Delivery Order 47PF0019D0065-47PF0021F0390
- This firm fixed-price delivery order was awarded by the General Services Administration Public Buildings Service Region 5 to Lawdensky Construction Company Incorporated, a family-owned construction firm, to install new carpet and vinyl base, and paint walls and doors on the second floor, mezzanine, and eleventh floor of the McNamara Federal Building in Detroit, Michigan. The contract, valued at $186,568.00, has a completion date of December 29, 2021 and was not set aside for any specific...
- The Administrative Office of the U.S. Courts awarded a $35,463.01 firm fixed price delivery order to DCR Services & Construction Inc. under the Repair and Alterations MI-MN-WI 2019 master indefinite-delivery/indefinite-quantity contract. The order is for installing new sink, wall and base cabinets, countertop, towel and soap dispensers, flooring tile and base in the Clerk of Courts breakroom at the Ford Federal Building in Grand Rapids, Michigan. Work will be performed at the specified...
- The Administrative Office of the U.S. Courts awarded a $24,612 firm fixed price delivery order to Lawdensky Construction Company Incorporated. The order is for electrical and data upgrades including floor boxes for power and data at the Everett Dirkssen Federal Courthouse in Chicago, Illinois. Upgrades are needed to accommodate an impending furniture move coordinated by the requiring agency. No set aside designation or subcontractors are indicated. The Administrative Office manages space and...
- This is a firm fixed-price delivery order awarded by the General Services Administration Public Buildings Service Region 5 to Lawdensky Construction Company Incorporated for $79,760.00 to provide construction services for the replacement of lighting fixtures in Office 2060 at the Everett M. Dirksen U.S. Courthouse in Chicago, Illinois. The work is scheduled for completion by March 10, 2024. Lawdensky Construction Company Incorporated is a for-profit construction firm that has been awarded over...
- This is a firm fixed-price delivery order contract awarded to Lawdensky Construction Company Incorporated, a for-profit construction firm based in Schaumburg, Illinois. The contract is for the replacement of carpeting at the Judge Pepper Federal Building and U.S. Courthouse in Milwaukee, Wisconsin. The contract has a ceiling value of $137,064.00 and a completion date of May 16, 2025. It was awarded on December 12, 2024 by the Administrative Office of the U.S. Courts, a civilian federal agency....
- This firm-fixed-price delivery order was awarded by the U.S. Marshals Service to Lawdensky Construction Company Incorporated, a for-profit construction firm, to relocate the fire alarm annunciator panel at the Dirksen Courthouse in Chicago, Illinois. The $110,251.00 contract has a completion date of March 3, 2025 and was not set aside for any small business category. Lawdensky Construction is a family-owned construction company that has executed over 50 federal contracts since 2019, primarily in...
- Lawdensky Construction Company Incorporated, a small business contractor based in Schaumburg, Illinois, was awarded a $118,207.92 firm fixed-price delivery order on August 14, 2025, to replace lighting on the 14th floor of the Everett McKinley Dirksen U.S. Courthouse located at 219 South Dearborn Street in Chicago, Illinois. The contract is designated as a total small business set-aside and is expected to be completed by September 14, 2026. This delivery order is issued under the GSA Region 5...
- Lawdensky Construction Company Incorporated has been awarded a firm fixed price delivery order valued at fifteen thousand fifty-one dollars by the Administrative Office of the U.S. Courts. The contract calls for repair and refinishing work on the seventeenth floor of the Dirksen Courthouse located in Chicago, Illinois, including replacement of an existing door jamb, trim, and finishes, refinishing of an existing door panel, and reinstallation of door hardware. The prime contractor will paint and...
- This is a firm fixed-price delivery order contract awarded by the U.S. Marshals Service, a civilian federal agency, to Lawdensky Construction Company Incorporated, a for-profit construction firm, for the U.S. Marshals Service Lobby Security Renovation Project at the Birch Bayh Federal Building & U.S. Courthouse in Indianapolis, Indiana. The contract has a ceiling value of $1,211,944.83 and a completion date of November 29, 2024. Lawdensky Construction is a family-owned construction company...
- The Administrative Office of the U.S. Courts awarded a $44,079 firm fixed price delivery order against its Repair and Alterations MI-MN-WI 2019 master IDIQ contract to Advantage Mechanical-Refrigeration, Inc. for Judge Jonker Courtroom Infrastructure Upgrades at the Gerald R. Ford Federal Building and U.S. Courthouse in Grand Rapids, Michigan. This total small business set-aside order is for courtroom infrastructure upgrades and will be performed by Advantage Mechanical Refrigeration in Grand...
- Repair and Alterations MI-MN-WI 2019Master IDIQ
- 47PF0019D0065Indefinite Delivery Contract
- 47PF0019D0065-47PF0021F0390Delivery Order
The Lawdensky Construction Company Incorporated was awarded a $8,800 firm fixed price delivery order against the Repair and Alterations MI-MN-WI 2019 master IDIQ contract to perform miscellaneous electrical work at the Ford Federal Building in Grand Rapids, Michigan for the Administrative Office of the U.S. Courts. Specifically, the contractor will add electrical floor boxes under a conference room table and power/data boxes to the conference table in the operations area. The work is to be completed between February 4, 2021 and July 2, 2021 at the place of performance in Grand Rapids. The master IDIQ was awarded by the Administrative Office of the U.S. Courts to provide repair and alteration services across Michigan, Minnesota, and Wisconsin courthouses.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $8.8k | 2/10/21 |