 2024, with a ceiling value of $799,638.64 under Total Small Business set-aside for egress lighting upgrades and emergency power installation at the George H.W. Bush and George W. Bush U.S. Courthouse in Midland, Texas. The work includes upgrading existing egress lighting, providing emergency power for egress lighting and elevators, and powering basement lift pumps. Place of performance is Midland, TX 79701. Ultimate completion date is November 27, 2026. The order is firm fixed price.
SCI reporting for FY2025 shows $4 thousand invoiced with 0.0 FTEs, with self-performance and no subcontractor engagement.
Description
This project is to upgrade existing egress lighting and provide emergency power for egress lighting, existing elevators, and other loads such as basement lift pumps at the GHW & GW bush & g. Mahon federal courthouse, 100 east wall ST, midland, TX
Quick answers
Who was awarded contract 47PH0925F0003?
47PH0925F0003 was awarded to A.r.e. Design & Build, LLC by Region 7 (Public Buildings Service) on November 13, 2024.
How much is contract 47PH0925F0003 worth?
The government has obligated $799,639 on 47PH0925F0003.
Is contract 47PH0925F0003 an order under another contract?
Yes. 47PH0925F0003 is a delivery order under 47PH0820D0003, an indefinite delivery contract.
Was contract 47PH0925F0003 competed?
The extent of competition for 47PH0925F0003 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award