Fire pump installation

Ended Awarded Last action

Contract number
47PM0321F0042
Awardee
Awarding agency
Obligated
$163,404

Award facts

Opportunity
  • 47PM0321Q0032 Solicitation number
Contract value 82% obligated
  • $163,404.00 Current, with exercised options
  • $200,133.00 Potential, with all options
Completion date 100% complete
  • Current, with exercised options
  • Potential, with all options
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Washington, DC 20024, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS0012 · Liberty loan fire pump installation ncte extending this contract from 11/28/2023 to 1/28/2024. $0
Supplemental Agreement for work within scope PS0011 · Ncte to 11/28/2023. $0
Supplemental Agreement for work within scope PS0010 · Contract number 47PM0321F0042 to provide construction services for the fire pump design at the liberty loan building for GSA is hereby modified to extend the… $0
Change Order PS0009 · No cost modification to extend the POP and add additional funds. The contract overall value will increase by $15,209.00 from $148,195.00 to $163,404.00. The… $15,209
Other Administrative Action PA0008 · Changing the contract officer from kimberly travis to marquida gaskins $0
Supplemental Agreement for work within scope PS0007 · No cost time extension for 90 days from 11/28/2022 to 2/28/2023. $0
Other Administrative Action PA0006 · Change CO from brigette young to kimberly travis. $0
Other Administrative Action PA0004 · Liberty loan fire pump installation $0
Supplemental Agreement for work within scope PS0003 · Extend performance completion date from 09/28/2022 to 11/28/2022. $0
Supplemental Agreement for work within scope PS0002 · Extend POP from 02/28/2022 to 09/30/2022 at no cost due to effectively complete the design of the water pump. $0
Original award $148,195
Show all 11

About this award

The General Services Administration awarded a firm-fixed-price delivery order valued at $200,133.00 to EBL Engineers, LLC, a limited liability company doing business as EBL Fire Engineering, for fire pump installation at Fort Lesley J. McNair in Washington, D.C. EBL Engineers is a for-profit organization that specializes in mechanical, electrical, and fire protection engineering services. This contract award has no set-aside designation. EBL Engineers holds several multi-million dollar indefinite delivery vehicle (IDV) contracts with various federal agencies, including the Department of the Air Force, Department of State, Environmental Protection Agency, Department of the Interior, and Department of the Treasury, to provide architectural, engineering, and fire protection services.

Quick answers

Who was awarded contract 47PM0321F0042?

47PM0321F0042 was awarded to EBL Engineers, LLC by National Capital Region (Public Buildings Service) on September 24, 2021.

How much is contract 47PM0321F0042 worth?

The government has obligated $163,404 on 47PM0321F0042. Its potential value, with all options, is $200,133.

Is contract 47PM0321F0042 an order under another contract?

Yes. 47PM0321F0042 is a delivery order under 47PF0019D0050, an indefinite delivery contract.

Was contract 47PM0321F0042 competed?

The extent of competition for 47PM0321F0042 was full and open competition after exclusion of sources. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award